Running head/management
1
Management assignment
Name
Institution
Date
Running head/management
Activity
2
Immediate
optimistic
Most likely
Pessimistic
predecessor
A
--
12
16
25
B
--
7
14
22
C
--
5
10
14
D
A
15
18
25
E
C
8
12
18
F
B
9
12
15
G
F
18
22
29
H
D, E. G
15
19
27
1 Draw an AON network for this project
A
D
C
E
B
G
F
Critical path
.
2 Compute the expected time estimate (te) for all activities.
H
Running head/management
3
Expected time= (a+4m+b)/6
A (12+16*4+25)/6= 16.8
B (7+14*4+22)/6= 14.2
C 5+4*10+14)/6= 9.8
D 15+4*18+25)/6= 18.7
E 8+4*12+18)/6= 12.3
F 9+4*12+15)/6= 12
G 18+4*22+29)/6= 22.5
H 15+4*19+27)/6= 19.7
3 Conduct a forward pass to compute early start and early finish times, and time
E.F =E.S+DURATION
4
Conduct a backward pass to compute late start and late finish times.
L.S= L.F-DURATION
5 Compute activity slacks.
SLACK= L.S.T-E.S.T
Activity
E.S.T
E.F.T
L.S.T
L.F.T
Duration
SLACK
Variance
A
0
16.8
0
30
16.8
0
4.7
B
0
14.2
0
14.2
14.2
0
6.3
C
0
9.8
0
36.4
9.8
0
2.3
D
16.8
48.7
30
48.7
18.7
13.2
2.8
E
9.8
...