how do you determine the ES, LS, EF, and LF for each activity?

Jul 6th, 2015

Thank you for the opportunity to help you with your question!

Computing Earliest Times

Step 1. Mark “start” node: ES=EF=0.

Step 2. Repeatedly do this until finishing all nodes:

For a node whose immediate predecessors are all marked, mark it as below:

ES = Latest EF of its immediate predecessors,

EF = ES + t

Note: EF=ES at the Finish node.

Computing Latest Times:

Step 1. Mark “Finish” node:

LF = LS = EF of “Finish” node.

Step 2. Repeatedly do this until finishing all nodes:

For a node whose immediate children’s are all marked with LF and LS, mark it as below:

LF = Earliest LS of its immediate children,

LS = LF – t

Note: LS=LF at Start node.


Please let me know if you need any clarification. I'm always happy to answer your questions.
Jul 6th, 2015

did the answer help you?

Jul 6th, 2015

Are you studying on the go? Check out our FREE app and post questions on the fly!
Download on the
App Store
...
Jul 6th, 2015
...
Jul 6th, 2015
Dec 4th, 2016
check_circle
Mark as Final Answer
check_circle
Unmark as Final Answer
check_circle
Final Answer

Secure Information

Content will be erased after question is completed.

check_circle
Final Answer