Description
See the attached file
Example :
- A diaper making company has opened a cloth diaper service. Company is interested in simulating the number of diapers required for a one-year- old. It hopes to use this data to show the cost effectiveness of cloth diapers. The table below shows the number of diapers demanded daily and the cumulative probabilities associated with each level of demand.
- Find the missing values and .
- Find the probability of each of daily demand?
- If the random number 35 were generated for a particular day, what would be the simulated demand for that day?
Daily Demand
Cumulative Probability
Interval of
Random Numbers
3
0.10
01-10
4
0.35
11-35
5
36-60
6
0.90
61-90
7
91-00
Answer the following Essay Type Questions: (6×3 = 18 marks)
Q. 1 An automobile parts manufacturer produces two types of automobile parts used for making four wheelers. Type 1 requires ½ hour of labor and 1 hour of machine time. Type 2 requires 1 hour of labor time and 2 hours of machine time. There are 500 hours available per week of labor and 700 machine hours available. Type 1 has a profit margin of $ 35 a unit and Type 2 have a profit margin of $ 50 a unit. The automobile parts manufacturer must choose the quantity of Type 1 and Type 2 machinery parts, which maximizes profit. Formulate this as a linear programming problem by defining the objective function and the constraints.
¡Q.2 The Kenneth State organization sells a product for which the annual demand is 5000 units.
The average holding cost is $ 1.00 per unit per year, and the ordering cost is $ 100 per order.
a) What is the economic order quantity for the product?
b) What is the total annual cost for this EOQ?
Unformatted Attachment Preview
Purchase answer to see full attachment

Explanation & Answer

q-2 & q-3...ARE REMAINING.wILL POST WITHIN 10 HRS
Answer the following Essay Type Questions:
(6×3 = 18 marks)
1. Consider the project with the following estimates for the activity times andprecedence
relationships:
Activity
A
B
C
D
E
F
G
H
Optimistic
Time (a)
3
5
2
2
1
3
7
2
Most
Pessimistic
Likely Time(m) Time (b)
4
5
7
9
3
10
5
8
7
7
5
7
8
9
6
10
Immediate
Predecessor(s)
----A
B
B
C, D
D, E
F
Draw the PERT network associated with the activities and calculate expected time and
variance corresponding to each activity.
Solution:
Path
A-CF-H
B-DF-H
Activity
A
C
F
H
B
D
F
H
to
3
2
3
2
5
2
3
2
tm
4
3
5
6
7
5
5
6
tp
5
10
7
10
9
8
7
10
te=(to+4tm+tp)/6
4
4
5
6
7
5
5
6
Path
total
19
23
B-EG
B
E
G
5
1
7
7
7
8
9
7
9
7
6
8
21
2. Using the data given in Q.1, answer the following questions:
(a) What is the expected duration of the project?
(b) What is the project variance?
(c) If the deadline of the project is 25 days, what is the probability of finishing the
project on time?
Solution:
3. The following Table represents a project with known activity times. All times are in
weeks.
Activity
A
B
C
D
E
F
G
Immediate
Predecessor
--A
B
C, D
B
E, F
Time
4
3
2
7
4
5
4
Construct the network for this problem and determine the earliest start, earliest finish, latest
start, latest finish and slack time for each activity.
Solution:
4. Calculate the probability of occurrence,cumulative probability and interval of
random numbers for the following data, hence complete the table
Demand
Frequency
Probability
Cumulative
Interval of Random
of
Occurrence
0
1
2
3
4
5
Probability
Numbers
10
30
20
60
40
50
Demand
Frequency
0
1
2
3
4
5
Total
10
30
20
60
40
50
210
Solution:
Probability of
Occurrence
0.0476
0.1429
0.0952
0.2857
0.1905
0.2381
Cumulative
Probability
0.0476
0.1905
0.2857
0.5714
0.7619
1.0000
Interval of Random
Numbers
00-04
05-19
20-28
29-57
58-76
77-100
5. The number of machine breakdowns in a day is 0, 1, or 2, with the probabilities 0.6,
0.3, and 0.1, respectiv...
