Description
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take?
ID.....Description.......Predecessor....Time (days)
A......Survey site..............None......2
B....Install drainage..........A......5
C....Install power lines......A.....3
D....Excavate site........ B, C..... 4
E....Pour foundation........D...... 3
I NEED YOU HELP ASAP
note: i found the solution in internet but my instructor return it to me and gave me ZERO and ask me to redo it in 6 hours
Explanation & Answer
Review
Review
24/7 Homework Help
Stuck on a homework question? Our verified tutors can answer all questions, from basic math to advanced rocket science!
Similar Content
Related Tags
Becoming
by Michelle Obama
The Hobbit
by J. R. R. Tolkien
The Joy Luck Club
by Amy Tan
We Were Eight Years in Power
by Ta-Nehisi Coates
Big Little Lies
by Liane Moriarty
Shattered - Inside Hillary Clintons Doomed Campaign
by Amie Parnes and Jonathan Allen
Sounds Like Titanic
by Jessica Chiccehito Hindman
How to Win at the Sport of Business
by Mark Cuban