Assume that you have completed three months of the project. The BAC was $120,000 for this six-month project. You can also make the following assumptions:

  1. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?
  2. How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?
  3. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing better or worse than planned?
  4. Use the SPI to estimate how long it will take to finish this project.
  5. Sketch an earned value chart using the information from your answers to parts a through d. Use Figure 7-6 as a guide.

Unformatted Attachment Preview

Cengage MindTap - Cengage learning Sack a new question - Studypool X X $ & → e https://ng.cengage.com/static/nb/ui/evo/index.html?dockAppUid-168LeISBN-9781337'1011008lid-1161771078/nbld-'10989788lsnapshotld-'109897881 Apps Ilawkes Learning N General... o Lublin Q Isaac use of force fl... Q Chapter 9 Ilomewo... M Inbox - soud.alsabil... BL Welcome, Saud-BL... Q MIRCO TINAL Flash... CENGAGE MINDTAP Search this course • saud Full Book 器 其 Chapters AAA ? 3 P Assume that you have completed three months of the project. The BAC was $120,000 for this six-month project. You can also make the following assumptions: O M PV - $60,000 EV = $55,000 AC = $50,000 A-Z d. What is the cosi variance, schedule variante, cost performance index (CPI), and schedule performance index (SPI) for the project? | سبع 11 Over < 11. How is the project doiny? is il ahead of schedule on behind schedule? Is il under bullyel C. Use the CPI to calculate the estimate at completion (EAC) for this project. Is the project performing heller om Worse than plannel? d. Use the SPI to estimate how long it will take to finish this project. e. Sketch an earned value chart using the information from your answers to parts a through d. Use Figure 7-6 as a guide. gi A] * CNG 4:43 PM 4/6/2019 Estimate at completion (EAC) 120,000 Budget at completion (BAC) 100,000 An EAC point above and to the right of the BAC point means the project is projected to cost more and take longer than planned. 80,000 Planned value (PV) $ 60,000 Actual cost (AC) 40,000 Earned value (EV) 20,000 T T T 1 2 3 4 5 8 9 10 11 12 13 6 7 Month --- Actual cost (AC) Planned value (PV) Earned value (EV)
Purchase answer to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Hello,Attached find the c...


Anonymous
Excellent! Definitely coming back for more study materials.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4

Related Tags