Jeff takes 5hrs longer to build a fence than it takes Bill. When they work together, it takes them 6hrs.  How long would it take Bill to do the job alone?

Oct 22nd, 2015

Thank you for the opportunity to help you with your question!

Bill does work of the fence per hour = 1/B
Jeff does 1/J per hour, = 1/(B+5)
Together, they do 1/6 per hour. 

1/B + 1/(B+5) = 1/6
B+5 + B = (1/6)*B*(B+5)
12B + 30 = B^2 + 5B
B^2 - 7B - 30 = 0
(B-10)*(B+3) = 0
B = 10 hours
J = 15 hours

Please let me know if you need any clarification. I'm always happy to answer your questions.
Oct 22nd, 2015

Did you know? You can earn $20 for every friend you invite to Studypool!
Click here to
Refer a Friend
...
Oct 22nd, 2015
...
Oct 22nd, 2015
Oct 21st, 2017
check_circle
Mark as Final Answer
check_circle
Unmark as Final Answer
check_circle
Final Answer

Secure Information

Content will be erased after question is completed.

check_circle
Final Answer