Description
Submit (attach) your WORD file for the homework 2 problems from Chapters 13 and 14 here.
You must attach a WORD file that I can print to grade. Handwritten jpeg or scanned files will NOT be accepted. Note that you may copy formulas/problems from the WORD files that I have provided in the lecture notes (or the homework solutions) and substitute your numbers to save some typing time. Show your detailed work and formulas if you submit an EXCEL file. I will not be able to dig out the formulas in your spread sheet cells as I may print the submissions to grade
Homework 2 Assignment: Submit the attached Homework 2 Problems from Chapters 13 and 14 in Assignments. Due date: Tuesday 04/30/19, 11:55 pm.
This homework is an individual assignment. PLEASE make sure to include your name on top of your submission and DO NOT provide your work in the text box. Note that you must show details of all calculations and provide complete answers to receive ANY credit. Just providing the answers, without any supporting work, will not graded and will not get any credit.
I am giving you almost 18 days to complete homework. You must attach a WORD or EXCEL file that I can print to grade. Handwritten jpeg or scanned files will NOT be accepted. Note that you may copy formulas/problems from the WORD files that I have provided in the lecture notes (or the homework solutions) and substitute your numbers in it. This will save you typing time, would keep your file neat, and it would be easier for me to check your work. Show your work and formulas completely if you submit an EXCEL file. I will not take the responsibility to dig out the formulas as I may print the submissions to grade.
Unformatted Attachment Preview
Purchase answer to see full attachment
Explanation & Answer
Attached.
Running head: HOMEWORK PROBLEMS-CHAPTERS 13 & 14
Homework Problems-chapters 13 & 14
Nate Dowdy
MGMT339.WB2 Class
4/24/2019
HOMEWORK PROBLEMS-CHAPTERS 13 & 14
2
Homework 2 Problems – Chapters 13 and 14
Problem 1 (20 points): The CPM network below represents a project with the estimated times in
weeks
B,
10
C,
9
D,
8
A, 3
G,
9
E, 6
F,
7
Solution
Activity
Predecessor
A
B
C
D
E
F
G
H
A
A,B
A
A
D,E
C,F
G
ES= Early start, the earliest date that the task can start.
Duration
(Weeks)
3
10
8
8
6
7
9
6
H,
6
HOMEWORK PROBLEMS-CHAPTERS 13 & 14
3
EF= Early finish, the earliest date that the task can finish.
LS= Latest start, the latest date that the task can start.
LF= Latest finish, the latest date that the task can finish.
Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish
without delaying the project. The critical path is the path through the project network...