Description
1. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?
Answer:
(AC = 650) - (EV = 600) - (PC = 560)
CV (Cost Variance) = (EV – AC) = (600 – 650) = (-50).
SV (Schedule Variance) = (EV – PV) = (600 – 560) = (40).
CPI (Cost performance index) = (EV ÷ AC) = (600 ÷ 650) = (0.92).
i need to paraphrase it depend on the solutionMy assessment would be that the project is over budget (as indicated by negative CV). However, since SV is positive, it indicates that project is on schedule. A CPI of .92 indicates that the cost of completing the project is higher than planned which is a bad condition.
Explanation & Answer
Review
Review
24/7 Study Help
Stuck on a study question? Our verified tutors can answer all questions, from basic math to advanced rocket science!
Similar Content
Related Tags
Little Women
by Louisa May Alcott
East of Eden
by John Steinback
The King Must Die
by Mary Renault
Breakfast at Tiffanys
by Truman Capote
Frankenstein
by Mary Shelley
The Girl With The Dragon Tattoo
by Stieg Larsson
Where'd You Go Bernadette
by Maria Semple
Rules Of Civility
by Amor Towles
The Color Purple
by Alice Walker