1.  On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?

Answer:

(AC = 650) - (EV = 600) - (PC = 560)

CV (Cost Variance) = (EV – AC) = (600 – 650) = (-50).

SV (Schedule Variance) = (EV – PV) = (600 – 560) = (40).

CPI (Cost performance index) = (EV ÷ AC) = (600 ÷ 650) = (0.92).

i need to paraphrase it depend on the solution 


My assessment would be that the project is over budget (as indicated by negative CV). However, since SV is positive, it indicates that project is on schedule. A CPI of .92 indicates that the cost of completing the project is higher than planned which is a bad condition.


Tutor Answer

(Top Tutor) Studypool Tutor
School: Rice University
PREMIUM TUTOR

Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1827 tutors are online

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors