Calculate the NPV for each project and determine which project should be accepted.

Anonymous
timer Asked: May 25th, 2019
account_balance_wallet $10

Question Description

Calculate the following problems using Microsoft® Excel®:

  • Calculate the NPV for each project and determine which project should be accepted.

Project A Project B Project C Project D

Inital Outlay (105,000.000) (99,000.00) (110,000.00) (85,000.00)

Inflow year 1 53,000.00 51,000.00 25,000.00 45,000.00

Inflow year 2 50,000.00 47,000.00 55,000.00 50,000.00

Inflow year 3 48,000.00 41,000.00 15,000.00 30,000.00

Inflow year 4 30,000.00 52,000.00 21,000.00 62,000.00

Inflow year 5 35,000.00 40,000.00 35,000.00 68,000.00

Rate 7% 10% 13% 18%

  • Your company is considering three independent projects. Given the following cash flow information, calculate the payback period for each. If your company requires a three-year payback before an investment can be accepted, which project(s) would be accepted?

Project D Project E Project F

Cost 205,000.00 179,000.00 110,000.00

Inflow year 53,000.00 51,000.00 25,000.00

Inflow year 2 50,000.00 87,000.00 55,000.00

Inflow year 3 48,000.00 41,000.00 21,000.00

Inflow year 4 30,000.00 52,000.00 9,000.00

Inflow year 5 24,000.00 40,000.00 35,000.00

  • Using market value and book value (separately), find the adjusted WACC, using 30% tax rate.

Component Balance Sheet Value Market Value Cost of Capital

Debt 5,000,000.00 6,850,000.00 8%

Preferred Stock 4,000,000.00 2,200,00.00 10%

Common Stock 2,000,000.00 5,600,000.00 13%

Tutor Answer

Dr_TanyaZam
School: UC Berkeley

Attached.

Initial Outlay
Inflow year 1
Inflow year 2
Inflow year 3
Inflow year 4
Inflow year 5
Rate
NPV =

Project A
Project B
Project C
$ 105.000,00
99000
110000
$ 53.000,00
51000
25000
$ 50.000,00
47000
55000
$ 48.000,00
41000
15000
$ 30.000,00
52000
21000
$ 35.000,00
40000
35000
7%
10%
13%
$285.228,32
$275.364,07
$217.469,00

The project that should be selected is Project B as it has a high Net Present Value

Project D
85000
45000
50000
30000
62000
68000
18%
$239.006,08

Project D

Cost
Inflow year 1
Inflow year 2
Inflow year 3
Inflow year 4
Inflow year 5

Project E

2050...

flag Report DMCA
Review

Anonymous
Tutor went the extra mile to help me with this essay. Citations were a bit shaky but I appreciated how well he handled APA styles and how ok he was to change them even though I didnt specify. Got a B+ which is believable and acceptable.

Similar Questions
Related Tags

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors