Description
Option #2: Schedule Chart Analysis
Download and examine the project task list from the link provided in the module. Based on this task list, you will create a PERT chart and write a paper that discusses the following:
- Identify which set of tasks create the critical path.
- Determine which task would be best to crash to reduce the critical path.
- Determine if there is a change to the critical path by crashing the task. Is there a new critical path?
- What other information would be beneficial to know to see if the selected task was the best option for crashing?
Your paper should be 2 pages, well written and in conformity with APA format for style and writing expectations. Your PERT chart is part of your page requirements. Include a title page and a reference page that includes at least two outside references to support your analysis.
Unformatted Attachment Preview
Purchase answer to see full attachment
Explanation & Answer
Here you go. In case of any further inputs please let me know!All the best!I appreciate working with you!
CPM/PERT
Tas
k
Task Description
AB
BC
BD
CE
DE
EF
Days to
Complete
Develop plans for product
Have programmers
customize software
Have engineer customize
hardware
Have quality officer test
software
5
Place hardware within casing
Install software onto
hardware
3
7
6
4
7
Cost
$
1,500.00
$
2,500.00
$
1,800.00
$
2,200.00
$
1,400.00
$
1,900.00
Days after
Crash
3
4
5
...
Review
Review
24/7 Study Help
Stuck on a study question? Our verified tutors can answer all questions, from basic math to advanced rocket science!
Similar Content
Related Tags
We Were Eight Years in Power
by Ta-Nehisi Coates
Killers of the Flower Moon
by David Grann
All Quiet on the Western Front
by Erich Maria Remarque
Untamed
by Glennon Doyle
The Scarlet Letter
by Nathaniel Hawthorne
Homo Deus
by Yuval Noah Harari
Mockingjay
by Suzanne Collins
Unf*ck Yourself
by Gary John Bishop
Catching Fire
by Suzanne Collins