Conflict Resolution Using Cognitive
Analysis Approach
Hashem Al-Tabtabai, Kuwait University, College of Engineering and Petroleum, Civil Engineering
Department, PO Box 5969, Safat 13060 Kuwait
Alex P. Alex, Kuwait University, College of Engineering and Petroleum, Civil Engineering
Department, PO Box 5969, Safat 13060 Kuwait
Ahmed Abou-alfotouh, Kuwait University, College of Engineering and Petroleum, Electrical
Engineering Department, PO Box 5969, Safat 13060 Kuwait
egaprojects require extensive coordination of various activities, each with different degrees of complexity and with different participants. The elaborateness of interactions often produces conflict situations at various stages of the
project. The importance of studying the origin and effect of conflict is critical for
project participants, because the actions they take in response to conflicting issues
can influence the management of both their projects and their organizations. Conflict develops because of various factors. These factors may be classified simply as
either “interpersonal” or “managerial.” Interpersonal differences can be attributed
to contrasting values, perceptions, and methods. Managerial-level differences can
arise from unbalanced views of project goals, lack of coordination, and inefficient
communication among the project participants. Conflict at the management level
may also arise from differences in practices advocated by respective organizations
under individual managerial units.
Some may consider the effect of conflict to be constructive; it can lead to new
ideas, new information, and novel ways of approaching problems. Simply put: conflict helps rectify “wrong” beliefs and values. Others may consider conflict to be destructive; it may erode organizational performance, create disorder among project
team members, and even cause delay in decision-making or result in schedule shifts
and cost overruns (Verma, 1996). The ability of project participants to manage conflict for the benefit of their organization is a significant factor in ensuring project success. Each conflict situation should be closely examined so that underlying causes can
be recognized in order to achieve resolution as swiftly and completely as possible.
Literature reviews in the field of conflict management (Singh & Vlatas, 1991)
have identified five conventional approaches to the resolution of conflict. These
approaches, with their limitations, are classified as follows:
■ Forcing: This is a typical win-lose type of resolution. The viewpoint of an individual is exercised at the expense of the other, thus creating an apparent removal
of any conflict between them. This approach brings feelings of resentment and
causes deterioration in the relationship between the persons in conflict.
■ Withdrawal: In this approach, the individuals withdraw from the conflict issues. In actuality, the conflicting issues are avoided. This type of resolution is not
effective because the approach does not eliminate the conflict.
M
▼
Abstract
Within the field of project management, research
in the subject of conflict analysis and resolution
has received considerable attention. This paper
presents the application of cognitive analysis,
based on the workings of “human judgment
theorists,” to the resolution of representative
conflict situations. The employed conflictresolution approach presents cognitive differences
between parties as a primary source of conflict.
However, it also presents feedback that provides
analysis of each individual’s judgment and
comparisons with his or her counterpart’s
judgment. This feedback, termed “cognitive
feedback,” is used as a way to give insight to
people in conflict, providing them an opportunity
to resolve their conflicts acceptably. The objective
of this paper is to establish a systematic
methodology for analyzing and resolving conflict.
An actual case study of conflict resolution between
union and management personnel at a
petrochemical plant in Kuwait is used to illustrate
the methodology. Both self-understanding and the
understanding of one’s counterpart were found to
be generally poor before receiving cognitive
feedback. The use of cognitive feedback for both
groups proved feasible and helped reduce conflict.
Keywords: conflict resolution; negotiation;
human judgment; cognitive analysis
©2001 by the Project Management Institute
2001, Vol. 32, No. 2, 4–16
8756–9728/01/$5.00 per article + $0.50 per page
4
Project Management Journal
March 2001
■ Smoothing: The emphasis in smoothing is to focus on
similarities rather than on differences over issues. Like withdrawal, smoothing may not address the real issues; thus, the
differences remain under the surface.
■ Compromising: Bargaining and searching for a solution is
the basis of this approach. But a compromise is often attained at the expense of optimum results. This approach
often involves third-party intervention, negotiation, and even
voting. This resolution is influenced by the relative strength
of the parties.
■ Confrontation: This approach involves a rational problemsolving approach. Disputing parties solve their differences by
first focusing on the issues, then looking at alternative approaches, and finally selecting the best alternative. This
method can be time-consuming and is frequently inappropriate for most communication.
These traditional approaches were developed three
decades ago. Traditional models consider conflict between
individuals to reflect differing views of the “What’s in it for
me?” attitude prevalent during this period (Al-Sedairy,
1994). At some point in history, conflict was considered as
universally destructive, reflecting the belief that disagreement
universally bred contempt. Furthermore, these approaches
failed to examine the psychological aspects of conflict, and
for that reason have not helped the individuals engaged in
conflict to resolve the value differences arising out of the
conflict situation. Finally, none of these traditional methods
advocate any methodology for modeling the conflict in
terms of its intensity and magnitude (Verma, 1996).
Judgmental analysis studies by human judgment theorists
have argued that cognitive differences between persons are
the basis of conflict among individuals (Blake, Hammond, &
Meyer, 1975; Hammond, McClelland, & Mumpower, 1980).
Their research has produced several theories that study interpersonal conflict and methods to resolve it. These theories
differ with the earlier-mentioned traditional conflict-resolution theories for three reasons. First, traditional (motivational) theories have not sufficiently enhanced the ability to
analyze, manage, or reduce human conflict. Second, traditional theories require us to look for self-serving behavior in
the other person whenever conflict occurs—a process that is
divisive and aggravates conflict. Third, preoccupation with
differential gain as the prime cause of conflict diverts our attention from other possible causes.
The objective of this paper is to introduce a systematic
methodology for analyzing and resolving conflict situations,
based on the works of human judgment researchers. The
paper proposes an alternate conflict-resolution strategy,
which argues that cognitive differences among individuals are
capable of producing conflict. The proposed strategy, based
on the social judgment theory (SJT), argues that the nature of
human judgment is such that it provides a prime source of
conflict and that many, although not all, disagreements flow
from the exercise of human judgment. Consequently, even if
self-serving motives are eliminated, interpersonal conflict
will persist.
June 2001
Need for Clarification of the Human Judgment
Process
Research done by human judgment theorists (Brehmer, 1988;
Einhorn & Hogarth, 1981; Hammond, Stewart, Brehmer, &
Steinman, 1975) has indicated that, unaided, a person faces
difficulties in clarifying his or her judgment for the following
reasons.
Human judgment is a covert process. It is difficult for an individual to accurately describe his or her judgment process.
Introspection and observation of the judgment process and
guessing at the reasons for them are the only means of uncovering or explaining judgments. Subjective reports of one’s
judgment process and the uninformed nature of guessing
often lead to inaccuracy.
Inaccurate Reporting. People often are unable to accurately
describe the principle by which they organize the data to
reach a judgment. Most explanations are incomplete at best
and misleading at worst. This is due to the variable nature of
subjective reporting on the process of judgment.
Inconsistency. Human judgment is neither a fully analytical nor an entirely controlled process. Even when people
do their best to be consistent, in identical situations they
will not necessarily draw identical judgments.
Based upon these statements, human judgment theorists
have argued that judgment does not always accomplish what is
required of it and that many, although not all, disagreements
flow from the exercise of human judgment. Human judgment
theorists, however, argue that methods can be applied to aid
decision-makers in making required judgments as well as improving their judgments in overcoming conflict situations.
Cognitive Analysis Approach as a Conflict-Resolution
Technique
The conflict-resolution technique presented here is based
on the assumption that human judgment is a cognitive
process (Hammond et al., 1975; Stewart, 1988). In this
process, an individual draws a conclusion or makes a judgment (Ys) about a distal or uncertain event (Ye) [depth variable]. The distal event is not visible; it is drawn from data or
cues (x , x … x ) [surface variable] that can be perceived or
1
2
n
that represent information available for making a judgment.
Moreover, individuals do not have access to the distal variable about which they intend to make a judgment, but have
access only to the surface variable upon which to base their
inferences. This ambiguity between the depth variable and
the surface variable [cues] explains the cognitive differences
among persons who arrive at a conclusion (i.e., the difference in Ys for each individual). This cognitive difference can
be inferred to be the major source of conflict between individuals making differing conclusions about a common task.
This approach proposes to resolve the difference that is
appearing in the cognitive system, rather than simply concentrating on the difference in the outcome Ys (its difference
among individuals in conflict). In this technique, the cues
used and the importance attributed to each cue are analyzed
Project Management Journal
5
Step 1:
Identify the Major Domain and
Issues of Conflict
Step 2:
Generate Conflict Profiles
Step 3:
Exercise of Judgment
Step 4:
Judgmental Parameters
Step 5:
Communicating Cognitive
Feedback
Step 6:
Negotiation Among Conflicting
Parties
Compromise
No
Yes
Stop
Figure 1. Steps of the Conflict-Resolution Process
to perceive the real conflict that is inherent in the judgments
among individuals.
A Systematic Methodology to Conflict Resolution
The workings of human judgment theorists can be expanded
to construct a systematic approach to the resolution of conflict.
6
This proposed methodology involves identifying and measuring the cues, the distal variable, and the judgments, and
finding the relationships among these variables. The following
steps (illustrated in Figure 1) explain this methodology.
Step 1: Identification of the Conflict Domain. Acknowledgment and establishment of the conflict situation is
the first step in any conflict-resolution method. The domain
Project Management Journal
June 2001
to be resolved is identified and recognized by all parties in
conflict. Conflicting parties are requested to identify all the
main issues or cues that caused the conflict. These factors
are then sorted and categorized, resulting in a maximum of
eight cues. Large numbers of cues may lead to inaccurate
and inconsistent judgment on the individuals’ parts. This
step should ensure that the parties in conflict are informed
about the presence of conflict and its scope, and will not retain ambiguity about the conflict domain.
Step 2: Generation of Conflict Cases. Hypothetical
case profiles are developed, which consist of a mix of cue
values representing different conflict situations. The cues are
given random values that adequately describe a set of possible conflict situations.
Step 3: Exercise of Judgment. The concerned individuals indicate their judgments by rating several profiles on a
numerical scale. The practice of judgment may take into
consideration two sets of meetings, with the second set containing a number of cases similar to those shown in the
first. The objective is to test the reliability of an individual
judgment in more than one instance.
Step 4: Analysis of the Results. If the judgments a
person has made and the information (cues) upon which
these judgments were based are known, then a mathematical representation can be developed that relates the judgment to the information. An additive nonlinear polynomial
model formed by adding squared terms to the standard
linear regression equation (as follows) is adopted to analyze
the judgment of conflicting parties.
J = a + b1x1 + b2x2 + … + bnxn + b1+n x12 +
b2+n x22 + … + bn+n xn2
[1]
J is the judgment, xn is the nth cue variable, bn is the regression coefficient for the cue n, and b1+n is the regression
coefficient for the square value of cue n. The selection of this
additive curvilinear model is based on the assumption that
the contribution of any cue is independent of the values of
the other cues. The mathematical regression analysis of judgments helps to study the characteristics of each individual by
externalizing several judgmental parameters (as follows),
which are used to resolve the conflict situation.
■ Relative weight. Sources of disagreement between individuals could be due to the different weights they attach to various aspects of the conflict situation. The weights are based
on the standard regression weights adjusted total to 100.
The importance given to each cue by the individuals indicates the weight attributed by each judge on each cue to the
judgment task.
■ Function form. The relationship between the cues and the
judgments can be graphically represented as function forms.
A positive linear function indicates that the judgment value
increases as the cue value increases, while a negative linear
function form indicates that the judgments of desirability
are inversely related to that cue.
■ Consistency. The consistency value represents the efficiency of the model in representing the individual deci-
June 2001
sions. The judgmental models can be tested for consistency
in terms of the correspondence between the statistical
model and the actual predictions, and the amount of judgment variance accounted for by the judgment model by
measuring the multiple correlation coefficient (R) and the
squared multiple correlation (R2), respectively.
■ Reliability. Another measure of consistency is the reliability measure (the product-moment coefficient). This measure indicates the extent to which a person makes similar
judgments when the same information is presented on different occasions.
■ Agreement. The correlation between a set of judgments
made by two parties for the same case reflects the overall
agreement between them. The value of ra in the lens model,
which indicates the degree to which the judgment was correct, will be an index of overall agreement between the two
conflicting parties, which ranges from high degree of disagreement (ra = –1.0) to high degree of agreement (ra = +1.0).
Step 5: Communication of the Judgment Differences
(Cognitive Feedback). Once the judgment parameters are
externalized and analyzed for each of the conflicting parties,
a comparison between individuals and their counterparts in
conflict can be performed. Comparison of weights and
function forms will externalize the major source of conflict
among individuals, provided the individuals make the judgments consistently. All the conflicting parties are provided
with their own judgment characteristics, along with those of
their counterparts, and the individuals are encouraged to
understand the viewpoint of the other and to reduce, if not
eliminate, the conflict that exists among them. Once the
judgment differences are communicated, the individuals are
encouraged to revise their decisions on the conflict issue by
reducing the cognitive difference rather than by discussing
only the difference in outcomes.
Step 6: Negotiation Among Conflicting Parties. In
the negotiation phase, each individual in conflict attempts
to reach an agreement on the evaluation of cases that was
given to them in previous steps. Evaluation of the acceptability of all cases is requested in order to ascertain the degree to which mutual judgment policies can be developed,
based on the provision of the cognitive feedback in comparison to conventional verbal procedures.
An Example: Union vs. Management Negotiation
The proposed conflict-resolution strategy could be applied
to resolve the conflict that can exist between a labor union
and the company management, based on the assumption
that much of the above-mentioned argument is true. What
is at issue is the extent to which the externalization of the
parameters of the judgment process can be demonstrated to
be of potential value, not only to union-management negotiators, but also to specialists in conflict resolution. A conflict situation between the management and labor union of
the Kuwait National Petroleum Company (KNPC) was used
to apply the proposed resolution method. The situation was
Project Management Journal
7
(1) Number of Promotion Tests
None
Pass Interview
Pass Exam
Pass Interview & Exam
Outside the Dept.
Through a
Committee
Outside the Dept.
Without Their
Opinion
(2) Selection of Section Head
Outside the Dept.
With Section
Consult.
Inside the Dept.
(3) Covering Period in Grade 7B
5
7.5
10
12.5
15
(years)
(4) Acting Period in Grades 8 & 10
3
6
9
12
15
18
(months)
Acceptability of Contracts
1
2
3
5
4
Strongly
Recommend to
Accept
6
7
Strongly
Recommend
to Reject
Figure 2. A Sample Profile
sufficiently controversial (70 days of strike had not relieved
the tension) and recent enough that the issues were still
clear to the negotiators.
Step 1: Identifying Major Issues of Conflict. Two of
the five management negotiators and two of the five union
negotiators who took part in the negotiation process agreed
to participate in the proposed conflict-resolution experiment. The four key issues under negotiation between the
labor union and management representatives, are as follows:
Issue 1: Promotion tests. The company conducted a variety
of certification and evaluation tests for promotion against
the wishes of the labor union, which wanted the promotions to be based on seniority.
Issue 2: Assignment of departments’ managers. The company wished to assign the department manager from outside that department, while the union preferred to have the
manager assigned from within the department.
Issue 3: Required years in service in Grade 7B. The number
of years necessary to serve in the Grade 7B level at KNPC in
order to be promoted to Grade 8 was an additional factor
under negotiation.
Issue 4: Required period in Grades 8 and 10. The duration,
in terms of months, that a worker should serve in Grades 8
and 10 was another factor under negotiation.
Time was spent with one management negotiator and
one union negotiator to discuss the issues involved in conflict in order to make certain that no issue of importance
was omitted.
Step 2: Generation of Hypothetical Profiles. Sample
negotiation contract scenarios were created, each repre-
8
senting a different combination of values for the four issues.
In order to ensure clarity and ease of evaluation, the first
and second cues were divided into four scale values (from
lowest to highest) and represented in graphic form, as
shown in Figure 2. The values for the first and second issues
are non-numerical, while the values for the last two issues
are numerical. The values for the first issue were: none, pass
an interview, pass a written exam, and pass both interview
and written exam. The values for the second issue were assignment: from inside the department, from outside the department after department consultation, from outside the
department through a committee, and without considering
the opinion of the department. The third issue was divided
into five scales (from 5–15 years), and the fourth issue was
divided into six scales (ranging from 3–18 months).
By using different combinations of the four issues, 480
different possible negotiation contracts were produced. To
facilitate the process of contract evaluation, 30 such possible
contracts were selected on a random basis as a representative
sample to illustrate the proposed conflict-resolution strategy.
A 7-point evaluation scale, ranging from “strongly accept
the contract” to “strongly reject the contract,” was designed
with the help of one union representative and one management representative. The aim was for the scale to simulate
the type of judgments made during actual negotiations.
Step 3: Collecting the Judgments. The participants
were given instructions and shown the 20 contracts for the
first time. Each participant judged each of the 20 contracts,
using the 7-point acceptance-rejection scale. Each participant
then made a subjective estimate of the weight (in terms of
Project Management Journal
June 2001
Issue
1
W=
5
=1
60
W
2
M2
W=
20
5
W=
W=40
W=10
U2
3
W=
40
10
W=
4
Note. The width of the line denotes the weights placed on each issue subjectively.
Figure 3. Example of How Differential Weights Attached to the Four Contract Issues Were Shown to the Negotiators
percentage) that he felt he would place on each of the four
issues. Then, after a one-hour break, 10 randomly selected
contracts, repeated from the first 20, and 10 new contracts
were shown to each participant. Each one judged them using
the scale. The purpose was to measure the reliability of a
person making judgments when the same information is
presented to that person on two different occasions. The authors supervised this training process of the participants, and
one of the co-authors was present during data-collection
phases to ensure that any questions were answered.
Each participant was paired with a member of the other
side, thus forming two pairs, coded U1-M1 and U2-M2
(where U = union, M = management). In both sessions,
each participant predicted what the counterpart would place
on each of the four issues.
Step 4: Externalization of Judgmental Parameters.
Following the collection of judgments (before the cognitive
feedback phase), the judgmental parameters of each negotiator’s contract were derived. These parameters were used to
show the participants, in pictorial form, the characteristics
of both their judgments and their counterparts’ judgments.
The purpose of presenting the results was to help the participants understand the sources of conflict.
Interactive computer software programs (a statistical
package entitled Policy PC and a spreadsheet in Microsoft
Excel) were used to provide key information for each of the
negotiators, in regard to that individual’s judgment process
as well as that of the counterpart’s. Each negotiator’s contract judgment was analyzed in terms of a special form of
multiple regression statistics. The regression analysis was
computed separately for each union and management negotiator, using each participant’s judgment as the dependent
variable. The independent, or predictor, variables in the
June 2001
analysis were the values of the issues, and the squares of the
difference of these values, and the mean of each one. Thus,
there were eight independent variables in each regression
analysis. This procedure permitted the analysis of both
linear and quadratic components of judgmental variance.
The following judgmental parameters were externalized
during the data analysis.
1. Differential weighting system among participants. The
weight each participant had given to each issue was displayed graphically. Figure 3 provides an example, in pictorial form, of the differential weighting system, providing a
direct visual representation of one source of conflict. In this
figure, the largest difference occurs in connection with the
promotion issue (Issue 1), to which the union negotiator
assigned a higher weight than that assigned by the management negotiator.
2. Comparisons of own weighting system. Figure 4 illustrates
the extent to which an individual negotiator misunderstood
his weighting system. For example, in this figure, negotiator
M1, in making his contract judgments, underestimated the
weight system that he attached to the promotion issue. He
had subjectively estimated that issue to be 50% significant,
while the weight derived from his actual judgment was
found to be 34%.
3. Comparison with counterpart’s weighting system. The top
two bars in Figure 4 provide an example of self-misunderstanding, while the comparison between the bottom bar
and the top bar provides an example of how misunderstanding of one’s counterpart is externalized. The counterpart’s actual weighting system (derived from the analysis of
his contract judgments) is compared with the negotiator’s
subjective weight estimates for his counterpart. For example,
comparison of the bottom bar and the top bar shows that
Project Management Journal
9
Model of M1
Model of U1
34
29
23
Subjective Estimate of M1
50
10
10
50
30
70
11
10
30
10
Subjective Estimate of M1 on U1
20
5 5
Model of M2
5
50
25
20
Model of U2
23
13
44
20
Subjective Estimate of M2
40
Top Bar: Weights Derived From
Practicing Own Judgments of
Contracts
19
60
40
30
5
44
32
Subjective Estimate of U2
Subjective Estimate of U2 on M2
50
17
Subjective Estimate of U1
Subjective Estimate of U1 on M1
15 5
25
47
14
20
10
10
Subjective Estimate of M2 on U2
10 10
40
Middle Bar: Subjective Estimate
of Own Weights
5
30
25
Bottom Bar: Subjective Estimate
of Counterpart’s Weights
Figure 4. Comparison Between Negotiator’s Subjective Report of Issue-Weighting System
With Actual Weighting System
the negotiator (M1) makes incorrect subjective weight estimates of his counterpart U1.
Data shown in Figure 4 represent the degree of misunderstanding that remained between the two negotiators,
even after several months of discussion during actual negotiations.
4. Function forms. The function forms used in relating the
judgment of each of the participants to each of the four issues were displayed graphically. Figure 5 provides an example of how function forms were shown to negotiators.
Opposing curvilinear function forms were found for Issue 1
(the promotion test), and both positive and negative nonlinear function forms were found for the issue, “the department head” (upper right). The notion of an optimal
settlement for both the union and management negotiators
for the department head issue in the intersection of their
function forms can be seen in Figure 5.
Step 5: Communicating the Judgmental Differences
(Cognitive Feedback). The feedback phase was administered one week after the judgment process. The purpose was
to provide cognitive feedback to all the negotiators. Feedback consisted of two parts. In the first part, each participant
was shown the data (externalized in Step 4) concerning the
negotiator’s own weights for each of the four contract issues,
as well as graphs showing the form (curvilinear) of relations
between each issue and his evaluations. After receiving this
form of feedback about his evaluation, each of the four ne-
10
gotiators (U1 and M1, U2 and M2) reevaluated the contracts
and estimated the weights that he used on this occasion.
In the second part of this phase, each negotiator observed his counterpart’s weights and graphs of the relations
between issues and judgments for each of the four issues.
Each negotiator then made new predictions of his counterpart’s evaluations of the contracts and predictions of his
counterpart’s weights. No discussion between participants
was permitted in this phase, thus ensuring that the feedback
was nonverbal.
Step 6: Negotiation Phase. A minimum bargaining was
suggested to achieve agreement on specific contracts. In the
negotiation phase, the conflicting parties were encouraged
to negotiate the issues based on the externalized judgment
parameters. Figures 7 and 8 provide examples of how function forms were shown to the negotiators. Figure 8 also
shows the settlement point reached by the conflicting parties. The illustration shows that negotiators can provide
such information, and indicates the form in which it can be
displayed. Such information could have been viewed directly by the participants, had they carried out their negotiations at a common site with interactive computer devices.
Instead, in our study, the graphs were reproduced separately
on paper and shown to the negotiators. Current growth in
information technology can be used to connect conflicting
parties situated at different locations, using local area networks or the World Wide Web.
Project Management Journal
June 2001
Issue 1
Issue 2
8
8
6
6
4
4
2
2
0
0
1
2
4
3
1
2
3
Inside
M1
U1
Issue 3
4
Outside Without
Section Opinion
M1
U1
Issue 4
8
8
6
6
4
4
2
2
0
0
5
7.5
M1
10
12.5
15
3
U1
10.5
M1
18
U1
Note. Scales from 1 to 3 indicate to accept, scale 4 indicates neutral, and scales 5 to 7 indicate reject.
Figure 5. Function Forms of the U1-M1 Negotiators Before Cognitive Feedback
Results of the Conflict Analysis
Degree of Union-Management Conflict. Table 1 and Figures 5 and 7 illustrate the degree of conflict between the
parties. Both groups initially were in wide disagreement.
The before cognitive feedback (BCF) phase data shows that
the first pair (U1-M1) were far apart in their judgments of
the acceptability of contracts when the correlation between
judgment evaluation was negative (–0.1576). Further BCF
data also shows that the second pair (U2-M2) were very poor
in their judgments of the acceptability of contracts when the
correlation was near zero (0.0267).
Figure 5 indicates that U1-M1 is in wide disagreement for
the first, second, and third issues, while there is slight agreement in the fourth issue, during the BCF phase. In the after
cognitive feedback (ACF) phase (see Figure 6), the disagreement still existed in the second and fourth issues, but agreement about the first issue was achieved.
Figure 7 indicates that U2-M2 was in wide disagreement
for the third and the fourth issues, while there was considerable agreement for the first and second issues, during the
BCF phase. The situation could be improved after the feed-
June 2001
back, as shown in Figure 8; there was a total agreement in
the second and fourth issues, while a slight disagreement
still existed in the first and the third issues.
Self-Misunderstanding of the Weighting System. Negotiators did not accurately estimate the weight they had
placed on each issue. There were wide individual differences
among the evaluations of management negotiators with regard to their own weights. Compared to U2, the subjective
estimate of U1 was closer to the actual weighting system
adopted during the judgment process. However, evaluations
of both union negotiators were more closely grouped than
those of management. The union negotiators assumed that
they had placed a higher weight on the promotional examination issue than they in fact did when evaluating the contracts. They also estimated a lower weight for the department
head issue (cue 2) than they actually demonstrated when
evaluating the contracts (ACF phase).
Self-Understanding of Individual Judgment Policies.
Although both union and management representatives
agreed prior to the experiment that there were at least four
major issues, the judgments made by three of the four participants revealed that Issue 1 was in fact more significant than
Project Management Journal
11
Issue 1
Issue 2
8
8
6
6
4
4
2
2
0
0
1
2
4
3
1
2
3
Inside
M1
U1
Issue 3
4
Outside Without
Section Opinion
M1
U1
Issue 4
8
8
6
6
4
4
2
2
0
0
5
7.5
M1
10
12.5
15
3
U1
10.5
M1
18
U1
Note. Scales from 1 to 3 indicate to accept, scale 4 indicates neutral, and scales 5 to 7 indicate reject.
Figure 6. Function Forms of the U1-M1 Negotiators After Cognitive Feedback
the other issues. As listed in Table 1, Issue 1 (promotional examinations) was important to the union representatives and
one representative of management. While Issues 2 and 3 had
moderate significance to unions and management, Issue 4
(covering the period) is in fact less significant in both the BCF
and ACF phases among the conflicting parties.
The above results illustrate how poor the negotiators’
self-understanding can be. The implications for negotiations
are clear: deficiencies in self-understanding lead to the unwitting communication of false information. An inaccurate
report of one’s own position is, of course, a barrier to the
achievement of agreement, despite the best of intentions.
Misunderstanding Others. Table 2 shows the predictive
accuracy where ra indicates the degree of correlation between
predicted evaluation and actual evaluation by a counterpart. G
indicates the same value corrected for the inconsistency of the
predictor. Both sides proved to be inaccurate. Prior to the exchange of information, M2 and U2 were unable to predict the
judgments of the other side with a significant degree of accuracy
in both the BCF and ACF phases (see Table 2). The other negotiators’ a priori understanding of their counterparts, therefore,
was poor. They had an inaccurate understanding of the other
12
side’s contract evaluation policy. After the feedback phase, the
three negotiators’ (M2, U1, and U2) accuracy improved in their
predictions. Although two of the negotiators (M1 and U2)
were generally inaccurate in their predictions of their counterparts’ evaluations, U2 improved his overall accuracy of
prediction between the BCF and ACF phases (see Table 2).
These findings illustrate one of the more important contributions of externalization. The negotiators were wrong in
being confident that they understood the policies of their
counterparts, a belief based on a long period of association
and negotiation. In order to improve accuracy, both the
target persons and the predictor would have to be much
more self-consistent. If the target person changed his evaluation policy before and after the feedback, his evaluations
would be more difficult to predict, as was the case with one
of the union negotiators. Although self-understanding before the feedback phase was poor, improvement in predictive accuracy appears to have been due largely to the
stability of the judgments of the target person at least as
much as to the utility of graphics feedback.
Intra-Union and Intra-Management Uniformity. A
correlation among each group’s judgments was computed
Project Management Journal
June 2001
Issue 1
Issue 2
8
8
6
6
4
4
2
2
0
0
1
2
4
3
1
2
3
Inside
M2
U2
Issue 3
4
Outside Without
Section Opinion
M2
U2
Issue 4
8
8
6
6
4
4
2
2
0
0
5
7.5
M2
10
12.5
15
3
U2
10.5
M2
18
U2
Note. Scales from 1 to 3 indicate to accept, scale 4 indicates neutral, and scales 5 to 7 indicate reject.
Figure 7. Function Forms of the U2-M2 Negotiators Before Cognitive Feedback
to learn the level of agreement among each group (see
Table 3). A high degree of uniformity existed among union
negotiators. Comparisons between the evaluations of
union negotiators produced fairly high indications of
agreement, especially in the ACF phase. When corrected for
inconsistency (see column labeled “G-ACF” in Table 3), it
is clear that the union negotiators were in agreement with
one another. Union negotiators could have readily substituted for one another without affecting contact evaluations.
On the other hand, non-uniformity existed among management negotiators. The correlation between management
evaluations was negative, which shows that management
negotiators were in wide disagreement among themselves
in both the BCF and ACF phases, even when corrected for
inconsistency.
Self-Consistency. Consistency of contract evaluations
would make negotiation much easier, while inconsistency
of contract evaluations implies that policies change from
the evaluation of one contract to the next. The consistency
of each participant’s judgment model was examined by the
coefficient of multiple regression (R) and the square multiple correlation coefficient (R2), as shown in Table 4. Self-
June 2001
consistency was generally high. The participants were quite
self-consistent at the BCF phase; however, all negotiators
were less consistent in the ACF phase.
Reliability. The reliability test, which is a measure of
consistency, was computed by presenting the participants
with two pairs of similar case profiles on two different occasions. The reliability measures of these persons are reported
in the last column of Table 4. The reliability measures of the
negotiators indicate reliability ranges from very good (R =
0.9323) to poor (R = 0.5343).
Changes in Policy. Changes occurred in the evaluation
policy. The models of all participants exhibited some
changes before and after the feedback periods, as shown in
Table 1. The change can be attributed to the role of feedback
in terms of both sides’ judgmental parameters. Access to
such information made a change on the part of the management negotiators that led to increased agreement. Another example in the changes in policy can be found by
comparing Figures 7 and 8. Function forms of U2 and M2
were opposite in nature at the BCF phase, while they
showed higher agreement after receiving cognitive feedback
in the ACF phase.
Project Management Journal
13
Issue 1
Issue 2
8
8
6
6
4
4
2
2
0
0
1
2
4
3
1
2
3
Inside
M2
U2
Issue 3
4
Outside Without
Section Opinion
M2
U2
Issue 4
8
8
6
6
4
4
2
2
0
0
5
7.5
M2
10
12.5
15
3
U2
10
M2
18
U2
Note. Scales from 1 to 3 indicate to accept, scale 4 indicates neutral, and scales 5 to 7 indicate reject.
* Indicates the values of final agreement
Figure 8. Function Forms of the U2-M2 Negotiators After Cognitive Feedback
The Use of Cognitive Feedback as an Aid to Reduce
Conflict
It can be concluded that the use of feedback can lead to
better agreement. The purpose of cognitive aid is to provide
each individual the opportunity to modify the judgment
values if he or she desires to do so after viewing a complete
judgment analysis of his or her own judgment and that of a
counterpart. Cognitive aid also allows for a comparison of
actual judgments made against the predicted judgments.
The feedback helps the persons in conflict to understand
their judgment process, how they arrived at a decision, and
also how colleagues perceive the same situation. Table 1 illustrates that the second pair (U2-M2), after receiving feedback, achieved a better agreement level. The results indicate
that the use of the proposed methodology and procedures
led to more agreement among conflicting parties.
The conflicting parties, based on the negotiations, arrived
at a final compromise on the issues. The negotiated settlement was to (1) conduct an exam and an interview for promotion, (2) select a department head from within the
department, (3) make the covering period in Grade 7B three
14
to five years, and (4) make the acting period in Grades 8–10
10 months. Figure 8 also shows the above settlement points
marked for each of the cues.
Discussion and Concluding Observations
The aim of this research was to establish a methodology for
externalizing the judgment process of conflicting parties.
The cognitive-analysis approach is applied to reduce the
conflict found between the parties. The identified conflicting issues were classified into four broad factors to act as
cues. The possible ranges of each of the cues were fixed after
discussions with the conflicting parties. Judgments were collected and analyzed with multiple regression techniques.
The function form of each cue for each of the participants,
along with the weight attached for each cue as perceived by
each, was computed. The judgmental analysis results (i.e.,
the variation in the weights produced, the participants’ different function forms for each issue, and the consistency
measures) provide evidence of conflict among individuals.
It also provides insight about the cognitive differences be-
Project Management Journal
June 2001
Negotiator
Cue 1
Cue 2
Cue 3
Cue 4
S
O
S
O
S
O
S
O
M1
M2
50
15
34
23
10
5
29
44
10
40
23
13
30
40
14
20
U1
U2
50
60
47
44
10
20
25
5
30
10
17
19
10
10
11
32
M1
M2
50
10
49
28
20
40
33
28
15
20
12
24
15
30
6
20
U1
U2
50
60
14
24
10
10
24
33
20
10
44
33
20
20
19
10
BCF
ACF
BCF = Before Cognitive Feedback
ACF = After Cognitive Feedback
Table 1. Comparison of Subjective (S) and Objective (O) Weights (in percent) for Each Negotiator for Each Issue
ra
Predictor
G
BCF
ACF
BCF
ACF
M1
M2
–0.4186
0.8833
0.5488
0.0086
–0.5809
0.9898
0.6051
0.0132
U1
U2
0.8109
0.3914
0.7060
0.5869
0.9230
0.4718
0.7942
0.6429
BCF = Before Cognitive Feedback
ACF = After Cognitive Feedback
ra = Degree of Correlation
Table 2. Predictive Accuracy
ra
Management Pair
M1–M2
Union Pair
U1–U2
G
BCF
ACF
BCF
ACF
–0.3794
–0.2073
–0.470427
–0.25704
0.5442
0.8734
0.63716
0.9779
BCF = Before Cognitive Feedback
ACF = After Cognitive Feedback
ra = Degree of Correlation
Table 3. Intra-Union and Intra-Management Uniformity
tween the parties. An attempt is made to reduce, if not eliminate, the conflict among the participants by giving cognitive feedback about their judgments and the judgments of
their counterparts. The conflict developed between the
union and management could be analyzed by the proposed
cognitive-analysis approach.
The results of this research show that the proposed
methodology could be useful for negotiation and resolution
June 2001
of conflict. Exchange of cognitive feedback among the labor
union and management participants has enabled them to
achieve a modest amount of agreement. It is important to
observe that the criterion for agreement used here is far more
stringent than that applied to ordinary negotiation. Cognitive feedback helps conflicting parties gain insight about the
tradeoffs among different cues, weights, and function forms,
relating cues to judgment and consistency in exercising their
Project Management Journal
15
Negotiator
R2
R
Reliability
BCF
ACF
BCF
ACF
M1
M2
0.721
0.869
0.907
0.653
0.519
0.755
0.823
0.426
0.7597
0.8792
U1
U2
0.879
0.830
0.889
0.913
0.772
0.688
0.791
0.834
0.9323
0.5343
BCF = Before Cognitive Feedback
ACF = After Cognitive Feedback
Table 4. Consistency of Contract Evaluations
judgments. This feedback helps them to refine their judgment skills, and also to modify different values and beliefs
they had about the conflict domain. Cognitive feedback provides maximum information on the reasons why the parties
are in conflict, as well as areas that need to be negotiated to
reach an agreement.
The proposed cognitive analysis approach helped the
project participants involved in conflict to concentrate on
the real differences that triggered the conflict among their
colleagues and themselves, rather than only discussing the
effects of the situation under conflict. The proposed conflict-resolution technique can be effectively applied when
important decisions have to be reached by project team
members of different domains, such as a construction contractor and a consultant.
References
Al-Sedairy, S.T. (1994). Management of conflict. International
Journal of Project Management, 12 (3), 143–151.
Blake, W.M., Hammond, K.R., & Meyer, G.M. (1975). An alternate approach to labour-management relations. ASQ, 311–327.
Brehmer, B. (1988). The development of social judgment theory.
In B. Brehmer & C.R.B. Joyce (Eds.), Human judgment: The SJT view
(pp. 13–40). Amsterdam: North-Holland.
Einhorn, H., & Hogarth, R. (1981). Behavioral decision theory:
Processes of judgment and choice. Annual Review of Psychology, 32,
53–88.
Hammond K.R., McClelland, G.H., & Mumpower, J.M. (1980).
Human judgment and decision making: Theories, methods, and procedures. New York: Praeger.
Hammond, K.R., Stewart, T.R., Brehmer, B., & Steinman, D.O.
(1975). Social judgment theory. In M. Kaplan & S. Shwartz (Eds.),
Human judgment and decision processes (pp. 271–312). New York:
Academic Press.
Singh, A., & Vlatas, D.A. (1991). Using conflict management for
better decision making. Journal of Management in Engineering, 7 (1),
70–82.
Stewart, T.R. (1988). Judgment analysis: Procedures. In B.
Brehmer & C.R.B. Joyce (Eds.), Human judgment: The SJT view (pp.
41–74). Amsterdam: North-Holland.
Verma, V. (1996). Human resources skills for the project manager.
Upper Darby, PA: Project Management Institute.
16
Hashem Al-Tabtabai, Ph.D., is an associate professor of
the Civil Engineering Department at Kuwait University. He
received B.S. and M.S. degrees in civil engineering from
North Carolina State University and a Ph.D. from
Colorado University at Boulder. His research focuses on
advanced information technology in project management, project
control, cost estimation, cost management, and cost control. He is a
member of PMI®.
Alex P. Alex received his B.E. degree in civil engineering
and M. Tech degree in engineering management from
Manipal Institute of Technology, Mangalore University,
India. He is currently an engineer at the Civil Engineering
Department, Kuwait University, and is also affiliated with
many private-sector firms in Kuwait offering professional construction
management services. His research interests are in modeling and
optimizing complex decision systems in project management, cost
estimation, project scheduling, resource allocation, and risk
management using computational intelligence techniques.
Project Management Journal
Ahmed Abou-alfotouh received B.S. and M.S. (honors)
degrees in electrical engineering from Kuwait University.
He is currently a research and teaching assistant at
Kuwait University. His research interests are in project
management, artificial neural networks, and power
systems.
June 2001
Contemporary
Project Management
FOURTH EDITION
Timothy J. Kloppenborg
•
Vittal Anantatmula
•
Kathryn N. Wells
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. WCN 02-200-203
MS Project 2016 Instructions in Contemporary Project Management 4e
Chapter
MS Project
3
MS Project 2016 Introduction
Ribbon, Quick Access Toolbar, view panes, Zoom Slider, Shortcuts, Scheduling Mode Selector
Setting Up Your First Project
Auto schedule, start date, identifying information, summary row
Create Milestone Schedule
Key milestones, zero duration, must finish on, information
7
Set Up a Work Breakdown Structure (WBS)
Understand the WBS definitions and displays
Enter WBS Elements (tasks), Create the outline,
Insert WBS Code Identifier column, Hide or show subtasks detail
8
Using MS Project for Critical Path Schedules
Set Up the Project Schedule
Set or update the project start date, Define organization’s working and nonworking time
Build the Network Diagram and Identify the Critical Path
Enter tasks and milestones, edit the timescale, understand and define task dependencies, assign task
duration estimates, identify the critical path, understand the network diagram view
Display and Print Schedules
9
Define Resources
Resource views, max units, resource calendars
Assigning Resources
Basic assignment, modify an assignment
Identify Overallocated Resources
Resource usage and Detailed Gantt views together
Overallocated Resources
Finding overallocated resources, dealing with overallocations
Crashing a Critical Path Activity
10
Develop Bottom-up Project Budget
Assignment costs, task costs, various cost perspectives
Develop Summary Project Budget
12
Baseline the Project Plan
First time baseline, subsequent baselines, viewing variances
14
Using MS Project to Monitor and Control Projects
What Makes a Schedule Useful?
How MS Project recalculates based on reported actuals, current and future impacts of variances, define
the performance update process (who, what, when)
Steps to Update the Project Schedule
Acquire performance data, set and display status date, Enter duration-based performance data,
reschedule remaining work, revise future estimates
15
Close Project
Creating project progress reports, sharing reports, export a report to MS Excel, archive project work,
capture and publish lessons learned
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
PMBOK® Guide 6e Coverage in Contemporary Project Management 4e
The numbers refer to the text page where the process is defined.
Project management (PM) processes and knowledge areas 10–11
Project life cycle 7–10, 62–64
Projects and strategic planning 33–37
Organizational influences 102–110
Portfolio and program management 37–42
®
PMBOK Guide, 6th ed. Coverage
Knowledge
Areas
Project
Integration
Management
Initiating
Process
Group
Develop
Project
Charter
60–79
Planning Process Group
Develop Project Management Plan
409–410
Executing Process
Group
Monitoring &
Controlling
Process Group
Closing
Process
Group
Direct and Manage
Project Work 459–460
Manage Project
Knowledge 192–193,
504–508
Monitor and Control
Project Work 460–462
Perform Integrated
Change Control
229–232, 462–463
Close
Project
or Phase
503,
508–511
Project Scope
Management
Plan Scope Management 211–212
Collect Requirements 212–216
Define Scope 216–220
Create WBS 220–229
Validate Scope
500–501
Control Scope
475–476
Project
Schedule
Management
Plan Schedule Management 246
Define Activities 249–253
Sequence Activities 253–255
Estimate Activity Durations 255–258
Develop Schedule 259–267
Control Schedule
476–480
Project Cost
Management
Plan Cost Management 329–330
Estimate Costs 330–341
Determine Budget 342–344
Control Costs 345,
476–480
Project Quality
Management
Plan Quality Management 401–404
Manage Quality
404–406, 469–474
Control Quality
406–409, 469–474
Project
Resources
Management
Plan Resource Management 290–295
Estimate Activity Resources 290
Aquire Resources
138–141
Develop Team 141–157
Manage Team 157–161
Control Resources 476
Project Communications
Management
Plan Communications Management
188–192
Manage
Communications
193–199, 465–467
Monitor
Communications
467–468
Project Risk
Management
Plan Risk Management 360–366
Identify Risks 75, 366–368
Perform Qualitative Risk Analysis 75,
368–372
Perform Quantitative Risk Analysis
372–373
Plan Risk Responses 75, 373–377
Implement Risk
Responses 464–465
Monitor Risks
463–464
Project
Procurement
Management
Plan Procurement Management
431–433, 438–441
Conduct
Procurements
434–438
Control Procurments
441
Plan Stakeholder Engagement 184–186
Manage Stakeholder
Engagement 187–188
Monitor Stakeholder
Engagement 188
Project Stakeholder
Management
Identify
Stakeholders 75–77,
178–184
® Guide), 6th ed. (Newtown Square, PA: Project Management
Source: Adapted from A Guide to the Project Management Body of Knowledge (PMBOK
Institute, Inc., 2017): 31.
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contemporary Project
Management
ORGANIZE
LEAD
PLAN
PERFORM
FOURTH EDITION
TIMOTHY J. KLOPPENBORG
Xavier University
VITTAL ANANTATMULA
Western Carolina University
KATHRYN N. WELLS
Keller Williams Real Estate
Australia • Brazil • Mexico • Singapore • United Kingdom • United States
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
This is an electronic version of the print textbook. Due to electronic rights restrictions,
some third party content may be suppressed. Editorial review has deemed that any suppressed
content does not materially affect the overall learning experience. The publisher reserves the right
to remove content from this title at any time if subsequent rights restrictions require it. For
valuable information on pricing, previous editions, changes to current editions, and alternate
formats, please visit www.cengage.com/highered to search by ISBN#, author, title, or keyword for
materials in your areas of interest.
Important Notice: Media content referenced within the product description or the product
text may not be available in the eBook version.
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. WCN 02-200-203
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contemporary Project Management,
Fourth Edition
2019 2015
Timothy J. Kloppenborg
Cengage Learning Customer & Sales Support, 1-800-354-9706
www.cengage.com/permissions
permissionrequest@cengage.com
2017947974
978 1 337 40645 1
Cengage Learning
20
02210
40
125
www.cengage.com.
www.cengage.com
www.cengagebrain.com
Printed in the United States of America
Print Number: 01
Print Year: 2017
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
MS Project 2016 Instructions in Contemporary Project Management 4e
Chapter
MS Project
3
MS Project 2016 Introduction
Ribbon, Quick Access Toolbar, view panes, Zoom Slider, Shortcuts, Scheduling Mode Selector
Setting Up Your First Project
Auto schedule, start date, identifying information, summary row
Create Milestone Schedule
Key milestones, zero duration, must finish on, information
7
Set Up a Work Breakdown Structure (WBS)
Understand the WBS definitions and displays
Enter WBS Elements (tasks), Create the outline,
Insert WBS Code Identifier column, Hide or show subtasks detail
8
Using MS Project for Critical Path Schedules
Set Up the Project Schedule
Set or update the project start date, Define organization’s working and nonworking time
Build the Network Diagram and Identify the Critical Path
Enter tasks and milestones, edit the timescale, understand and define task dependencies, assign task
duration estimates, identify the critical path, understand the network diagram view
Display and Print Schedules
9
Define Resources
Resource views, max units, resource calendars
Assigning Resources
Basic assignment, modify an assignment
Identify Overallocated Resources
Resource usage and Detailed Gantt views together
Overallocated Resources
Finding overallocated resources, dealing with overallocations
Crashing a Critical Path Activity
10
Develop Bottom-up Project Budget
Assignment costs, task costs, various cost perspectives
Develop Summary Project Budget
12
Baseline the Project Plan
First time baseline, subsequent baselines, viewing variances
14
Using MS Project to Monitor and Control Projects
What Makes a Schedule Useful?
How MS Project recalculates based on reported actuals, current and future impacts of variances, define
the performance update process (who, what, when)
Steps to Update the Project Schedule
Acquire performance data, set and display status date, Enter duration-based performance data,
reschedule remaining work, revise future estimates
15
Close Project
Creating project progress reports, sharing reports, export a report to MS Excel, archive project work,
capture and publish lessons learned
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
PMBOK® Guide 6e Coverage in Contemporary Project Management 4e
The numbers refer to the text page where the process is defined.
Project management (PM) processes and knowledge areas 10–11
Project life cycle 7–10, 62–64
Projects and strategic planning 33–37
Organizational influences 102–110
Portfolio and program management 37–42
®
PMBOK Guide, 6th ed. Coverage
Knowledge
Areas
Project
Integration
Management
Initiating
Process
Group
Develop
Project
Charter
60–79
Planning Process Group
Develop Project Management Plan
409–410
Executing Process
Group
Monitoring &
Controlling
Process Group
Closing
Process
Group
Direct and Manage
Project Work 459–460
Manage Project
Knowledge 192–193,
504–508
Monitor and Control
Project Work 460–462
Perform Integrated
Change Control
229–232, 462–463
Close
Project
or Phase
503,
508–511
Project Scope
Management
Plan Scope Management 211–212
Collect Requirements 212–216
Define Scope 216–220
Create WBS 220–229
Validate Scope
500–501
Control Scope
475–476
Project
Schedule
Management
Plan Schedule Management 246
Define Activities 249–253
Sequence Activities 253–255
Estimate Activity Durations 255–258
Develop Schedule 259–267
Control Schedule
476–480
Project Cost
Management
Plan Cost Management 329–330
Estimate Costs 330–341
Determine Budget 342–344
Control Costs 345,
476–480
Project Quality
Management
Plan Quality Management 401–404
Manage Quality
404–406, 469–474
Control Quality
406–409, 469–474
Project
Resources
Management
Plan Resource Management 290–295
Estimate Activity Resources 290
Aquire Resources
138–141
Develop Team 141–157
Manage Team 157–161
Control Resources 476
Project Communications
Management
Plan Communications Management
188–192
Manage
Communications
193–199, 465–467
Monitor
Communications
467–468
Project Risk
Management
Plan Risk Management 360–366
Identify Risks 75, 366–368
Perform Qualitative Risk Analysis 75,
368–372
Perform Quantitative Risk Analysis
372–373
Plan Risk Responses 75, 373–377
Implement Risk
Responses 464–465
Monitor Risks
463–464
Project
Procurement
Management
Plan Procurement Management
431–433, 438–441
Conduct
Procurements
434–438
Control Procurments
441
Plan Stakeholder Engagement 184–186
Manage Stakeholder
Engagement 187–188
Monitor Stakeholder
Engagement 188
Project Stakeholder
Management
Identify
Stakeholders 75–77,
178–184
® Guide), 6th ed. (Newtown Square, PA: Project Management
Source: Adapted from A Guide to the Project Management Body of Knowledge (PMBOK
Institute, Inc., 2017): 31.
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Brief Contents
Preface xx
About the Authors xxix
PART
PART
PART
1
Organizing Projects
1
Introduction to Project Management
2
Project Selection and Prioritization 32
3
Chartering Projects 60
2
Leading Projects
4
Organizational Capability: Structure, Culture, and Roles 100
5
Leading and Managing Project Teams 136
6
Stakeholder Analysis and Communication Planning 176
3
Planning Projects
7
Scope Planning 210
8
Scheduling Projects
9
Resourcing Projects 286
2
244
10
Budgeting Projects
11
Project Risk Planning 358
12
Project Quality Planning and Project Kickoff 386
PART
4
328
Performing Projects
13
Project Supply Chain Management
14
Determining Project Progress and Results 456
15
Finishing the Project and Realizing the Benefits
Appendix
Appendix
Appendix
Appendix
Appendix
A
B
C
D
E
426
498
PMP and CAPM Exam Prep Suggestions 522
Agile Differences Covered 527
Answers to Selected Exercises 532
Project Deliverables 537
Strengths Themes As Used in Project Management
Index 539
[Available Online]
v
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Project Customer Tradeoff Matrix
1.2 Foundational Elements
Life Cycle and Development Approach
Elevator Pitch
2.4 Organizational Systems
3.4 Project Manager Competencies
Selecting Projects
Integration
Leader Roles and Responsibilities
Project Selection and Prioritization Matrix
Project Resource Assignment Matrix
4.1 Develop
Project Charter
Charter
Assumptions Log
4.2 Develop Project Management Plan
5.1 Plan
Scope
Management
Scope
5.2 Collect
Requirements
Requirements Documents
Scope
6.1 Plan
Schedule
Management
Schedule
Activities
7.1 Plan
Cost
Management
Quality
8.1 Plan
Quality
Management
Resources
9.1 Plan
Resource
Management
10.1 Plan
Communications
Management
Communication
12.1 Plan
Procurement
Management
Procurement
13.1 Identify
Stakeholders
Stakeholder
Register
Duration
Estimates
7.3 Determine
Budget
Network
6.3 Sequence
Activities
6.5 Develop
Schedule
Schedule Baseline
Cost Baseline
Quality
Mgt.
Plan
RACI
Team
Charter
Communications
Matrix
11.1 Plan
Risk
Management
Risk
Stakeholders
7.2 Estimate
Costs
Scope
Statement
Activity List
Milestone List
6.4 Estimate
activity
Durations
Cost
5.4 Create
WBS
9.2 Estimate
Activity
Resources
11.2 Identify
Risks
Risk Register
11.3 Perform
Qualitative
Risk Analysis
Bid
Documents
Make or Buy
Analysis
Resource Requirements
11.5 Plan
Risk
Responses
11.4 Perform
Quantitative
Risk Analysis
13.2 Plan
Stakeholder
Stakeholders
Engagement
Engagement Assessment Matrix
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Realizing
s
PM Plan Baselines Life Cycle
and Development Approach
4.5 Monitor and
Control
Project Work
4.3 Direct and Manage
Project Work
4.4 Manage Project
Knowledge
s
Analysis
Lessons
Learned
Register
4.7 Close Project Closure
Documents
or Phase
Customer
Feedback
Transition Plan
4.6 Perform
Integrated
Change Control
Retrospectives
Scope
Baseline with WBS
5.5 Validate
Scope
5.6 Control
Scope
6.6 Control
Schedule
Resource Histogram
Project Crashing
7.4 Control
Costs
Quality
Reports
8.2 Manage
Quality
8.3 Control
Quality
Scope
Backlog
Burn
Down/Up
Charts
Earned Value
Analysis
Quality
Measurements
9.3 Acquire
Resources
9.4 Develop
Team
Team
Assessments
Team
Assignments
9.6 Control
Resources
9.5 Manage
Team
10.2 Manage
Communications
Agendas
Minutes
Issues Log
Meeting Evaluation
10.3 Monitor
Communications Change
Requests
Progress Report
11.6 Implement
Risk Responses
11.7 Monitor
Risks
12.2 Conduct
Procurements
12.3 Control
Procurements
13.3 Manage
Stakeholder
Engagement
Source
Selection
Matrix
13.4 Monitor
Stakeholder
Engagement
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
Preface . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xx
About the Authors . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . xxix
PART
CHAPTER
1
Organizing Projects
1
Introduction to Project Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2
1.1 What Is a Project?
3
1.2 History of Project Management
5
1.3 How Can Project Work Be Described? 6
1.3a Projects versus Operations 6 / 1.3b Soft Skills and Hard Skills
and Responsibility 7 / 1.3d Project Life Cycle 7
7 / 1.3c Authority
1.4 Understanding Projects 10
1.4a Project Management Institute 10 / 1.4b Project Management Body of Knowledge
(PMBOK ) 10 / 1.4c The PMI Talent Triangle 11 / 1.4d Selecting and Prioritizing
Projects 14 / 1.4e Project Goals and Constraints 14 / 1.4f Defining Project Success
and Failure 15 / 1.4g Using Microsoft Project to Help Plan and Measure
Projects 16 / 1.4h Types of Projects 16 / 1.4i Scalability of Project Tools 17
®
1.5 Project Roles 17
1.5a Project Executive-Level Roles 18 / 1.5b Project Management-Level Roles
1.5c Project Associate-Level Roles 20
19 /
1.6 Overview of the Book 20
1.6a Part 1: Organizing and Initiating Projects 20 / 1.6b Part 2: Leading Projects
1.6c Part 3: Planning Projects 21 / 1.6d Part 4: Performing Projects 23
PMP/CAPM Study Ideas
Summary
23
24
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
25
26
Integrated Example Projects
27
Suburban Homes Construction Project
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
Endnotes
24
25
PMBOK Guide Questions
References
21 /
27
28
28
29
30
31
viii
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
CHAPTER
ix
2
Project Selection and Prioritization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 32
2.1 Strategic Planning Process 33
2.1a Strategic Analysis 33 / 2.1b Guiding Principles
Objectives 36 / 2.1d Flow-Down Objectives 37
34 / 2.1c Strategic
2.2 Portfolio Management 37
2.2a Portfolios 38 / 2.2b Programs 39 / 2.2c Projects and Subprojects 39 /
2.2d Assessing an Organization’s Ability to Perform Projects 42 / 2.2e Identifying
Potential Projects 42 / 2.2f Using a Cost-Benefit Analysis Model to Select
Projects 43 / 2.2g Using a Scoring Model to Select Projects 45 / 2.2h Prioritizing
Projects 48 / 2.2i Resourcing Projects 48
2.3 Securing Projects 49
2.3a Identify Potential Project Opportunities 50 / 2.3b Determine Which Opportunities to
Pursue 50 / 2.3c Prepare and Submit a Project Proposal 51 / 2.3d Negotiate to
Secure the Project 51
PMP/CAPM Study Ideas
Summary
52
52
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
53
53
PMBOK Guide Questions
Exercises
53
54
Integrated Example Projects
55
Casa DE PAZ Development Project
Semester Project Instructions
Endnotes
CHAPTER
56
56
Project Management in Action
References
52
57
58
59
3
Chartering Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 60
3.1 What Is a Project Charter?
62
3.2 Why Is a Project Charter Used?
3.3 When Is a Charter Needed?
63
64
3.4 Typical Elements in a Project Charter 65
3.4a Title 65 / 3.4b Scope Overview 65 / 3.4c Business Case 66 /
3.4d Background 66 / 3.4e Milestone Schedule with Acceptance Criteria 66 /
3.4f Risks, Assumptions, and Constraints 67 / 3.4g Resource Estimates 69 /
3.4h Stakeholder List 69 / 3.4i Team Operating Principles 69 / 3.4j Lessons
Learned 70 / 3.4k Signatures and Commitment 70
3.5 Constructing a Project Charter 70
3.5a Scope Overview and Business Case Instructions 70 / 3.5b Background
Instructions 71 / 3.5c Milestone Schedule with Acceptance Criteria
Instructions 72 / 3.5d Risks, Assumptions, and Constraints Instructions 75 /
3.5e Resources Needed Instructions 75 / 3.5f Stakeholder List Instructions 75 /
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
x
Contents
3.5g Team Operating Principles Instructions 77 / 3.5h Lessons Learned
Instructions 77 / 3.5i Signatures and Commitment Instructions 78
3.6 Ratifying the Project Charter
79
3.7 Starting a Project Using Microsoft Project 79
3.7a MS Project 2016 Introduction 80 / 3.7b Setting up Your First Project
3.7c Define Your Project 82 / 3.7d Create a Milestone Schedule 83
PMP/CAPM Study Ideas
Summary
88
88
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
89
90
Integrated Example Projects
91
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
References
Endnotes
PART
CHAPTER
2
88
89
89
PMBOK Guide Questions
Exercises
81 /
93
93
93
96
97
Leading Projects
4
Organizational Capability: Structure, Culture, and Roles . . . . . . . . . . . . . . . . . . . . . 100
4.1 Types of Organizational Structures 103
4.1a Functional 103 / 4.1b Projectized 104 / 4.1c Matrix
105
4.2 Organizational Culture and Its Impact on Projects 109
4.2a Culture of the Parent Organization 110 / 4.2b Project Cultural Norms
111
4.3 Project Life Cycles 111
4.3a Define-Measure-Analyze-Improve-Control (DMAIC) Model 112 / 4.3b Research and
Development (R&D) Project Life Cycle Model 113 / 4.3c Construction Project Life
Cycle Model 113 / 4.3d Agile Project Life Cycle Model 113
4.4 Agile Project Management 114
4.4a What Is Agile? 114 / 4.4b Why Use Agile? 114 / 4.4c What Is an Agile
Mindset? 114 / 4.4d What Are the Key Roles in Agile Projects? 115 / 4.4e How Do
You Start an Agile Project? 115 / 4.4f How Do You Continue an Agile Project?
115 / 4.4g What Is Needed for Agile to Be Successful? 116
4.5 Traditional Project Executive Roles 116
4.5a Steering Team 116 / 4.5b Sponsor 117 / 4.5c Customer
Projects Officer/Project Management Office 121
4.6 Traditional Project Management Roles 121
4.6a Functional Manager 121 / 4.6b Project Manager
119 / 4.5d Chief
122 / 4.6c Facilitator
4.7 Traditional Project Team Roles 126
4.7a Core Team Members 126 / 4.7b Subject Matter Experts
124
126
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
4.8 Role Differences on Agile Projects
PMP/CAPM Study Ideas
Summary
126
128
128
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
129
129
130
Integrated Example Projects
130
Casa DE PAZ Development Project
Semester Project Instructions
Endnotes
CHAPTER
131
131
Project Management in Action
References
128
129
PMBOK Guide Questions
Exercises
xi
132
134
135
5
Leading and Managing Project Teams . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 136
5.1 Acquire Project Team 138
5.1a Preassignment of Project Team Members 139 / 5.1b Negotiation for Project Team
Members 139 / 5.1c On-Boarding Project Team Members 140
5.2 Develop Project Team 141
5.2a Stages of Project Team Development 142 / 5.2b Characteristics of High-Performing
Project Teams 144 / 5.2c Assessing Individual Member Capability 147 /
5.2d Assessing Project Team Capability 148 / 5.2e Building Individual and Project
Team Capability 150 / 5.2f Establishing Project Team Ground Rules 153
5.3 Manage Project Team 157
5.3a Project Manager Power and Leadership 157 / 5.3b Assessing Performance of
Individuals and Project Teams 159 / 5.3c Project Team Management Outcomes
5.4 Relationship Building Within the Core Team
159
160
5.5 Managing Project Conflicts 161
5.5a Sources of Project Conflict 162 / 5.5b Conflict-Resolution Process and
Styles 163 / 5.5c Negotiation 164
5.6 Communication Needs of Global and Virtual Teams 166
5.6a Virtual Teams 166 / 5.6b Cultural Differences 166 / 5.6c Countries and Project
Communication Preferences 167
PMP/CAPM Study Ideas
Summary
167
168
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
168
168
169
PMBOK Guide Questions
Integrated Example Projects
170
170
Casa DE PAZ Development Project
Semester Project Instructions
171
171
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
xii
Contents
Project Management in Action
References
Endnotes
CHAPTER
172
174
175
6
Stakeholder Analysis and Communication Planning . . . . . . . . . . . . . . . . . . . . . . . . . 176
6.1 Identify Stakeholders 178
6.1a Find Stakeholders 179 / 6.1b Analyze Stakeholders
Stakeholders 183
180 / 6.1c Document
6.2 Plan Stakeholder Engagement 184
6.2a Creating a Stakeholder Engagement Assessment Matrix
Relationships with Stakeholders 185
6.3 Manage Stakeholder Engagement
187
6.4 Monitor Stakeholder Engagement
188
184 / 6.2b Planning to Build
6.5 Plan Communications Management 188
6.5a Purposes of a Project Communications Plan 188 / 6.5b Communications Plan
Considerations 189 / 6.5c Communications Matrix 191 / 6.5d Manage Project
Knowledge 192
6.6 Manage Communications 193
6.6a Determine Project Information Needs 193 / 6.6b Establish Information Retrieval and
Distribution System 193 / 6.6c Project Meeting Management 194 / 6.6d Issues
Management 197
PMP/CAPM Study Ideas
Summary
199
199
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
200
200
PMBOK Guide Questions
201
Integrated Example Projects
202
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
References
Endnotes
PART
CHAPTER
3
200
202
203
204
206
207
Planning Projects
7
Scope Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 210
7.1 Plan Scope Management
211
7.2 Collect Requirements 212
7.2a Gather Stakeholder Input and Needs
213
7.3 Define Scope 217
7.3a Reasons to Define Scope 217 / 7.3b How to Define Scope
Scope in Agile Projects 218
217 / 7.3c Defining
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
7.4 Work Breakdown Structure (WBS) 220
7.4a What Is the WBS? 220 / 7.4b Why Use a WBS? 221 / 7.4c WBS
Formats 222 / 7.4d Work Packages 224 / 7.4e How to Construct a WBS
7.5 Establish Change Control
Summary
239
Chapter Review Questions
Discussion Questions
239
240
241
Integrated Example Projects
241
Casa DE PAZ Development Project
Semester Project Instructions
CHAPTER
242
242
Project Management in Action
References
239
239
PMBOK Guide Questions
Exercises
232
237
Key Terms Consistent with PMI Standards and Guides
®
226
229
7.6 Using MS Project for Work Breakdown Structures (WBS)
7.6a Set Up a WBS in MS Project 232
PMP/CAPM Study Ideas
xiii
242
243
8
Scheduling Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 244
8.1 Plan Schedule Management
246
8.2 Purposes of a Project Schedule
247
8.3 Historical Development of Project Schedules
247
8.4 How Project Schedules Are Limited and Created
8.5 Define Activities
248
249
8.6 Sequence Activities 253
8.6a Leads and Lags 254 / 8.6b Alternative Dependencies
8.7 Estimate Activity Duration 255
8.7a Problems and Remedies in Duration Estimating
255
256 / 8.7b Learning Curves
8.8 Develop Project Schedules 259
8.8a Two-Pass Method 259 / 8.8b Enumeration Method
258
263
8.9 Uncertainty in Project Schedules 264
8.9a Program Evaluation and Review Technique
265 / 8.9b Monte Carlo Simulation
8.10 Show the Project Schedule on a Gantt Chart
268
266
8.11 Using Microsoft Project for Critical Path Schedules 268
8.11a Set up the Project Schedule 269 / 8.11b Build the Network Diagram and Identify
the Critical Path 270
PMP/CAPM Study Ideas
Summary
275
276
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
276
277
277
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
xiv
Contents
Exercises
®
278
PMBOK Guide Questions
280
Integrated Example Projects
281
Casa DE PAZ Development Project
Semester Project Instructions
283
Project Management in Action
References
Endnotes
CHAPTER
281
283
284
285
9
Resourcing Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 286
9.1 Abilities Needed When Resourcing Projects 288
9.1a The Science and Art of Resourcing Projects 288 / 9.1b Considerations When
Resourcing Projects 288 / 9.1c Activity- versus Resource-Dominated Schedules 289
9.2 Estimate Resource Needs
290
9.3 Plan Resource Management 290
9.3a Identify Potential Resources 291 / 9.3b Determine Resource Availability
9.3c Decide Timing Issues When Resourcing Projects 294
9.4 Project Team Composition Issues 295
9.4a Cross-Functional Teams 295 / 9.4b Co-Located Teams
Teams 295 / 9.4d Outsourcing 295
293 /
295 / 9.4c Virtual
9.5 Assign a Resource to Each Activity 296
9.5a Show Resource Responsibilities on RACI Chart 297 / 9.5b Show Resource
Assignments on Gantt Chart 297 / 9.5c Summarize Resource Responsibilities by Time
Period with Histogram 297
9.6 Dealing with Resource Overloads 300
9.6a Methods of Resolving Resource Overloads
9.7 Compress the Project Schedule 303
9.7a Actions to Reduce the Critical Path
Tracking 307
300
303 / 9.7b Crashing
304 / 9.7c Fast
9.8 Alternative Scheduling Methods 309
9.8a Critical Chain Project Management (CCPM) 309 / 9.8b Reverse Phase
Schedules 310 / 9.8c Rolling Wave Planning 310 / 9.8d Agile Project
Planning 310 / 9.8e Auto/Manual Scheduling 310
9.9 Using MS Project for Resource Allocation 311
9.9a Step 1: Defining Resources 311 / 9.9b Step 2: Set Up a Resource Calendar 312 /
9.9c Step 3: Assigning Resources 312 / 9.9d Step 4: Finding Overallocated
Resources 315 / 9.9e Step 5: Dealing with Overallocations 316 / 9.9f Crashing a
Critical Path Activity 317
PMP/CAPM Study Ideas
Summary
319
319
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
320
320
PMBOK Guide Questions
Exercises
320
321
322
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
Integrated Example Projects
324
Casa DE PAZ Development Project
Semester Project Instructions
Endnote
CHAPTER
324
325
Project Management in Action
References
xv
325
327
327
10
Budgeting Projects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 328
10.1 Plan Cost Management
329
10.2 Estimate Cost 330
10.2a Types of Cost 331 / 10.2b Accuracy and Timing of Cost Estimates 334 /
10.2c Methods of Estimating Costs 335 / 10.2d Project Cost Estimating Issues
10.3 Determine Budget 342
10.3a Aggregating Costs 342 / 10.3b Analyzing Reserve Needs
10.3c Determining Cash Flow 344
10.4 Establishing Cost Control
Summary
345 / 10.5b Develop Summary
349
349
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
350
351
352
Integrated Example Projects
353
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
References
Endnotes
CHAPTER
350
350
PMBOK Guide Questions
Exercises
342 /
345
10.5 Using MS Project for Project Budgets 345
10.5a Developing a Bottom-Up Project Budget Estimate
Project Budget 347
PMP/CAPM Study Ideas
338
354
354
354
356
356
11
Project Risk Planning . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 358
11.1 Plan Risk Management 360
11.1a Roles and Responsibilities
362 / 11.1b Categories and Definitions
11.2 Identify Risks 366
11.2a Information Gathering 366 / 11.2b Reviews
Relationships 368 / 11.2d Risk Register 368
362
367 / 11.2c Understanding
11.3 Risk Analysis 368
11.3a Perform Qualitative Risk Analysis 368 / 11.3b Perform Quantitative Risk
Analysis 372 / 11.3c Risk Register Updates 373
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
xvi
Contents
11.4 Plan Risk Responses 373
11.4a Strategies for Responding to Risks
PMP/CAPM Study Ideas
Summary
373 / 11.4b Risk Register Updates
377
378
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
379
379
380
Integrated Example Projects
381
Casa DE PAZ Development Project
Semester Project Instructions
Endnotes
CHAPTER
381
382
Project Management in Action
References
378
379
PMBOK Guide Questions
Exercises
377
382
384
384
12
Project Quality Planning and Project Kickoff . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 386
12.1 Development of Contemporary Quality Concepts 388
12.1a Quality Gurus 388 / 12.1b Total Quality Management/Malcolm Baldrige
12.1c ISO 9001:2008 390 / 12.1d Lean Six Sigma 390
389 /
12.2 Core Project Quality Concepts 392
12.2a Stakeholder Satisfaction 393 / 12.2b Process Management 394 / 12.2c FactBased Management 396 / 12.2d Fact-Based Project Management Example 398 /
12.2e Empowered Performance 399 / 12.2f Summary of Core Concepts 400
12.3 Plan Quality Management 401
12.3a Quality Policy 401 / 12.3b Quality Management Plan Contents 403 /
12.3c Quality Baseline 404 / 12.3d Process Improvement Plan 404
12.4 Manage Quality
404
12.5 Control Quality
406
12.6 Cost of Quality
409
12.7 Develop Project Management Plan 409
12.7a Resolve Conflicts 409 / 12.7b Establish Configuration Management
12.7c Apply Sanity Tests to All Project Plans 410
12.8 Kickoff Project 410
12.8a Preconditions to Meeting Success
411 / 12.8b Meeting Activities
12.9 Baseline and Communicate Project Management Plan
410 /
411
413
12.10 Using MS Project for Project Baselines 413
12.10a Baseline the Project Plan 413 / 12.10b Create the First Time Baseline 414 /
12.10c Subsequent Baselines 414 / 12.10d Viewing Baselines and Variances 415
PMP/CAPM Study Ideas
Summary
416
417
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
417
418
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
Discussion Questions
®
418
PMBOK Guide Questions
Exercises
418
419
Integrated Example Projects
420
Casa DE PAZ Development Project
Semester Project Instructions
Endnotes
PART
CHAPTER
4
420
420
Project Management in Action
References
xvii
421
423
424
Performing Projects
13
Project Supply Chain Management . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 426
13.1 Introduction to Project Supply Chain Management 428
13.1a SCM Components 430 / 13.1b SCM Factors 430 / 13.1c SCM
Decisions 430 / 13.1d Project Procurement Management Processes 431
13.2 Plan Procurement Management 431
13.2a Outputs of Planning 431 / 13.2b Make-or-Buy Decisions
432
13.3 Conduct Procurements 434
13.3a Sources for Potential Suppliers 434 / 13.3b Approaches Used When Evaluating
Prospective Suppliers 435 / 13.3c Supplier Selection 436
13.4 Contract Types 438
13.4a Fixed-Price Contracts 439 / 13.4b Cost-Reimbursable Contracts
13.4c Time and Material (T&M) Contracts 440
13.5 Control Procurements
441
13.6 Improving Project Supply Chains 441
13.6a Project Partnering and Collaboration 442 / 13.6b Third Parties
Purchasing 447 / 13.6d Sourcing 447 / 13.6e Logistics 447 /
13.6f Information 448
PMP/CAPM Study Ideas
Summary
448
Chapter Review Questions
Discussion Questions
®
449
450
451
Integrated Example Projects
451
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
Endnotes
449
449
PMBOK Guide Questions
References
447 / 13.6c Lean
448
Key Terms Consistent with PMI Standards and Guides
Exercises
440 /
452
452
452
453
454
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
xviii
Contents
CHAPTER
14
Determining Project Progress and Results . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 456
14.1 Project Balanced Scorecard Approach
458
14.2 Internal Project Issues 459
14.2a Direct and Manage Project Work 459 / 14.2b Monitor and Control Project
Work 460 / 14.2c Monitoring Project Risk 463 / 14.2d Implement Risk
Responses 464 / 14.2e Manage Communications 465 / 14.2f Monitor
Communications 467
14.3 Customer Issues 469
14.3a Manage and Control Quality
469 / 14.3b Control Scope
475
14.4 Financial Issues 476
14.4a Control Resources 476 / 14.4b Control Schedule and Costs
Value Management for Controlling Schedule and Costs 476
476 / 14.4c Earned
14.5 Using MS Project to Monitor and Control Projects 480
14.5a What Makes a Schedule Useful? 480 / 14.5b How MS Project Recalculates the
Schedule Based on Reported Actuals 481 / 14.5c Current and Future Impacts of Time
and Cost Variance 481 / 14.5d Define the Performance Update Process 481 /
14.5e Steps to Update the Project Schedule 482
14.6 Replanning If Necessary
487
PMP/CAPM Study Ideas
488
Summary
488
Key Terms Consistent with PMI Standards and Guides
Chapter Review Questions
Discussion Questions
®
489
489
PMBOK Guide Questions
Exercises
490
491
Integrated Example Projects
492
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
References
Endnotes
CHAPTER
488
493
493
494
496
497
15
Finishing the Project and Realizing the Benefits . . . . . . . . . . . . . . . . . . . . . . . . . . . . 498
15.1 Validate Scope
500
15.2 Terminate Projects Early
501
15.3 Close Project 503
15.3a Write Transition Plan 503 / 15.3b Knowledge Management
the Closeout Report 508
504 / 15.3c Create
15.4 Post-Project Activities 509
15.4a Reassign Workers 509 / 15.4b Celebrate Success and Reward Participants
15.4c Provide Ongoing Support 510 / 15.4d Ensure Project Benefits Are
Realized 510
509 /
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Contents
15.5 Using MS Project for Project Closure
15.5a Creating Project Progress Reports
PMP/CAPM Study Ideas
Summary
511
511 / 15.5b Archiving Project Work
515
Chapter Review Questions
Discussion Questions
516
517
Integrated Example Projects
517
Casa DE PAZ Development Project
Semester Project Instructions
Project Management in Action
References
Endnotes
515
515
516
PMBOK Guide Questions
Exercise
512
515
Key Terms Consistent with PMI Standards and Guides
®
xix
518
518
518
520
521
Appendix A PMP and CAPM Exam Prep Suggestions . . . . . . . . . . . . . . . . . . . . . . . . . . 522
Appendix B Agile Differences Covered . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 527
Appendix C Answers to Selected Exercises . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 532
Appendix D Project Deliverables . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 537
Appendix E Strengths Themes As Used in Project Management . . . . [Available Online]
Index . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 539
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Preface
While project managers today still need to use many techniques that have stood the test
of several decades, they increasingly also must recognize the business need for a project,
sort through multiple conflicting stakeholder demands. They must know how to deal
with rapid change, a myriad of communication issues, global and virtual project teams,
modern approaches to quality improvement, when to tailor their project management
approach to include methods and behaviors from Agile, and many other issues that are
more challenging than those in projects of the past.
Contemporary project management utilizes the tried-and-true project management
techniques along with modern improvements such as the most current versions of Microsoft Project Professional 2016, the sixth edition of the Guide to the Project Management
Body of Knowledge (PMBOK Guide), and many approaches derived from adaptive
(Agile) project management. Contemporary project management also uses many tools
and understandings that come from modern approaches to quality and communications,
expanded role definitions, leadership principles, human strengths, and many other
sources. Contemporary project management is scalable, using simple versions of important techniques on small projects and more involved versions on more complex projects.
®
®
Distinctive Approach
This book covers contemporary project management topics using contemporary project
management methods. For example, when considering the topic of dealing with multiple
stakeholders, every chapter was reviewed by students, practitioners, and academics. This
allowed simultaneous consideration of student learning, practitioner realism, and academic research and teaching perspectives.
The practical examples and practitioner reviewers came from a variety of industries, different parts of the world, and from many sizes and types of projects in order to emphasize
the scalability and universality of contemporary project management techniques.
New to This Edition
Core, behavioral, and technical learning objectives. We have expanded the number
of learning objectives and classified them as core, behavioral, or technical. About
half of the objectives are core: what we believe every student of project management
should learn. A professor could teach a solid project management introductory class
by deeply using only the core objectives. On the other hand, there are measurable
student objectives for either a behavioral or a technical approach. All suggested student assignments and questions are tied specifically to one of the learning objectives.
A professor could use this text for a two-semester sequence that emphasizes both indepth behavioral and technical approaches.
Videos. Exclusively available to those using the MindTap product for this book, we
have created dozens of short (average time, five minutes) videos to show the art of
many of the techniques. These demonstrate the use of many of the techniques in a
by-hand or spreadsheet fashion as well as using Microsoft Project 2016. Several
questions that can be assigned to students are included with the videos that
xx
Copyright 2019 Cengage Learning. All Rights Reserved. May not be copied, scanned, or duplicated, in whole or in part. Due to electronic rights, some third party content may be suppressed from the eBook and/or eChapter(s).
Editorial review has deemed that any suppressed content does not materially affect the overall learning experience. Cengage Learning reserves the right to remove additional content at any time if subsequent rights restrictions require it.
Preface
xxi
demonstrate how to use Microsoft Project to complement learning. Answers (sometimes definitive, sometimes representative, depending on the nature of the technique) are included in the instructor’s manual (IM).
Extensive flowchart to help the sixth edition of the PMBOK Guide come to life.
All sixth edition PMBOK Guide knowledge areas, processes, and process groups,
plus major deliverables from each process and the primary workflows between
them, are specifically included in an interactive, color-coded flowchart that is
included in full inside the back cover of the text. We also start each chapter by
showing the portion of the flowchart that is covered in that chapter. We now use
definitions both from the PMBOK Guide, Sixth Edition and also from more than
a dozen Project Management Institute specialized Practice Guides and Standards.
The end of each chapter contains specific suggestions for PMP and CAPM test
preparation pertaining to the chapter’s topics plus ten PMBOK Guide-type questions that are typical of what would be seen on PMP and CAPM exams.
Appendix A gives general study suggestions for the CAPM and PMP exams.
Project deliverables. A list of 38 project deliverables that can be used as assignments
for students and in-class exercises are included in Appendix D. Each deliverable is
specifically tied to a student learning objective and shown on the PMBOK Guide
flowchart. About half of these are core, while the others are behavioral or technical.
Examples of completed deliverables are included in the text. Teaching suggestions
and grading rubrics are included in the IM. Appendix D identifies the type of objective, chapter covered, and PMBOK Guide process, knowledge area, and process
group in which the deliverable is typically created on a real project.
Substantial increase in Agile coverage. Agile techniques and methods are considered much more often than even three years ago. As such, many experienced project
manager...
Purchase answer to see full
attachment