1. Calculate the direct cost of labor for a project team member using the following data:
Hourly rate: $40/hr
Hours needed: 80
Overhead rate: 40%
To calculate Direct Cost of Labor:
80 𝑥 $40 = $3,200
Since the overhead costs are not included in direct cost of labor.
To get the overhead cost;
$3,200 𝑥 0.40 = $1280
To calculate Total Direct Costs.
We add $3,200 + $1280 = $𝟒, 𝟒𝟖𝟎