SNHU Negative Cost Variance Worksheet

User Generated

gntyvsr08

Writing

Southern New Hampshire University

Description

Assume you are on a project management team along with four other team members. Your project manager has given the team a report showing negative cost variance and asked the team to meet to discuss the causes and some possible ways to address it.

Before starting, the project manager wants to make sure that everyone has a good understanding of negative cost variance. The project manager turns to you and asks, "What does negative cost variance mean to you?" Provide an answer to that question and then elaborate by explaining how negative cost variance can be addressed to bring the project back on budget. Would you compromise on scope or schedule or possibly something else? Discuss your reasoning and support it with PMI® principles.

Explanation & Answer:
3 pages
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

please find the attached file. i look forward to working with you again. good bye

Running head: NEGATIVE COST VARIANCE

Name
Institution
Course
Tutor
Date

1

NEGATIVE COST VARIANCE

2

Cost variance shows a project’s financial performance by calculating the mathematical
difference the Actual Cost of Work Performed (ACWP) from the Budgeted Cost of Work
Performed (BCWP). A negative cost variance shows negative figures in the occurrence of
spending more on the project than the budget allowed. This can have bad ramifications to the
business when too much money is spent on production and the company ca...