PJM 330 CSU Portfolio Project Simulation Analysis Paper

User Generated

wbangunazuhgpuvaf

Business Finance

pjm 330

California State University Global Campus

PJM

Description

Each part of this project is important and must be completed on time, and Part 3 is due this week.

Part 3: Your assessment should be well structured, like all project management communications. Use the following outline as section headings in your paper to provide structure. Also, make good use of bulleted lists, numbered lists, and tables to further provide structure and clearly communicate information.

  • Introduction: Provide background and tell the reader what to expect from the paper.
  • Key decisions made: Describe a few of the decisions made in the simulation that were critical to the overall success or failure of the project.
  • Lessons learned: Use subheadings and address successes, issues, and actions to consider in the future when faced with similar challenges.
  • Learning-curve benefits: Based on the key decisions made and lessons learned, explain how the learning-curve theory would benefit similar projects in the future.
  • Best practices: Compile a list of three best practices that can be applied to similar projects in the future.

Unformatted Attachment Preview

Running Head: DOUBLE MASTERS SIMULATION SUMMARY 1 Double Masters Simulation Summary Colorado State University- Global Campus Double Masters Simulation Summary DOUBLE MASTERS SIMULATION SUMMARY 2 The Double Masters Simulation presented an instructive learning tool and a real-life understanding of project management. This simulation allowed an opportunity to obtain project management skills through the use of a virtual platform. After completing the simulation, a project scorecard, found in Appendix 1, was produced, which supplied an outline for each assessment item that was scored. This document intends to provide a summary of the areas I was unsuccessful in executing the project. Decisions and Questions As displayed in the scorecard in Appendix 1, the highest score achievable was 40; the achieved score was 33. Responses were scored good, fair, and poor. There was a total of 20 decisions with 13 good responses, three fair responses, and four poor responses. The first question that received a fair assessment was in regards to what type of contract was used for the localization vendors. I selected cost price plus incentive fees after reviewing the fee schedule within the contract. I choose this option because the fee per task was listed in the spreadsheet and stated a 10% fee was included. However, time and material was the correct answer. After receiving feedback within the simulation, I reviewed the fee schedule once again and then understood why this was the contract type used. The next question that resulted in a fair assessment was responding to Mr. Prince as to why the decision was made to not move forward with the Spanish localization. I chose to respond to Mr. Prince's email by explaining the steps taken into consideration when deciding to decline the project, including NPV, payback period, IRR, and resource constraints. However, I later learned and agreed with the decision that I should have also proposed solutions on how to work together in the future, helping smooth the situation, rather than creating tension. The final question that received a fair assessment was how my VAC/EAC would be affected due to the $9,000 back charge. I chose that my EAV/VAC would DOUBLE MASTERS SIMULATION SUMMARY 3 be negatively affected. I was under the assumption that we were initially responsible for the training costs, and since we did not fulfill the training, we were back charged. However, this was incorrect as management reserves are in place to pay for costs unrelated to the cost baseline. The four poor decisions that were made due to my lack of verifying before deciding. The first decision that received a poor assessment was the choice to replace a team member during his vacation time. The simulation stated that this team member did not have any work due during this time, and he would be available to take phone calls and answer emails. However, with having no professional project management experience, I chose to have someone take his place while he was out of the office. I made this decision to have support in the office just in case there was an issue that arose that the team member on vacation could not handle. However, the decision should not have been escalated to avoid conflict. The second decision that received a poor assessment was how should the over project work performance be reported. My decision to this scenario was to report with EAC, VAC, CPI, Gantt Chart tasks, risks. This decision was made incorrectly because I failed to reference my course notes. EAC and VAC are not helpful in reporting current work performance but used to forecast budget at completion. Also, the Gantt Chart provides too much detail for a report to senior management. The correct answer for this scenario would be to report using CPI, SPI, milestone charts, and risks. CPI “measures the value of work completed compared to the actual cost spent”(Usmani, 2019). SPI shows how the project is progressing, compared to the planned schedule. Again, this decision was poorly made as a result of me not checking my course notes. The last two poor assessments were related to forecasting the final budget of the project and to attend the launch party or archive records. I made the decision to use actual cost. However, VAC/EAC needed to be used to forecast the budget at completion. Lastly, I chose to archive records because a launch party sounded too DOUBLE MASTERS SIMULATION SUMMARY 4 good. However, records are archived throughout the project as deliverables are completed. Software typically does this automatically. Mail Read The mail read had a possible score of five; I achieved a score of three. After reviewing the scorecard, points were last in this category because of the lack of mail that was read. I failed to read 49 messages. Many of these messages were depicted as audio in the simulation. Also, many of these messages did not receive information to make decisions or answer questions, so I did not feel the need to read them. However, it is important that a project manager reviews all communications, as they could provide important information. Scheduled Completion Date The scorecard in Appendix 1 shows that I achieved a 17.5 out of a possible 25. The scorecard does not explain why points were lost in this section, but I can assume it was due to an overrun schedule. This was the most challenging part of the simulation for me. I had the opportunity to edit the schedule and costs for each task. It was not very easy to align the schedule with all of the involved national holidays. I would assume in a real project, multiple members of the team would be involved in creating a schedule this complex. Percent of Budget Used and Budget Requests In this area, the relationship of the cost schedule and risk was depicted. The risk register offered an opportunity to see how contingency reserves are set and how they are allocated. Project managers control the contingency reserve, therefore allowing them to use it when risk occurs (Usmani, 2019). I was also able to see how management reserves are calculated as an overall percentage of the cost baseline. It is crucial for a project manager to analyze all possibilities of DOUBLE MASTERS SIMULATION SUMMARY 5 risks, which then can be transferred into contingency and management reserves. These reserves offer the project a barrier against risk. Conclusion This project management simulation provided great insight to a real-world project. It is great to read all of the course material and learn the information, but it is much more useful when it can be applied. This simulation also gave feedback in scenarios that were incorrectly answered, which is important in understanding why something should have been done a certain way. The feedback provided also showed me areas where I need to focus. References Usmani, F. (2019, December 5). Schedule Performance Index (SPI) & Cost Performance Index DOUBLE MASTERS SIMULATION SUMMARY 6 (CPI). Retrieved from https://pmstudycircle.com/2012/05/schedule-performance-index-spi-and-cost-performanc e-index-cpi/ Usmani, F. (2019, October 22). Contingency Reserve vs Management Reserve. Retrieved from https://pmstudycircle.com/2012/02/contingency-reserve-vs-management-reserve/ DOUBLE MASTERS SIMULATION SUMMARY 7 Appendix Appendix 1
Purchase answer to see full attachment
Explanation & Answer:
7 pages
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Let me know where you need further help

OUTLINE
Introduction
Body
Conclusion
References


Running Head: DOUBLE MASTER SIMULATION ANAYLSIS

Double Master Simulation Analysis

Name
Institution Affiliation
Course
Date

1

DOUBLE MASTER SIMULATION ANAYLSIS

2

Master Simulation Analysis
Introduction
The economic stability of an organization, stakeholder’s satisfaction and optimum
utilization of the available resources within the company are highly dependent on project
management within that organization. As a result, in the contemporary business setting where
the profitability and continuity of an organization are paramount, the demand for project
managers is on the rise (Cardona-Meza & Olivar-Tost, 2017). As the project management Body
of Knowledge (PMBOK), 2013 outlays, project management is an interim project inhibited by
cost, scope, and time, and the project managers are equipped with communication skills,
optimization, and organization, that they bring to the table (Double Masters, 2019).
Consequently, the acquiring process of these skills and knowledge to effectively coordinate
and monitor projects is an essential process; however, prone to a diverse range of challenges.
Some of the significant challenges of the field is learning the art of optimizing the allocation
of necessary inputs and integrating them to meet the predefined objectives. Also, as the field
encompasses a broad range of arising challenges, with each project exhibiting its own set of
challenges and the efficiency of the project manager in solving and handling those challenges
both proactively and reactively, where necessary is vital for the completion of a given project.
In that light, the integration and use of Double Masters Stimulation in the learning process
offering a real-world experience of a project manager on a large scale project where one is
responsible for managing the budget, schedule, human resources, interactions with the
stakeholders and decision making across board offered vital insights and experience on the
‘real world’ of the field (Double Masters, 2019). By that token, this paper will, therefore, delve
into giving an analysis of the double master Stimulation, focusing on the decisions made and
their effect on the overall state of the project and extensively look into the lessons learned

DOUBLE MASTER SIMULATION ANAYLSIS

3

addressing the success, issues, and actions to consider in future when encountered with similar
situations.
Decisions making and Overall effect of the project.
i. The contract for localization Vendors
The deployment of localization vendors in a project requires several considerations and
decisions to be made. Among them being location, quality process, technology options, cost
and schedule, type of partner, and contract terms. In the simulation, one of the decisions made
was in line with the kind of contract used for the vendors. At this moment, I decided to choose
cost price and initiative fees after reviewing the fee schedule in the agreement. My choice was
aligned to the 10% fee per task included in the spreadsheet. However, the most effective option,
in this case, ought to have been time and material. Therefore, this decision attracted a fair
assessment in the stimulation hence averagely contributing to the overall state of the project.
ii. Communication with the stakeholders
Communication plays an integral role in the success or failure of a project. It’s through
communication that one can express their feeling a...


Anonymous
Great! Studypool always delivers quality work.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4

Related Tags