Determine CPI on a project

Business & Finance
Tutor: None Selected Time limit: 1 Day

If the CPI on a project is .85 and EV is $10,000, what must the AC be?

Aug 5th, 2014

CPI = EV/AC

or AC = EV/CPI = 10000/0.85 =11764.71

AC= Actual cost =$11764.71 approx $11765