Business Finance
Earned Value Calculations

Question Description

The original plan for the project was for it to last one year at a cost

of $100,000. Using the following information, calculate SPI, ETC, and EAC:

Planned value = $45,000

Earned Value  = $37,000

CV = - $12,000

SPI 

ETC

      EAC

Final Answer

SPI = EV/PV=37000/45000 =0.822

CV= -12000 =EV-AC= 37000-AC

AC = 37000-(-12000)=49000

CPI =37000/49000= 0.7551

Assumption 1: Cost over run not one time

EAC = BAC/CPI =100000/0.7551 =132432.43

Assumption 2: Cost overrun onetile

EAC= AC+(BAC-EV)= 49000+(100000-37000)=112000

ETC =EAC -AC

Assumption 1 

ETC= 132432.43- 49000=83432.43

Assumption 2

ETC =112000-49000=63000

There are other assumptions too.

madhavant (2757)
University of Virginia

Anonymous
Solid work, thanks.

Anonymous
The tutor was great. I’m satisfied with the service.

Anonymous
Goes above and beyond expectations !

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors