Earned Value Calculations

label Business
account_circle Unassigned
schedule 1 Day
account_balance_wallet $5

The original plan for the project was for it to last one year at a cost

of $100,000. Using the following information, calculate SPI, ETC, and EAC:

Planned value = $45,000

Earned Value  = $37,000

CV = - $12,000

SPI 

ETC

      EAC

Aug 5th, 2014

SPI = EV/PV=37000/45000 =0.822

CV= -12000 =EV-AC= 37000-AC

AC = 37000-(-12000)=49000

CPI =37000/49000= 0.7551

Assumption 1: Cost over run not one time

EAC = BAC/CPI =100000/0.7551 =132432.43

Assumption 2: Cost overrun onetile

EAC= AC+(BAC-EV)= 49000+(100000-37000)=112000

ETC =EAC -AC

Assumption 1 

ETC= 132432.43- 49000=83432.43

Assumption 2

ETC =112000-49000=63000

There are other assumptions too.

Aug 5th, 2014

Did you know? You can earn $20 for every friend you invite to Studypool!
Click here to
Refer a Friend
...
Aug 5th, 2014
...
Aug 5th, 2014
Sep 20th, 2017
check_circle
Mark as Final Answer
check_circle
Unmark as Final Answer
check_circle
Final Answer

Secure Information

Content will be erased after question is completed.

check_circle
Final Answer