Earned Value Calculations

Business & Finance
Tutor: None Selected Time limit: 1 Day

The original plan for the project was for it to last one year at a cost

of $100,000. Using the following information, calculate SPI, ETC, and EAC:

Planned value = $45,000

Earned Value  = $37,000

CV = - $12,000

SPI 

ETC

      EAC

Aug 5th, 2014

SPI = EV/PV=37000/45000 =0.822

CV= -12000 =EV-AC= 37000-AC

AC = 37000-(-12000)=49000

CPI =37000/49000= 0.7551

Assumption 1: Cost over run not one time

EAC = BAC/CPI =100000/0.7551 =132432.43

Assumption 2: Cost overrun onetile

EAC= AC+(BAC-EV)= 49000+(100000-37000)=112000

ETC =EAC -AC

Assumption 1 

ETC= 132432.43- 49000=83432.43

Assumption 2

ETC =112000-49000=63000

There are other assumptions too.

Aug 5th, 2014

Studypool's Notebank makes it easy to buy and sell old notes, study guides, reviews, etc.
Click to visit
The Notebank
...
Aug 5th, 2014
...
Aug 5th, 2014
May 28th, 2017
check_circle
Mark as Final Answer
check_circle
Unmark as Final Answer
check_circle
Final Answer

Secure Information

Content will be erased after question is completed.

check_circle
Final Answer