Question Description

I’m studying and need help with a Business question to help me learn.

A fence cost $1759, material cost $838. If you are paying 3 employees $6 per hour, and fence installation requires 29 hours when all employees are working. How much is wages? What will be your gross profit on the job? Round to nearest cent

Student has agreed that all tutoring, explanations, and answers provided by the tutor will be used to help in the learning process and in accordance with Studypool's honor code & terms of service.

Final Answer

Fence Cost  1759

Materials Cost     838

Wages  3*6*29 =522

Gross Profit   1759 –(838+522) =1759-1360 =399

Wages = $522