IT 625 SNHU Drafting Conflict Resolution Research Paper

User Generated

Nawlyn

Business Finance

IT 625

Southern New Hampshire University

IT

Description

Milestone One of your final project, a draft of the conflict resolution plan.


The conflict resolution plan will allow you the opportunity to apply the leadership, communication, and collaboration strategies you have learned during this course to a real-world situation. IT projects, like any other projects, can go off course for a variety of reasons, causing stress and strife in project teams. Given the Medical Informatics case study you have analyzed, construct a conflict resolution plan that addresses the various points of conflict within the project team. You will be writing this plan for your management group. Analyze the case and recommend strategies for managing conflict, communication, and strengthening the team. Your plan should address team dynamics, conflict resolution leadership, and motivation and confidence.

MUST HAVE MICROSOFT PROJECT AS WELL.

Unformatted Attachment Preview

IT 625 Final Project Milestone One Guidelines and Rubric Conflict Resolution Plan Draft Note: In order to successfully complete this project, you will need to carefully review the Final Project Guidelines and Rubric document and the Medical Informatics case study documents, located in the Assignments section of the course. Overview: In this milestone, you will analyze the Medical Informatics case study in order to complete a draft of the conflict resolution plan. The detailed guidelines for what should be included in your conflict resolution plan draft are outlined below. You should use the headings provided in the outline as headings in your draft to ensure that you have considered all of the required elements. The purpose of these milestones is to provide the opportunity to complete pieces of your final project through the course of the term, and obtain instructor feedback as part of grading that you can then apply to your final submission. Keep in mind that your final project, submitted in Module Nine, will be composed of the information you have gathered in each of the five milestones, crafted into a comprehensive, cohesive, well-written, and professional project proposal. Background: IT project managers are often called to manage new projects, or to assume leadership over troubled projects. In this course, you will have the opportunity to resolve conflict within project teams for the Medical Informatics case study, determine strategies to improve the outcome of the project, and deliver several documents that will allow you to develop the skills necessary to become a successful IT project manager. For your final project, you will analyze the Medical Informatics case study, which portrays a troubled information technology project, a project team experiencing conflict, and specific financial and timeline requirements. From this analysis you will determine the extent to which corrective action must be taken and establish strategies for mitigating conflict and managing change within the team. The conflict resolution plan will allow you the opportunity to apply the leadership, communication, and collaboration strategies you have learned during this course to a real-world situation. IT projects, like any other projects, can go off course for a variety of reasons, causing stress and strife in project teams. Given the case you have analyzed, construct a conflict resolution plan that addresses the various points of issue within the project team. You will be writing this plan for your management group. For the purposes of this milestone, you will complete a draft only. Your instructor will provide feedback, which you can incorporate into your final project due in Module Nine. Analyze the Medical Informatics case study and recommend strategies for managing conflict, communication, and strengthening the team. Specifically, the following critical elements must be addressed: A. Team Dynamics: Analyze the team structure, dynamics, and conflict. Things to consider include: 1. The roles and titles, reporting structure, and history of the team 2. Stage of the five-stage team development model this team is in (forming, storming, norming, performing, adjourning) 3. Cause of conflict 4. Skills the team is lacking based on their roles B. Conflict Resolution Leadership: Recommend appropriate leadership strategies to resolve the conflict within the team. Consider the following: 1. Leadership style for current stage of the team development (guiding, coaching, structuring, directing) 2. How to determine appropriate skills (soft and hard) for each role 3. A strategy to employ to resolve the conflict (assertiveness, accommodation, avoidance, or compromise) C. Motivation and Confidence: Recommend strategies for motivating and strengthening that will allow you to develop a cohesive information technology team that will deliver high-performance results and add business value. Provide support for your recommendations. Guidelines for Submission: This draft must follow these formatting guidelines: double spacing, 12-point Times New Roman font, one-inch margins, with APA citations only if outside sources are cited. There is no minimum length for this draft; however, it should address all of the critical elements listed above. Rubric Critical Elements Team Dynamics Proficient (100%) Accurately analyzes the team structure, dynamics, and conflict Conflict Resolution Recommends appropriate Leadership leaderships strategies to resolve conflict Motivation and Confidence Recommends strategies for motivating and strengthening the team that are appropriate based on supporting information Articulation of Response Submission has no major errors related to citations, grammar, spelling, syntax, or organization Needs Improvement (75%) Analyzes the team structure, dynamics, and conflict, but with gaps in accuracy or detail Recommends leadership strategies to resolve conflict, but recommendations are not appropriate for the team Recommends strategies for motivating and strengthening the team, but accompanying explanations are not supportive of recommendations or lack detail Submission has major errors related to citations, grammar, spelling, syntax, or organization that negatively impact readability and articulation of main ideas Not Evident (0%) Does not analyze the team structure, dynamics, and conflict Value 30 Does not recommend leadership strategies to resolve conflict 30 Does not describe recommended motivational strategy to set team expectations 30 Submission has critical errors related to citations, grammar, spelling, syntax, or organization that prevent understanding of ideas Total 10 100% IT 625 Final Project Case Study: Medical Informatics Background Medical Informatics, a leading health services company, embarked on a new product development project. Medical Informatics needs to expand its clinical data warehouse (CDW) to ingest third-party data feeds from wellness vendor and onsite clinic data to incorporate this information to downstream employer group analytics and reporting processes. This expansion will also be used to develop new activity reports to message value on these products. The nature of the company’s business is that it operates in an extremely competitive environment that necessitates fast delivery to market so as to prevent competitor companies from gaining dominant market share with similar competitive products. Therefore, the key success factors of the project were time to market and quality. Cost of delivery was not a major concern. Scope The scope of the project was to create a modular software package to handle wellness vendor data to ensure appropriate preventative care is being tracked for members, including the systems changes, the vendor wellness database tables, and wellness vendor reporting. The project was divided into modules consisting of: wellness DB tables, promote tables, and wellness vendor reporting. A project manager was appointed, but has since left due to personal reasons. Time Scales The launch date was set as December 21, 2017. The product had to be ready for launch on this date, as all the marketing material would reflect this date and the launch had to precede the launch of similar products from competitors. The project kickoff was May 5, 2017. The tasks that had been completed prior to May 5, 2017 were the business case compilation and approval and the project team establishment. Technology The systems development was to be done using the MS Visual Studio programming language and SQL environment, which was new to the development team. The developers were sent on MS Visual Studio programming training two weeks prior to the project start. The developers were used to working in a Java programming environment and had not worked with any MS-oriented languages before. The new wellness vendor reports will integrate into the existing system located behind the intranet. These new reports, unlike the existing reports, will utilize both SQL Server and Teradata. SQL Server will control the security access and parameter selection for the reports. The application will then send the selected parameters to Teradata in order to populate the body of the report. Infrastructure Database Servers  MS SQL Server 2008 R2  Teradata 14 Reporting Servers  The system will use an SSRS deployment server. Development Tools    MS Visual Studio 2008 Shell SQL Server Business Intelligence Development Studio SQL Server Management Studio Business Requirements The current application will display the wellness vendor reports. The system generates SQL Server Reporting Services (SSRS) reports based on user-selected parameters. Users can choose to view reports in three formats: Excel 97-2003 (XLS), Portable Document Format (PDF), or Comma Separated Value (CSV). The exported data within Excel or CSV files will contain “user-friendly” headers and not database column headers. Scripts will execute on a weekly basis to import the following vendor sources into the target system:  Chip Rewards  Spire Scripts will execute on a monthly basis to import the following vendor sources into the target system: MDLive. Case Study Summary of Events Business Case Development The product development department developed the business case for the proposed new product, including projected cost/benefit analysis based on previous similar products and current market share. The business case was reviewed by executive management and approved. Requirements Definition The product development department developed the requirements specification for the new product. These requirements were specified based on the understanding level of the project team, which had many years of experience in the company and an extremely good understanding of the systems. Some of the finer details of the requirements, such as the reporting requirements and the final policy document wording, were not defined at this initial stage. The outstanding requirements would be agreed upon during the project, once the users had decided exactly what they wanted in this regard. Project Team Appointment John was appointed as the overall project manager. John had been with the company for 23 years and been involved in numerous projects for new product developments in the past. He knows the existing systems intimately and had good working relationships with all the various departments involved in product development and launch. The project team appointed consisted of people from various departments, all of whom had been involved in previous product development projects. Their knowledge of the systems and applications is extensive. After delivery of Module Two, John left due to personal reasons. Project Kick-off The product development executive, the sponsor of the project, chaired the project kick-off meeting, held on May 5, 2017. She emphasized the importance of the project to the company, as it would ensure good returns by getting the new product to market before its competitors. She stressed that the delivery date must not be compromised in any way, as this would open the doors for competitive products and the opportunity would be missed. The project manager and the team were asked to get busy immediately with their planning, and a follow-up meeting was set for August 5, 2017 to review the project plans. Project Plan Development The project team had been involved in many similar projects in the past, and thus knew exactly what the project entailed. For this reason the plans were based on previous historical information of past projects. The project plans included only the systems-related work. The interfacing to other areas, such as the legal department, marketing, and operations, would be handled by the project manager at the specific time required for their input. Project plans were drawn up using a scheduling tool. The phases and tasks were detailed, but resources were not allocated to the tasks, since resources knew exactly what their role was on the project and which tasks related to them. Task dependencies were not put into the plan, as this made the plan too complex. Dependencies were handled by each team member and by the project manager. Project Plan Management Management of the project plan consisted of updating tasks with their percentage complete on a weekly basis. Record of actual hours spent on specific tasks was deemed not necessary. Each resource gave an estimate of the percentage complete for each task, which was used to update the plan. Resource availability was handled in an informal manner whereby each resource gave feedback on a weekly basis regarding his or her workload on the project and other non-project work responsibilities, such as systems maintenance. Progress Reporting Progress reports were produced every two weeks. These consisted of a progress summary, deliverables attained, percent complete, risks, issues, and cost information. (See the most recent Wellness Progress Report below.) Minutes were kept for some meetings. (See the most recent Meeting Minutes below.) Progress for Period May 5, 2017 – August 5, 2017 Initial progress was good, with all team members working well together. Programming started almost immediately, since the team knew the systems so well that they were able to make some of the required changes immediately. Some issues were identified with the user requirements, since not enough detail was in the requirements document. These issues were resolved between the programmers and the users. Some of the programmers experienced problems when they discovered they were working on the wrong version of the user requirements. This was resolved when the users printed out the current version of the requirements for all the team members to make sure they were all working on the current version. Progress was not as fast as desired, due mainly to users changing their minds about the requirements. The programmers were very accommodating with such changes and tried their utmost to keep the users satisfied. Unfortunately, the number of changes and additional requirements requested by the users caused the work to fall behind schedule. When some of the programmers complained to the project manager, he said that it was essential that users received what they wanted, so their changes must be accommodated, even if it meant having to work extra hours to catch up. The programming was also delayed from time to time due to technical problems experienced with the new development environment. The company did not have anyone experienced in the new development software, thus had to rely on vendor support, which was a bit lacking due to their commitments at other companies. Progress for Period August 5, 2017 – October 5, 2017 (two months before live date) The sponsor became concerned with the project progress, since she felt there was a risk of not meeting the required delivery date. The programmers were working long hours to try catch up on the project work, as well as doing their required maintenance and problem fixing of the live systems. The legal department said that they may not be able to provide the policy document wording in time for the live date, due to other priorities. They said they may have been able to if they had known about it sooner. The user department said they may have a problem getting the test packs ready for user testing, as some staff were going on leave over the Thanksgiving period. Initial testing revealed that the performance of some of the modules was very slow. This was resolved to some extent when it was found that some of the programmers had used inefficient coding, as they were new to the programming language being used. There were also a number of bugs reported, one of which causes the product to crash at least once a week. There are numerous change requests submitted by users for enhancements to the product. John, the project manager, has left, and the project team is in complete disarray, and there seem to be issues between the architect and database administrators on just how the database supports the vendor reports. As of now the two areas are not working together to develop solutions for the issues. There also seems to be a loss of a defined testing strategy, which has cropped concerns with development and user acceptance. There is no existing method of capturing reported issues, or how to handle changes. Management is unhappy about the project and there is no established communications method to inform them about the project status. The project is over budget by 20%. The vendor is asking for prepayment in order to deliver the third and final module for the final payment of $75,000, which was 75% of the total vendor cost. The module has not been tested yet. There is no communications plan, no risk plan, no systems implementation plan (to define how system implementation testing is handled), and no total cost of ownership (TCO) fee schedule. There is a conflict within the project team (e.g., team members have conflicting roles, or experience time pressure as a result of working in two positions within the organization simultaneously). Wellness Progress Report Client Project Project Manager 1 VP Operations Wellness Vendor John Current W1005 Development Start: End: Project Number Type of Project Reporting Period Progress Summary Programming work is almost complete and testing has begun. Unfortunately, it is going to take longer than planned to complete the programming due to changes requested by the users and errors made by the programmers using the new programming language. We are hoping that this time will be caught up by working overtime and reducing the testing time planned. 2 Major Activities Completed before Reporting Period Commenced 2.1 2.2 2.3 2.4 2.5 Business case approved User requirements document completed Programming underway Unit testing underway Test pack compilation started 3 Major Activities during Reporting Period 3.1 3.2 3.3 3.4 3.5 Programming continuing Unit testing underway Test packs complete Implementation plan started Changes made per user requests to date 4 Deliverables and Milestones No Description 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 Initial project plan Approved project charter Program code System testing User acceptance testing Go live Post implementation audit Project acceptance sign-off 5 Risks 5.1 Delivery date may be missed due to changes in user requirements Project team members may take leave over the Thanksgiving holidays Other departments may not have resources to do the policy docs and testing when required 5.2 5.3 Contingency Plan/Actions Baseline End Date Forecast or Actual End Date Actionee % Complete Status Impact (1-10) Probability (1-10) Score (I * P) Work overtime to catch up 8 5 40 JC Open Plan leave into project schedule 7 5 35 JC Open Agree tasks with other departments 8 6 48 JC Open 6 Issues 6.1 Changes to requirements requested by the users are causing delays in project delivery 9 JC Agree final requirements with the users 6.2 Currently behind schedule with some tasks, but should be able to catch up without affecting the scheduled delivery date 9 JC Work overtime 6.3 8 JC Agree date with Legal Dept. 6.4 Get final policy document wording from legal department Make sure Testers are available for required testing dates 8 JC Agree resources and dates for testing with user departments 7 List of Scope Change Requests No Impact (1-10) Date 7.1 Action Due Date/ Status Client Approval Description Impact No official change requests to date 8 Major Activities for Next Period 8.1 8.2 8.3 8.4 8.5 8.6 Complete programming Complete and get approval for project charter Start system testing Start planning for user acceptance test (compile test plan) Fix errors and omissions identified during testing Compile and agree implementation plan 8 Actionee Budget Tracking Task/Phase Wellness Vendor Planned Cost (Baseline) 441,650 Actual Cost to Date 230,892 Remaining Cost 210,758 Estimate at Completion 529,980 Percent Variance 20% Meeting Minutes MEETING DATE: May 15, 2017 PROJECT: SUBJECT: ATTENDEES: APOLOGIES: Wellness Vendor Weekly Progress Roy Kirk (RK), John Current (JC), Kevin Smith (KS), project team members Sue Barrett (Sponsor) Outstanding from Previous Meeting’s Minutes Item 1. Minute JC to discuss user requirements changes impact with sponsor Actionee Status / Due Date JC JC could not get meeting with sponsor Actionee Status / Due Date Meeting Minutes Item 1. 2. 3. 4. 5. 6. Minute Testing plan to be drawn up and testers allocated by the user department Leave schedule to be drawn up for all project staff to assess project schedule impact Legal department to give expected completion date for new policy document wording Machine needs to be booked and set up for training of testers and running of the user acceptance test Testers to be identified by user departments and allocated for testing period required Current problems with system performance of the Java code to be escalated to vendor for urgent resolution JC JC JC KS SB JC Scope Change Requests Item 1. Change request description No official scope change requests to date Next meeting: 02/04/2017 (3pm. – 4pm) - Meeting Room 2.3 Actionee Due Date Status Identified Problems and Solutions Item No. 1. 2. 3. 4. 5. 6. Problem Description Root Cause Proposed Resolution Action Proposed Preventative Action for Future Projects Item No. 7. 8. 9. 10. 11. 12. Problem Description Root Cause Proposed Resolution Action Proposed Preventative Action for Future Projects Item No. 13. 14. 15. 16. 17. 18. Problem Description Root Cause Proposed Resolution Action Proposed Preventative Action for Future Projects Wellness Vendor - Project Charter Project Name: Wellness Vendor Project Information Project Number W1005 IS Request Number RW1005 Request Date Request Name Business Area May 15, 2017 Wellness Vendor Information Technology (IT) Sr. VP Information Systems 54 Requester Business Unit Executive Sponsor VP Operations IT Sr. VP Information Systems VP Operations Project Owner Overall Score Business Area Approver Scope & Objectives Business Problem Addressed Request Vision & Scope Business Assumptions & Risks Timing & Dependencies Narrative Summary of Benefits Create modular software package to handle wellness vendor data to ensure appropriate preventative care is being tracked for members. Vendor wellness member tracking and management. Vendor data availability and format. Data analytics and reporting capabilities. Go-live date: Dec 21, 2017 Increase vendor revenue, decrease inappropriate utilization of care, and improve return on investment for wellness vendor programs. Business / Strategic Alignment Corporate Sustainability Administrative Efficiency Revenue Generating Customer Service or Experience Member Touchpoint Measures/Trends Request Expands Scope of Products & Services Request contributes to IHM’s Strategic Objectives How This Request Supports These Drivers Strategic Score 9 9 9 3 3 3 3 Increase in revenue 39 Wellness Vendor - Project Charter Risk / Compliance Fulfill a Corporate Requirement Address a Federal / State Mandate Address an Association Mandate Address a Customer Mandate How This Request Supports These Drivers Risk Score 15 0 0 0 Increase preventative care management and administrative cost internally. 15 Business Requirements 1. 2. 3. 4. 5. Vendor sends daily data input file for report analytics. Send weekly vendor output analytics file (summarization of weekly activities). Vendor evaluates information for approval on correctness of data output. Additional files, upon request sent to/from vendor. Vendor I/S reporting (requires report prototypes). Constraints/Exclusions Project Exclusions Governing Agreements N/A Governmental regulations and guidelines, vendor contract language Organizational Impact Operations Call Center Product Management Information Technology Business Continuity & Disaster Recovery Vendor wellness programs , I/S technical support, report & analytics Customer service IT support Wellness product management for modular software Wellness provider file layouts and reporting Data storage Wellness Vendor - Project Charter Risks Risk Area Vendor Performance Likelihood Risk Owner Description All governmental regulations and standards must be in compliance and maintained by vendor. All accreditation standard(s) must be in compliance and maintained for vendor. High Resources Resources Internal/External Estimated hours Role Description Identified in project plan Internal Refer to project plan
Purchase answer to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

Drafting_Conflict_Resolution_Pla
n
by HAL Lab

Submission date: 28-Sep-2020 04:00PM (UTC-0400)
Submission ID: 1399583835
File name: Drafting_Conflict_Resolution_Plans.edited.docx (18.04K)
Word count: 756
Character count: 3722

Drafting_Conflict_Resolution_Plan
ORIGINALITY REPORT

2

%

SIMILARITY INDEX

2%

0%

2%

INTERNET SOURCES

PUBLICATIONS

STUDENT PAPERS

PRIMARY SOURCES

1

2%

www.surveymonkey.com
Internet Source

Exclude quotes

Off

Exclude bibliography

On

Exclude matches

Off


Report: Drafting_Conflict_Resolution_Plans

Drafting_Con ict_Resolution_Plans
by HAL

General metrics
4,556

764

47

3 min 3 sec

5 min 52 sec

characters

words

sentences

reading
time

speaking
time

Score
99

Writing Issues
1

Issues left

1
Critical

Advanced

This text scores better than 99%
of all texts checked by Grammarly

Plagiarism
This text hasn’t been checked for plagiarism

Report was generated on Monday, Sep 28, 2020, 10:58 PM

Page 1 of 7

Report: Drafting_Conflict_Resolution_Plans

Writing Issues
1

Engagement

1

Word choice

Unique Words

29%

Measures vocabulary diversity by calculating the
percentage of words used only once in your
document

unique words

Rare Words

28%

Measures depth of vocabulary by identifying words
that are not among the 5,000 most common English
words.

rare words

Word Length

4.7

Measures average word length

characters per word

Sentence Length

16.3

Measures average sentence length

words per sentence

Report was generated on Monday, Sep 28, 2020, 10:58 PM

Page 2 of 7

Report: Drafting_Conflict_Resolution_Plans

Drafting_Con ict_Resolution_Plans
5
CONFLICT RESOLUTION

Running head: CONFLICT RESOLUTION 1

Drafting Con ict Resolution
Name:
Institutional Af liation:
Date:
Table of Contents
Drafting Con ict Resolution Plans 3
Project 3
Potential con icts 3
Strengthening the team 4
References 5

Report was generated on Monday, Sep 28, 2020, 10:58 PM

Page 3 of 7

Report: Drafting_Conflict_Resolution_Plans

Drafting Con ict Resolution Plans
The project
As a result of the need that the healthcare organization have about the
attainment of the intended health outcome, the project was aimed to ensure
that technology is integrated to assist in the realization of most of the goals.
The creation of a stable form of data transfer, storage and processing is the
main feature of the project that will make it an essential to...


Anonymous
This is great! Exactly what I wanted.

Studypool
4.7
Indeed
4.5
Sitejabber
4.4

Similar Content

Related Tags