The Fishbone Diagram

4. On a construction site, the job is clearly behind schedule. Discussion with the workers points to problems with having materials ready when needed. Some of the materials in the supply trailer seem to be of the wrong sizes – such as piping and fittings. It takes a long time to get the materials each day, and workers are held back.

Draw a Cause and Effect (Fishbone) diagram to try to find the possible causes for this situation. Start with an observed effect “Material supply problems”

Show possible causes on 5 bones of the chart. These should be labeled: Materials,

Workers, Methods, Equipment, and Environment. Show at least 3 possible causes on each bone.

NOTE – use action words or phrases. Do not use numbers.

(i) Brainstorm on the problem, then list the ideas. Work from the list to sketch the

basic structure of the chart, then add the ideas to the chart as possible causes.

(ii) Write a short summary to suggest specific ideas on how the findings from the

chart may be used to improve the materials problem.


6. Factual Review Question:

Explain the purpose of a scatter diagram. Give an example of how one could be used in a construction project.

7. Five-S application:

In your group, discuss a construction project one of you may be involved in, or may have observed at some time.

Explain briefly how you think Five-S could be used to improve the project, and what

results could be expected. Try to be specific about any steps needed.

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

1
Management Analysis

Management Analysis
Student’s Name
Institutional Affiliation

2
Management Analysis

WORKERS
ENVIRONMENT

MATERIALS
Uncertain Delivery times

MATERIAL
SUPPLY
PROBLEMS
Inaccurate measuring methods

Regulations and Protocols

EQUIPMENT

METHODS

3
Management Analysis

ii)

How the findings can be used to improve the materials problem;

MATERIALS
a) Uncertain Delivery Times
Low stockpiles show that the contractor must depend on the material delivery time to be on
schedule. A single traffic jam holds materials required for the project execution hence leading to
costly budget overruns (Chandra,2017). Contractors requires delivery times to enable them
schedule in advance.
b) Unavailability of material
Lack and scarcity of material from the market results in delay for the work schedule. Contractors
need to establish that the materials are available prior to commencement of work.
c) Rising cost of material
High demands of construction material, scarcity and other factors result in rise in the cost of
materials. The contractors should project such inflation in the budget and discuss and make
necessary recommend...