Background about Risk
Risk Engineering, which consists of assessing and controlling risks, is a key component to successful
project management.
Gambling establishments from the 17th and 18th century were the first known body to investigate risk.
Various games were assessed to determine payback and discrete events were studied. Evaluating what
playing card would be next or would the next ball be black and white introduced probability theory.
Insurance companies began using probability theory in the 19th century for continuous events, for
example, insurance risk exposure was investigated to determine the probability of death at various ages.
From the 1950s through the 1970s decision theory took off, which is the study of identifying values,
uncertainties, and related issues to understand a given decision and its justification. In the 1980s software
projects began to include risk techniques to reduce errors and produce successful project. In the 1990s,
the Software Engineering Institute (SEI) introduced "Team Risk Management" and increased emphasis
on risk management. We will talk more about the SEI in Module 11.
Definition of Risk
Risk is defined as an event, action, or thing with:
1. A potential loss associated with it,
2. An uncertainty or chance involved, or
3. Some choice involved. Robert Charette introduced this definition in 1987.
Risk is the lack of resources such as information, control, or time to accomplish a task. Losses may be in
the form of reduced quality of the delivered product, increased cost, delayed completion, or failure. The
classic Operations Research definition of risk focuses only on the probability of occurrence, not on the
consequences or loss. Risks deal with uncertainties and unknowns insofar as they lead to failure or
produce adverse outcomes.
Robert N. Charette, Sr. Consultant with Agile Project Management Practice and director of the Risk
Management Intelligence Network introduced the Evolutionary Hierarchy of Risk. He proposed that there
are levels of risk. The lowest level is Crisis Management, where the team is fighting the "project fires." At
this level, risks are addressed only after they become problems. On the Capability Maturity Model
Integrated® (CMMI®) scale, this would be at level 0. Fix-on-Failure is the next level; when a risk is
detected, the team reacts quickly. Again this takes place only after the risk has occurred. The third level is
Mitigation where the team plans ahead of time to provide resources to cover risks as they occur, but the
team does not take the next step to prevent them. In Prevention, the team implements and executes a
plan as part of the software project to identify risks and prevent them from becoming a problem. The next
level is Eliminate Root Causes where the team identifies and eliminates factors that make it possible for
the risks to occur. This and the next step is where the Japanese car industry focused when their cars
became popular in the 1990s. Anticipation suggests that you expect that you will have risks and you
used techniques such as inspections to prevent and eliminate the risks. Lastly Management of Change,
CMMI® Level 4 and 5 activities, is where the team manages change.
Risk Engineering and Current Software Programs
Most Requests for Proposal (RFPs) require offerors to identify risks and provide risk mitigation strategies
and the Statement of Work (SOW) probably requires risk management. Contract Deliverable Resource
Lists (CDRLs) may include a Data Item Description (DID) for a Risk Assess Report. The commercial and
Government standards such as ISO 12207 requires a section on risk. The risk management process
must be defined for the project. One or more people assigned to the program must have funded
responsibility for risk management.
An example from Earth Observing Satellite Data Information System Core System (ECS) SOW has
paragraph 3.2.4 which specifies requirements for risk assessment. For example DID 210/SE3 is the Risk
Assessment Report. Paraphrased it reads:
Design Analysis, Work Breakdown Structure (WBS) 2.4: The contractor shall conduct performance
analyses and risk assessments of the design to evaluate the optimization, correlation, completeness, and
risk associated with the design, and to ensure that the implemented system will meet all the requirements
of the specification.
SE means the System Engineering Office responsible for production of the DID. SE3 means the
document is reviewed and controlled by the contractor, that is, the document must be delivered to the
customer for information only yet subject to approval. The document is due one month prior to each
Incremental Design Review (IDR) and there will be five IDRs. This report:
•
•
•
Identifies possible high risk areas in the design, manufacture, integration, and test areas,
Assesses the risks identified in terms of technical objectives, goals, schedule, and budget; and
Identifies appropriate plans to mitigate risks and provides costs for alternate or backup
approaches.
Two Phases of Risk: Assessment and Control
Risk Assessment
Identification
The purpose of Risk Identification is to identify and categorize potential problem areas. Identification is
initiated during the proposal and continually updated during the project. Risks can be identified through:
•
•
•
•
•
•
•
•
•
•
•
•
Visiting the customer operational sites
Participating in customer working groups
Examining results from Independent Research and Development (IR&D) programs
Reviewing historical lessons learned data
Analyzing assumptions from estimation
Examining cost drivers from the cost estimation model
Prototyping
Benchmarking hardware
Performing special trade studies or analyses
Running performance models or simulation
Analyzing poorly defined items in the specification and plans
Using checklists of generic software problems
Barry Boehm and Robert Charette both have checklists of common software risk problems and
you will notice that they are not identical.
Top 10 Checklist Barry Boehm
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
Personnel shortfalls
Unrealistic schedules and budgets
Developing the wrong software functions
Developing the wrong user interface
Gold plating (excessive requirements or
overdesign)
Continuous stream of requirements changes
(excessive requirements volatility)
Shortfall in externally furnished components
Shortfall in externally performed tasks
Real-time performance shortfalls
Straining computer science capabilities
Common Software Risks Robert Charette
1.
2.
3.
4.
5.
Inadequate development model
Inadequate software development plan
Unsuitable organizational structure
Too many new methodologies
Building a complex project from scratch
The Software Engineering Institute (SEI) created a taxonomy approach to identify risks based on these
assumptions:
•
•
•
•
•
Software development risks are generally known by the development staff but not always
communicated.
A structured and repeatable method of risk identification will encourage consistent risk
management.
Effective risk management must cover all key development and support areas of the project.
The risk identification process must create and sustain a non-judgmental, objective environment
so that tentative or controversial views are heard.
No overall judgment can be made about the success or failure of a project based solely on the
number of risks uncovered.
The software taxonomy is organized into three major classes:
•
•
Product Engineering covers the technical aspects of the work to be accomplished.
Development Environment covers the methods, procedures, and tools used to produce the
product.
•
Program Constraints are the contractual, organizational, and operational factors within which
the software is developed, but which are generally outside of the direct control of local
management.
The classes are organized into 13 elements and 64 attributes.
The next item contains a video that provides a brief overview of software taxonomy.
Analysis
Risk analysis assigns a quantitative value to identified risks. A quantitative value is preferred over low,
medium, and high, although this range is often uses. Analysis is conducted to discover the cause, effect,
and magnitude of the perceived risk. It is common to analyze risk in terms of the Risk Factor (Rf) which is
determined by estimating the Probability of Failure (Pf) and the Consequences of Failure (Cf).
Pf is determined by considering the maturity (m), complexity (c), and dependency (d) factors in the
equation:
Pf = (Pm + Pc + Pd) / 3 where:
Probability of Failure Calculation
Magnitude
Pf
Maturity Factor Complexity Factor
Pm
Pc
Dependency Factor
Pd
Independent of existing
system, facility, or associate
contractor
0.1 (low)
Existing design Simple design
0.5 (medium)
Major design
change
Moderate
increase in
complexity
Performance dependent on
existing system performance,
facility, associate contractor
0.9 (high)
State of art,
some research
complete
Extremely
complex
Performance dependent on
new system schedule, facility,
or associate contractor
Cf is determined by considering the technical (t), cost (c), and schedule (s) factors in the equation:
Cf = (Ct + Cc + Cs) / 3 where:
Consequences of Failure Calculation
Technical
Factor
Ct
Cost Factor
Cc
Schedule Factor
Cs
0.1 (low)
Minimal or no
consequences
Budget estimates
not exceeded,
some $ transfer
Negligible impact on program,
slight schedule change,
compensated by available
slack
0.5 (medium)
Some
reduction in
technical
Cost estimates
increased by 5%
to 20%
Small slip in schedule
Magnitude
Cf
Technical
Factor
Ct
Magnitude
Cf
Cost Factor
Cc
Schedule Factor
Cs
performance
0.9 (high)
Technical
goals cannot
be achieved
Cost estimates
increased by >
50%
Large schedule slip, affects
segment milestones or
possible affect on system
milestones
Then the resulting Risk Factor is defined as Rf = Pf + Cf − (Pf * Cf), for example:
Pf
Cf
Rf
.7
.7
.7 + .7 − (.7*.7) = .90
.5
.7
.5 + .7 − (.5*.7) = .85
.5
.3
.5 + .3 − (.5*.3) = .65
.4
.2
.4 + .2 − (.4*.2) = .52
Be aware that the Risk Factor is less meaningful when either probability or consequences of failure
approach one or zero. For example: the consequences of failure of the fuel gauge in an airplane are
technically unacceptable; hence, consequences could be assessed as one. Even if the probability of
failure is zero, that is, the Risk Factor is one:
Rf = Pf + Cf − (Pf * Cf) = 0 + 1 − (0 * 1) = 1
Other factors should be considered for these situations in regions "A" and "B":
The product of the analysis step includes a list of quantified risk items with attributes. Each risk item must
be saved and routinely maintained as in the example.
Attribute
Description
Risk item number
Program unique identifier
Risk item name
Name of risk item
Attribute
Description
Description
Textual description of risk item
Potential impact
Description of impact to the
program if the risk comes true, in
terms of cost, schedule,
performance
Risk factor
Numeric value based on
probability and consequences of
risk
Specific activities to mitigate or
Current
recover from the risk, including
mitigation/contingency
status of plans and responsible
plans
organization
Monitoring thresholds
Specific values on a scale which
defines success or requires
additional action
Scale
Measurement scale relevant to
monitoring thresholds for risk item
A monitoring threshold which results in a reduction of the risk factor to a low level is the success
threshold; while a monitoring threshold which requires additional risk related activity is an action
threshold.
Prioritization
In risk prioritization, the Risk Factor is used to sort the risks where the highest values get highest priority.
Each risk factor is evaluated to determine most appropriate risk management plans to prioritize
implementation strategies. Consider this sample data:
Risk Item
Rf
Cf
Pf
1. Low probability,
low consequences
0.19 0.10 0.10
2. Low probability,
high consequences
0.73 0.70 0.10
3. High probability,
low consequences
0.73 0.10 0.70
4. High probability,
high consequences
0.91 0.70 0.70
The plans for Risk Item 2 should focus on reducing the consequences of the risk; the plans for Risk Item
3 should focus on reducing the probability of the risk, and further evaluation should concentrate on the
components of the probability or consequences of failure.
Risk Control
Planning
The first step in Risk Control is Risk Planning. Feasible options are identified for managing the risk;
examples of risk management options include:
Note that some strategies are aimed at avoiding risk including (2) prototyping, (4) scope down
requirements, and (6) modelling and simulation, while others are aimed at transferring risk including (3)
subcontractor performance and cost incentives, (7) shift function to hardware, and (8) leave function to
operator. You need to compare effectiveness and the cost of various options. One method is to apply the
Risk Reduction Leverage (RRL), a quality for price ratio, which is defined as:
RRL = (Risk Exposure Before − Risk Exposure After) / Risk Reduction Cost
For example, assume the loss due to a software interface error is estimated at $100,000 and the
probability of error being introduced is estimated at 0.3 or 30%. Then the Risk Exposure Before =
$100,000 x (.3) = $30,000. Your research shows that there are three approaches for eliminating the error:
•
•
•
An interface (I/F) checking tool that costs $5,000 and reduces the probability to 0.2 or 20%,
An I/F testing approach that costs $15,000 and reduces the probability to 0.1 or 10%, or
Reusing tried and proven interface software that costs $3,000 and reduces the probability to 0.1
or 10%
Using this data, we can solve the equations for the RRL as:
RRL = (Risk Exposure Before − Risk Exposure After) / Risk Reduction Cost
Option 1: RRL (checker) = [$30K − ($100K x (.2))] / $5K = 2
Option 2: RRL (testing) = [$30K − ($100K x (.1))] / $15K = 1.33
Option 3: RRL (reuse) = [$30K − ($100K x (.1))] / $3K = 6.66 (Best Solution)
Now with this quality for price data, specific action plans including the implementation criteria for success
and/or action thresholds can be developed for the options. The risk management plans may be
contingency plans, in case the failure occurs, or mitigation plans, to proactively reduce the likelihood
that the risk will occur, or both.
Project management then reviews the risk management plans, refines them, and the appropriate
approach is selected. The plans must answer the following questions for each risk item:
•
•
•
•
•
Why? Answering risk item importance and relation to project objectives
What? When? Answering risk resolution deliverables, milestones, and activities
Who? Where? Answering responsibilities and organization
How? Answering the approach
How much? Answering budget, schedule, and key personnel
Resolution
Effective risk resolution often hinges on finding a creative solution to the specific risk. Thus the solution
depends on the risk. There are eight (8) generic methods to resolve risks.
Avoid the risk
Do not do the risky activity:
negotiate elimination of the
requirement or hire a consultant
(specialist) to do the risky work
Transfer the risk
Buy special purpose hardware
rather than develop software or find
a COTS solution
Buy information
about the risk
Spend money to investigate the
risk: prototype, bring in a consultant
to evaluate your design, or
establish an IR&D project well
ahead of time
Eliminate the root
cause of the risk
Analyze the risk to look for
underlying causes using techniques
such as Kaizen, Lean, or Six
Sigma; and minimize or eliminate
root causes
Assume the risk
If the consequences are small and
the cost to avoid the risk is large,
simply accept the consequences if
the risk occurs
Publicize the risk
Notify upper management,
marketing, and the customers
about the risk and consequences:
minimize the surprise if it occurs
and get buy in for resolutions
Control the risk
Accept that the risk might occur and
develop plans to handle it if it does
Remember the
risk
Build a collection of risk
management plans and resolutions
for use on future projects
Monitoring
In Risk Monitoring, the software manager tracks the status of open and potential risk areas. Technical,
cost, and schedule performance of each implemented risk plan is qualitatively assessed at internal
periodic project management reviews to:
•
•
•
Verify outcomes were as envisioned,
Identify opportunities for refinement of risk plan, and
Provide feedback to those making programmatic decisions
Customer personnel are apprised of each risk area at the monthly progress reviews and major technical
reviews. Risk monitoring techniques include collecting metrics, reviewing risks, and tracking the top ten
risks as in the chart.
Top 10 Risk Tracking: Third Week
This Last Weeks
weekweek on list
Risk Item
Risk resolution progress
1
1
3
Scoping product to fit required schedule
Working session with customer
2
4
3
Resolving subcontractor OS I/F
uncertainties
New changes proposed by
subcontractor
3
2
3
Algorithm boundary checking
Prototype on schedule
4
6
2
Workstation availability
Delay in delivery reported
5
5
3
User I/F definition
User study complete, awaiting
prototype
6
3
3
Staffing lead developer for control
software
Candidate identified, offer
extended
7
-
1
Reusable text-formatting software
uncertainties
Evaluation underway
8
7
3
Application performance risk
Benchmark to complete this week
This Last Weeks
weekweek on list
Risk Item
Risk resolution progress
9
9
2
CM procedures for incremental
development
CM procedures identified, SEPG
tailoring
10
8
2
Staffing programmer for control software
Programmer accepted offer;
reports on 08/01
Risk Management Panel
Large programs/projects often create a Risk Management Panel (RMP) which should be documented in
the appropriate Project Instruction. The purpose of the RMP is to provide accurate current data and multidisciplinary inputs to Program/Project Management to make informed decisions about managing the
risks. The panel typically includes the Deputy Program/Project Manager who acts as the RMP chair, the
Chief System Engineer, the Quality Assurance Office Manager, the Software Development Manager, the
Operations and Maintenance Manager, the Independent Test Office Manager, the Commercial off the
Shelf (COTS) Procurement Manager and a Customer Representative. The RMP acts as a reviewing body
at each checkpoint of the risk management process: identification, analysis, prioritization, planning,
resolution, and monitoring. The outputs of the RMP are approvals and redirections for each checkpoint in
the risk management process. Decisions of the RMP are reported to other relevant management forums
such as the Project Review, Configuration Control Boards (CCBs), and monthly status meetings. Issues
or feedback from these forums may require the RMP to deliberate further.
Risk Management Summary
In summary, the risk engineering process is defined as:
Organizations have a choice. They can take a risk based management approach or they can choose not
to invest in reducing risk. There are positives and negatives to both approaches, but the software
industry's current stance is the risk based management approach is better and cheaper in the long run.
Risk-based Management
Orientation
"Realistically oriented", risks set up
boundary conditions, foresee and
contain possible failure, proactive
not reactive
•
Problems
•
•
•
Benefits
•
•
Risk analysis may be
inaccurate, underestimation can
cause major problems,
overestimation can lead to
excessive mitigation effort
Takes resources away from
other tasks
Effects of risk engineering hard
to measure: total avoidance
removes proof that cost was
justified
Better perception of risks &
options for management:
reduction in project exposure to
risk
Improved credibility of plans
More proactive
U.S. software development
Example:
Think of the
car industry
in the 1990s
•
•
•
Change to meet user-requested
requirements, independent of
component availability
More functional, higher cost,
less reliable
Greater need for risk-based
management approach
No Risk Investment
"Success oriented", "can do"
attitude, minimize thought of
possible failure, leave little extra
to handle contingencies
•
•
•
Reactive
No planning
No options for management
consideration
•
Funds are not diverted to
risk mitigation activities
"Can do" attitude
•
Japanese software development
•
•
•
Change functionality in
response to availability of
components
Less functional yet more
reliable
Less need for risk
management
Software Engineering
Institute Risk Taxonomy
Risk Identification
Engineering for Professionals
Product Engineering
Class
Element
Product Engineering
Requirements
Design
Code & Unit Test
Integra6on & Test
Engineering Special6es
-‐ Stability
-‐ Func'onality
-‐ Feasibility
-‐ Environment
-‐ Maintainability
-‐ Completeness
-‐ Difficulty
-‐ Tes'ng
-‐ Product Integra'on
-‐ Reliability
-‐ Clarity
-‐ Interfaces
-‐ Coding/Implementa'on
-‐ System Integra'on
-‐ Safety
-‐ Validity
-‐ Performance
-‐ Security
-‐ Feasibility
-‐ Testability
-‐ Hunan factors
-‐ Precedent
-‐ HW constraints
-‐ Specifica'ons
-‐ Scale
-‐ Non-‐developmental SW
AIribute
Engineering for Professionals
Development Environment
Development Environment
Development Process
Development System
Management Process
Management methods
Work environment
-‐ Formality
-‐ Capacity
-‐ Planning
-‐ Monitoring
-‐ Quality aOtude
-‐ Suitability
-‐ Suitability
-‐ Project organiza'on
-‐ Personnel management
-‐ Coopera'on
-‐ Process Control
-‐ Usability
-‐ Management experience
-‐ Quality assurance
-‐ Communica'on
-‐ Familiarity
-‐ Familiarity
-‐ Program interfaces
-‐ Configura'on mgmt
-‐ Morale
-‐ Product control
-‐ Reliability
-‐ System support
-‐ Deliverability
Engineering for Professionals
Program Constraints
Program Constraints
Resources
Contract
-‐ Schedule
-‐ Type of contract
-‐ Staff
-‐ Restric'ons
-‐ Budget
-‐ Dependencies
-‐ Facili'es
Engineering for Professionals
Program Interfaces
Customer -‐ -‐ Corporate Mgmt
Associate contractor -‐ -‐ Vendors
Subcontractors -‐ -‐ Poli'cs
Prime contractor -‐