Integrated Corridor Management:
Implementation Guide and Lessons
Learned
www.its.dot.gov/index.htm
Final Report Version 2.0 — September 2015
FHWA-JPO-16-280
Produced by FHWA Office of Operations Support Contract # DTFH61-05-D-00002
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Federal Highway Administration
Federal Transit Administration
Notice
This document is disseminated under the sponsorship of the Department of Transportation
in the interest of information exchange. The United States Government assumes no liability
for its contents or use thereof.
The U.S. Government is not endorsing any manufacturers, products, or services cited
herein and any trade name that may appear in the work has been included only because it
is essential to the contents of the work.
i
Technical Report Documentation Page
1. Report No.
2. Government Accession No.
3. Recipient’s Catalog No.
FHWA-JPO-16-280
4. Title and Subtitle
5. Report Date
Integrated Corridor Management: Implementation Guide and Lessons Learned (Final Report
Version 2.0)
September 2015
6. Performing Organization Code
8. Performing Organization Report No.
7. Author(s)
Blake Christie, Dawn Hardesty, Greg Hatcher, Michael Mercer
10. Work Unit No. (TRAIS)
9. Performing Organization Name And Address
Noblis, Inc.
3150 Fairview Park Drive
Falls Church, VA 22042
703-610-2000
11. Contract or Grant No.
DTFH61-11-D-00018, T-12010
12. Sponsoring Agency Name and Address
13. Type of Report and Period Covered
U.S. Department of Transportation
ITS Joint Program Office
1200 New Jersey Avenue, SE
Washington, DC 20590
855-368-4200
Final Report version 2.0 2015
14. Sponsoring Agency Code
ITS JPO
15. Supplementary Notes
U.S. DOT Team: Brian Cronin, RITA; Steven Mortensen, FTA, Robert Sheehan, FHWA; Neil Spiller, FHWA and Dale Thompson, FHWA.
16. Abstract
This implementation guide is intended for use by adopters of integrated corridor management (ICM) approaches and strategies to address congestion
and travel time reliability issues within specific travel corridors. It introduces the topic of ICM and identifies the type of information system, the
integrated corridor management system (ICMS) that is used to support transportation network managers and operators in applying ICM.
The guide discusses typical issues (lessons learned) that arose during the U.S. Department of Transportation’s (U.S. DOT’s) research initiative, where
the U.S. DOT partnered with eight transportation agencies in large metropolitan areas (known as “Pioneer Sites”) to research effective means of
implementing ICM approaches in their major travel corridors. Each of the Pioneer Sites used a systems engineering approach to define the needs for
ICM within their corridor and the needs and requirements for an ICMS to support ICM. Two of the original eight Pioneer Sites were selected to serve
as Pioneer Demonstration Sites, where an actual ICMS was built, operated, maintained and evaluated to assess how effective ICM strategies were in
improving the flow of traffic within the corridor.
The guide offers suggestions for each stage of an implementation effort for an ICMS, to assist other agencies in benefitting from the research done to
date and from the experiences of the Pioneer Sites. In addition to the material covered in the guide itself, there are extensive references to other
documents and source material that can assist ICM adopters in successfully applying these concepts for their regions. Please note that this Version 2.0
of the ICM Implementation Guide and Lessons Learned supersedes Version 1.0 of the ICM Implementation Guide and Lessons Learned published in
February of 2012. At the time the version 1.0 guide was written, the Dallas and San Diego ICM Pioneer Sites were still in the system definition and
design stages of the project lifecycle. This version 2.0 update of the guide provides additional lessons learned and examples through the full
implementation of the Dallas and San Diego ICM Pioneer Site projects.
17. Key Words
18. Distribution Statement
Intelligent Transportation System, ITS, Integrated Corridor
Management, ICM, Integrated Corridor Management System,
ICMS, Pioneer Site, Implementation, Guide, Lessons Learned,
Analysis, Modeling, Simulation, AMS, Demonstration, Evaluation,
Systems Engineering, Planning, Operations, Maintenance
No restrictions.
19. Security Classif. (of this report)
20. Security Classif. (of this page)
Unclassified
Unclassified
Form DOT F 1700. 7 (8-72)
21. No. of Pages
22. Price
152
N/A
Reproduction of completed page authorized
ii
Acknowledgements
The Noblis team would like to thank the U.S. DOT and ICM stakeholder reviewers for their valuable input.
Ahmad Sadegh, Telvent (Schneider
Electric)
Alan Gorman, DART
Alex Estrella, SANDAG
Andy Oberlander, TxDOT
Andy Palanisamy, Leidos
Anna Giragosian, Leidos
April Armstrong, AHA Insight
Brian Cronin, FHWA
Brian Fariello, TxDOT
Chris Poe, TTI
Dale Thompson, FHWA
Dan Carlson, Delcan (Parsons)
Duana Love, FTA
Ed Fok, FHWA
Ed Seymour, TTI
Emiliano Lopez, FHWA
Fariel Bouattoura, Telvent (Schneider
Electric)
Jeremy Schroeder, Battelle
Jim Hunt, FHWA
Joe Hunt, TxDOT
Joerg 'Nu' Rosenbohm, Nu-in-ITS
Kevin Miller, Telvent (Schneider
Electric)
Kirk Howser, City of Dallas
Koorosh Olyai, Stantec
Lee Biernbaum, Volpe
Lloyd Neal, City of Plano
Margaret Petrella, Volpe
Marian Thompson, NCTCOG
Matthew Juckes, TSS Aimsun Online
Michael Krueger, ASE Consulting
Michael Waisley, Battelle
Nancy Rantowich, ASE Consulting
Natalie Bettger, NCTCOG
Neil Spiller, FHWA
Paul Olson, FHWA
Peter Thompson, SANDAG
Robert Saylor, City of Richardson
Robert Sheehan, FHWA
Roberto Macias, TTI
Stan Glowacki, SANDAG
Steve Callas, Tri-Met
Steve Mortensen, FTA
Teresa Malone, Delcan (Parsons)
Todd Plesko, DART
Vassili Alexiadis, Cambridge
Systematics
Khaled Abdelghany, SMU
iii
Table of Contents
Acknowledgements .......................................................................................................................... iii
Abstract ...............................................................................................................................................iv
Chapter 1. Introduction to the ICM Guide .....................................................................................1
Overview ....................................................................................................................... 1
How to Use This Guide ................................................................................................. 2
Chapter 2. Understanding Integrated Management of Transportation Corridors ..................5
What Is Integrated Corridor Management? ................................................................. 5
What Is an Integrated Corridor Management System? ............................................... 9
Analysis, Modeling, and Simulation for ICM ...............................................................11
Managing the Complexity of an ICMS Implementation ............................................. 12
Chapter 3. ICM Implementation Guidance and Lessons Learned ..........................................14
Get Started (Phase1) ........................................................................................................................16
Establish Goals (Phase 2) ...............................................................................................................27
Plan for Success (Phase 3).............................................................................................................37
Project Management Plan .......................................................................................... 37
Systems Engineering Management Plan................................................................... 41
Concept of Operations ................................................................................................ 47
Specify and Design (Phase 4) ........................................................................................................57
Architecture ................................................................................................................. 57
Requirements .............................................................................................................. 67
Detailed Design ........................................................................................................... 76
Build and Test (Phase 5)..................................................................................................................82
Operate and Maintain (Phase 6).....................................................................................................89
System Retirement/Replacement (Phase 7)................................................................................99
APPENDIX A. Conceptualizing Integrated Corridor Management ................................ 103
APPENDIX B. Defining the ICMS Decision Support System .......................................... 125
APPENDIX C. ICM Walkthroughs ........................................................................................... 128
APPENDIX D. List of Acronyms and Abbreviations.......................................................... 135
APPENDIX E. References ......................................................................................................... 137
APPENDIX F. Endnotes .............................................................................................................. 141
ii
List of Tables
Table 1.
Table 2.
Table 3.
Table 4.
Table 5.
Table 6.
Table 7.
Table 8.
Table 9.
Expected Annual ICM Benefits of Pioneer Sites ............................................................................ 9
ICM Implementation Process ....................................................................................................... 15
Dallas Example: Mapping of Goals Against Corridor Needs ....................................................... 56
Example: National ITS Architecture Data Flows and Primitive Data Elements ........................... 62
Sample Requirements to Needs Traceability (Hypothetical Example) ........................................ 72
Dallas ICM Pioneer Site Example: Action Verbs and Definitions ................................................ 74
San Diego Example: Performance Measures for Institutional/ Organizational Coordination ...... 94
DSS Recommended Response Plans from 8/16-9/29 ................................................................ 97
ICM Operational Needs and ICM Environment Levels .............................................................. 120
List of Figures
Figure 1. U.S. DOT ICM Pioneer Sites ........................................................................................................ 1
Figure 2. Generic Structure Diagram ........................................................................................................... 3
Figure 3. San Diego ICM Example: Developing Systems for High Performance Corridors ...................... 10
Figure 4. San Diego ICM Example: Future Decision Support System (conceptual) ................................. 11
Figure 5. Systems Engineering VEE Diagram ........................................................................................... 13
Figure 6. Getting Started With ICM ............................................................................................................ 17
Figure 7. US-75 ICM Institutional Framework ............................................................................................ 25
Figure 8. Establishing Goals for ICM ......................................................................................................... 28
Figure 9. ICMS PMP Planning Process ..................................................................................................... 38
Figure 10. Dallas ICM Example: Risk Management Process .................................................................... 41
Figure 11. ICMS SEMP Planning Process ................................................................................................. 43
Figure 12. ICMS ConOps Planning Process.............................................................................................. 49
Figure 13. ICMS Architecture Planning Process........................................................................................ 59
Figure 14. Structured Analysis and Design Technique (SADT)................................................................. 60
Figure 15. Example: National ITS Architecture Parking Management Data Flow ..................................... 63
Figure 16. ICMS Context Diagram ............................................................................................................. 64
Figure 17. Dallas ICM Example: High-Level Integrated Corridor Management System Concept ............. 66
Figure 18. ICMS Requirements Planning Process .................................................................................... 68
Figure 19. ICMS Detailed Design Planning Process ................................................................................. 77
Figure 20. ICMS Build and Test Planning Process .................................................................................... 83
Figure 21. ICMS Operations and Maintenance Planning Process ............................................................ 90
Figure 22. San Diego ICM Example: I-15 ICMS Summary of Operations and Maintenance Activities ..... 95
Figure 23. Incident Events with “Recommended” Response Plans from 8/16-9/29, 2014 ........................ 96
Figure 24. I-15 Integrated Corridor Management Alternate Route Wayfinding Sign Locations. ............... 98
Figure 25. ICMS System Retirement/Replacement Planning Process .................................................... 100
Figure 26. I-5 Corridor, Seattle ................................................................................................................ 104
Figure 27. Truck Fire Incident on I-5 ........................................................................................................ 105
Figure 28. ICM Strategic Areas ................................................................................................................ 107
Figure 29. ICM Levels .............................................................................................................................. 111
Figure 30. ICM Environment .................................................................................................................... 112
Figure 31. Dallas ICMS DSS Concept ..................................................................................................... 127
iii
Abstract
This implementation guide is intended for use by adopters of integrated corridor management (ICM)
approaches and strategies to address congestion and travel time reliability issues within specific travel
corridors. It introduces the topic of ICM and identifies the type of information system, the integrated
corridor management system (ICMS) that is used to support transportation network managers and
operators in applying ICM.
The guide discusses typical issues (lessons learned) that arose during the U.S. Department of
Transportation’s (U.S. DOT’s) research initiative, where the U.S. DOT partnered with eight transportation
agencies in large metropolitan areas (known as “Pioneer Sites”) to research effective means of
implementing ICM approaches in their major travel corridors. Each of the Pioneer Sites used a systems
engineering approach to define the needs for ICM within their corridor and the needs and requirements
for an ICMS to support ICM. Two of the original eight Pioneer Sites were selected to serve as Pioneer
Demonstration Sites, where an actual ICMS was built, operated, maintained and evaluated to assess how
effective ICM strategies were in improving the flow of traffic within the corridor.
The guide offers suggestions for each stage of an implementation effort for an ICMS, to assist other
agencies in benefitting from the research done to date and from the experiences of the Pioneer Sites.
The guide is only one of a set of documents that the U.S. DOT intends to publish to provide guidance and
advice to prospective adopters of ICM. In addition to the material covered in the guide itself, there are
extensive references to other documents and source material that can assist ICM adopters in
successfully applying these concepts for their regions. It is important to note that both sites are continuing
to operate and make enhancements to their ICM deployments, as well as expanding the system to other
corridors within their respective regions.
Please note that this Version 2.0 of the ICM Implementation Guide and Lessons Learned supersedes
Version 1.0 of the ICM Implementation Guide and Lessons Learned published in February of 2012. At the
time the version 1.0 guide was written, the Dallas and San Diego ICM Pioneer Sites were still in the
system definition and design stages of the project lifecycle. This version 2.0 update of the guide provides
additional lessons learned and examples through the full implementation of the Dallas and San Diego
ICM Pioneer Site projects.
Chapter 1. Introduction to the ICM Guide
Chapter 1. Introduction to the ICM Guide
Overview
Integrated Corridor Management (ICM) is a promising tool in the congestion management toolbox that seeks
to optimize the use of existing infrastructure assets and leverage unused capacity along our nation’s urban
corridors. ICM is defined as a collection of operational strategies and advanced technologies that allow
transportation subsystems, managed by one or more transportation agencies, to operate in a coordinated and
integrated manner[1]. With ICM, transportation professionals manage the transportation corridor as a
multimodal system rather than taking the more traditional approach of managing individual assets.
Beginning in 2006, the U.S. DOT partnered with eight “Pioneer Sites” in an initiative to develop, deploy, and
evaluate ICM concepts in our Nation’s busiest corridors—the ICM Pioneer Sites are listed in Figure 1.
Because of practical limitations, only two of the initial eight sites (those identified with an asterisk) were
selected to deploy and operate and maintain ICM systems
Figure 1. U.S. DOT ICM Pioneer Sites
(ICMS). The U.S. DOT ICM Initiative aims to advance the
state of the practice in transportation corridor operations to
manage congestion. This initiative is providing the institutional
Dallas, Texas*
guidance, operational capabilities, Intelligent Transportation
Houston, Texas
Systems (ITS) technology, and technical methods needed for
Minneapolis, Minnesota
effective ICMS.
Montgomery County, Maryland
Oakland, California
ICM can be viewed as the evolution of ITS technologies: first,
San Antonio, Texas
agencies deployed individual devices; next agencies deployed
San Diego, California*
separate modal systems; and now agencies are working on
Seattle, Washington
multi-modal integration in ICM. ICM can improve corridor
* ICM Pioneer Demonstration Sites
travel by integrating existing ITS devices and systems,
including assets operated by different agencies, into a
proactive solution designed to manage demand and capacity
across all travel modes. This evolution to ICM brings
operational benefits as well as the challenges of technical complexity and interagency coordination. The
purpose of this ICM Implementation Guide is to provide information to ICM “early adopters” on how to plan,
develop, deploy, operate, and maintain an ICMS. This guide addresses both the benefits and challenges by
explaining the ICM project process and conveying firsthand knowledge and experience from the ICM Pioneer
Sites.
The target audience for this guide is public-sector transportation project managers who wish to implement an
ICMS in their region. Note, that this guide is not a “how to” manual on Systems Engineering for an ICMS. The
Systems Engineering process is used as the framework for the ICMS project process; however, the breadth of
the Systems Engineering process is too extensive to cover comprehensively for ICM in a short guide of this
type. This guide describes the phases in the system life cycle and the associated ICMS deliverables, focusing
on how the ICM Pioneer Sites addressed each phase.
The U.S. DOT ICM initiative is a multi-stage effort spanning several years. In the first stage, the eight Pioneer
Sites developed their Concept of Operations and System Requirements Specification. In the second stage
three sites—Dallas, Minneapolis, and San Diego—were selected to model the potential impact of ICM on their
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 1
Chapter 1. Introduction to the ICM Guide
corridors. In the third stage two sites—Dallas and San Diego—were selected as ICM Pioneer Demonstration
Sites to design, build, operate, and maintain their respective ICMSs and evaluate the impact on the corridors.
The goal of this guide is to further the ICM program toward the ultimate goal of empowering future
locations to implement ICM and seeks to fulfill the following set of objectives for the reader: Use the
applicable steps and deliverables from the Pioneer Site Process;
Focus on measures and benefits, including performance monitoring and performance
management;
Understand ICM operations and maintenance (O&M);
Adhere to existing Federal Highway Administration/Federal Transit Administration (FHWA/FTA)
rules, policy, and guidance—for example, the FTA Policy and FHWA Rule on ITS Architecture
and Standards Conformity;[2]
Provide references to other guidebooks for more detail on ITS and Systems Engineering; for
example, the FHWA Systems Engineering for ITS Handbook[3] and the FHWA/ California
Department of Transportation (Caltrans) Systems Engineering Guidebook for ITS: Version 3.0;[4]
and
Identify some unique challenges of ICM implementation.
This guide advises a potential ICM adopter both on the references the site should use from its region and on
the appropriate references from Pioneer Sites and Standards Development Organizations. Several examples
are included, as well as some templates. The appendices contain additional information to assist the reader,
such as a list of acronyms and abbreviations and a bibliography of references and resources.
An important component of ICM is Analysis, Modeling, and Simulation (AMS). The use of AMS provides ICM
adopters with the means to assess operational strategies before they are implemented and to continuously
monitor changing conditions and operational effectiveness. The AMS methodologies used for ICM receive their
own special treatment in the ICM AMS Guide. The ICM AMS Guide has been incorporated into the Federal
Highway Administration (FHWA) Traffic Analysis Toolbox (Volume XIII) and Traffic Simulation Guidelines.
Implementers of ICM are well served to consider the ICM AMS Guide in its entirety.[5]
How to Use This Guide
Chapters 1 and 2 of this guide introduce ICM and the potential complexity of deploying systems to support it.
These chapters also explain the distinction between ICM and an ICMS. Chapter 3 of this guide provides some
insight on what it takes to implement an ICMS including suggestions for management of the process,
highlights of recommended practices and ICMS challenges, testimonials, lessons learned, and examples from
the Pioneer Site implementations.
In chapter 3, sections 1 through 7 follow an intentionally similar format. Each section provides information on
one of the seven phases of an ICMS implementation. The length of time needed to complete each phase of an
ICMS implementation depends on the size and complexity of the project. Because of a potentially longtime to
complete implementation phases, the sections were designed to be read independently as the project
progresses.
Each section starts with a brief summary of the project phase and then each phase description contains the
following information areas—manage for quality, resources, process highlights, questions to answer, lessons
learned, and example. This convention should aid the reader in understanding the process and will provide
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 2
Chapter 1. Introduction to the ICM Guide
consistency for the reader in using the guide as a reference throughout the process by tying together the
different phases using similar themes. These six information areas are described below.
Manage for Quality
Each Manage for Quality section provides guidance on the management structure for each implementation
phase, describing important activities for which the leader of the given phase will be responsible. Each
Manage for Quality section also includes a graphic showing some of the typical planning/development
activities that will occur in each phase of the ICM implementation (note that the diagram is in the Highlights
section in a few instances). See Figure 2 for the overall generic structure diagram.
Figure 2. Generic Structure Diagram
[Source: Modeled after: Systems Engineering Guidebook for Intelligent Transportation Systems,
Version 3.0, U.S. DOT, November 2009.]
These graphics are adaptations from the Systems Engineering Guidebook for ITS[6] and are tailored for an
ICM implementation. Each graphic includes inputs, activities, and the resulting outputs for each phase of the
project. Outputs of one project phase often become inputs to the next project phase and may be seen on the
graphic for the next project phase. The graphics also include constraints on the project phase, which are
typically items that control or impose limits on the work (e.g., laws, rules, guides, and standards). Stakeholders
may want to add additional controls, inputs, or outputs that they deem necessary. The graphics also identify
the physical enablers or resources that facilitate the activities. Many activities identified in the graphics
correspond to typical project planning and development activities (e. g., feasibility studies, simulation and
modeling, regional ITS architecture), so no explanation is provided in this guide for those activities. However,
for those activities that may be new to some implementers, the guide provides guidance and or resources to
assist readers with those activities.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 3
Chapter 1. Introduction to the ICM Guide
Resources
Each section of the guide provides a list of key resources. A brief summary of the resource is provided as it
relates to each project phase. For detailed information on each resource, the reader should access the
endnotes, which provide specific page, appendix, and template references.
Highlights
Each section includes a phase highlights section that provides information on and examples of some of the
more challenging and perhaps less well-known activities in each project phase. These activities were
specifically included to help implementers understand the less well-known ICM implementation concepts.
Questions to Answer
Each section includes questions that stakeholders should address during reviews of the project or prior to
completion of each phase. Stakeholders may want to add to the list to satisfy their own unique project needs.
Lessons Learned
Each section includes lessons learned from the ICM Pioneer Site implementations. These lessons learned
provide some insight into challenges that ICM implementers may encounter and recommendations for
implementing solutions.
Pioneer Site Example
Finally, each section includes a featured example of work performed during the ICM Pioneer Site
implementations. These examples are not intended to be recommended practice; however, they do provide a
perspective on work that the sites performed. Considering these were pioneer projects, future ICM
implementers may want to consider adopting process improvements for future implementations.
The guide highlights each Pioneer Site example in a separate box set apart from the text of the guide as
shown below.
Pioneer Site Example
Throughout the text there are other examples both from the Pioneer Sites and from other sources that are
highlighted in this manner.
Note: This guide does assume some understanding of project management and systems engineering. It is
strongly recommended that both project management and systems engineering expertise be available to
ensure project processes are conducted correctly.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 4
Chapter 2. Understanding Integrated Management of Transportation Corridors
Chapter 2. Understanding Integrated
Management of Transportation Corridors
This chapter explains the main concepts and benefits of Integrated Corridor Management and Integrated
Corridor Management Systems. Additionally, this chapter gives some perspective on how to manage the
complexity of an Integrated Corridor Management System.
What Is Integrated Corridor Management?
Integrated Corridor Management is the operational coordination of multiple transportation networks and crossnetwork connections comprising a corridor and the institutional coordination of those agencies and entities
responsible for corridor mobility.[7] It will transform the manner in which transportation networks are managed
within a corridor, enabling agencies to see the overall impact of multimodal transportation network
management decisions and to optimize the movement of people and goods within the corridor instead of just
on individual networks.
“The overall ICM process is extremely
helpful in bringing together multiThe integration of operations among all transportation networks
modal stakeholders to discuss the
within a corridor is one solution to the growing congestion
organization and management of
problem and its resulting mobility reductions within urban
corridor resources to achieve
transportation corridors. Integration maximizes the effectiveness
operational efficiencies for corridor
of operations and mitigates the effect of incidents that affect the
transportation.”
movement of people and goods within the corridor. This
integrated operation of corridor transportation networks is the
Koorosh Olyai
subject of a major U.S. DOT initiative known as Integrated
Assistant Vice President
Corridor Management. Without ICM, each transportation
Mobility Programs Development
network operator reacts to changes in demand or capacity in
Dallas Area Rapid Transit
the manner permitted by the operator’s network management
system. The freeway operator, for example, might post
messages on dynamic messaging signs located sufficiently before an incident to divert travelers from one
freeway to another (if possible) or to the arterials that allow operators to bypass the incident. However, if the
arterial network operators are not expecting this additional
volume on their roads, their networks may become congested,
“ICM provides the opportunity to
and delays may build. Similarly, transit bus operators cannot
proactively improve and maximize the
prepare for or encourage travelers to shift to their mode of
performance of the transportation
transportation, since they are not expecting any reason for
system by serving as an alternate to
increased demand. With an effective ICM approach in place,
traditional major infrastructure
however, the transportation system operators in the corridor
investments which may be more
would be able to take a series of actions that could mitigate the
expensive or constrained by
effects of increased demand or reduced capacity on the entire
environmental issues”
corridor.
Alex Estrella, ICM Manager,
ICM is about more than just incident management or incident
San Diego Association of
response. The concept of ICM is further explored in the white
Governments
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 5
Chapter 2. Understanding Integrated Management of Transportation Corridors
paper “Conceptualizing Integrated Corridor Management” in Appendix A. This white paper provides a detailed
examination of the following four strategic areas of ICM:
Demand Management
Load Balancing
Event Response
Capital Improvement
In addition to understanding what ICM is, agencies interested in ICM also want to answer these related
questions:
Should I implement ICM?
What are some ICM strategies?
What benefits can I expect from ICM?
These three questions are examined below.
Should I implement ICM? In determining a viable candidate corridor for ICM, it is helpful to answer the
following questions about the current operations in the corridor:
Is congestion in the corridor increasing and are travel times becoming less reliable?
Does the corridor have existing infrastructure and systems for each modal network and can the
existing infrastructures and systems be effectively integrated?
ICM provides benefits through corridor-wide capacity optimization across all networks
and modes.
Do some of the agencies in the corridor already have agreements to coordinate operations and
management?
ICM will facilitate informed travel decisions to maximize corridor efficiency.
Are the existing transportation systems fully optimized?
ICM requires a solid foundation of real-time or near real-time data for coordination of
effective responses to corridor conditions.
Does the corridor contain alternative routes and modes for travelers?
ICM can take advantage of these systems to meet the operational needs of the corridor.
Do existing infrastructure devices and systems provide real-time or near real-time data on
corridor conditions that can be used to compute corridor performance measures and to assess
the effectiveness of potential control strategies?
ICM strategies can provide a near-term solution to these issues.
Implementing ICM would involve expanding operations to involve all transportation
networks in a corridor.
Are all relevant agencies on board with supporting corridor operations? To be effective, ICM
requires resource commitments (personnel and funding) from all affected agencies.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 6
Chapter 2. Understanding Integrated Management of Transportation Corridors
What are some ICM strategies? Determining the most effective ICM strategies is part of the process of
implementing ICM. To better understand some of the strategies used as part of ICM, it is helpful to look at the
example of the ICM Pioneer Demonstration Sites and their respective strategies listed below:
Dallas, Texas, US 75 ICM Proposed ICM Approach and Strategies by Goal:[8]
Increase corridor throughput: HOV lanes, transit usage increase,
increase/maximize supply (additional transit, additional parking, and diversion of
vehicles), integrated approach to management (trade-offs between agencies to
improve overall corridor operations), and modeling of corridor and strategies (for
the decision support subsystem);
Improve travel time reliability: advanced traveler information system (ATIS) and
incident management (response time improvements – consistent goal among
agencies within corridor);
Improved incident management: inter-agency cooperation, inter-agency
information sharing (center-to-center), agency training on common approach
(current courses available), integrated policies for incident response (towing
policies, response times), and decision support model (for historical, and near
real-time scenario evaluation); and
Enable intermodal travel decisions: model of multi-mode system, ATIS
(availability of other modes, linked Web sites/portal, and third party integration),
and marketing/advertising (public outreach/education).
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 7
Chapter 2. Understanding Integrated Management of Transportation Corridors
San Diego, California, ICM Strategies Based on the I-15 Corridor Goals and
Objectives:[9]
Share/distribute information: manual information sharing, information
clearinghouse/information exchange network between corridor networks and
agencies; 511 (pre-trip traveler information); en-route traveler information (smart
signage and smart parking); access to corridor information by ISPs and other
value-added entities; automated information sharing (real-time data); and
common incident reporting system and asset management system;
Improve junctions/interfaces: signal pre-emption – identifying “best route” for
emergency vehicles; multimodal electronic payment; signal priority for transit, bus
priority on arterials; transit hub connection protection; multi-agency/multi-network
incident response teams/service patrols; and training exercise;
Accommodate/promote network shifts: modify ramp metering rates to
accommodate traffic (including buses) shifting from arterials; promote route shifts
between roadway and transit via en-route traveler information devices; promote
shifts between transit facilities via en-route traveler information devices;
congestion pricing for managed lanes; and modify arterial signal timing to
accommodate traffic diverted from the freeway;
Capacity/demand management (short-term): land use control; modify HOV
restrictions; increase roadway capacity by opening HOV/HOT lanes/shoulders;
scheduled closures for construction; coordinate schedule maintenance and
construction activities among corridor networks; planned temporary addition of
transit capacity; and modify parking fees (smart parking); and
Capacity/demand management (long-term): peak spreading; ridesharing
programs; expand transit capacity; and land use around BRT stations.
What benefits can I expect from ICM? The potential effects of ICM have been simulated at the three Pioneer
AMS Sites. The results of these experiments have been documented and some example results are listed in
Table 1 below. The differences in benefits among each of the Pioneer AMS Sites are the result of differences
in corridor sizes, selection of control strategies, and other factors that varied from site to site. What is
consistent, however, is that the overall benefit-cost ratios are all at least 10:1. (Note: the table lists net benefits;
i.e., total benefits minus total costs, rather than overall benefits.)
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 8
Chapter 2. Understanding Integrated Management of Transportation Corridors
Table 1. Expected Annual ICM Benefits of Pioneer Sites
Benefit (from Simulations)
Dallas
Annual Travel Time Savings (Person-Hours)
Tons of Mobile Emissions Saved Annually
10-Year Net Benefit
10-Year Cost
San
Diego
740,000
132,000
246,000
3%
4. 4%
10. 6%
981,000
17,600
323,000
9,400
175
3,100
$264M
$82M
$104M
$14M
$4M
$12M
20:1
22:1
10:1
Improvement in Travel Time Reliability
(Reduction in Travel Time Variance)
Gallons of Fuel Saved Annually
Minneapolis
Benefit-Cost Ratio
[Source: Integrated Corridor Management (ICM) ITS Benefits, Costs, and Lessons Learned:
2014 Update Report, USDOT FHWA. 2014]
What Is an Integrated Corridor Management System?
While ICM is the concept and practice of managing a corridor in an integrated fashion, the ICMS is the
underlying infrastructure that enables agencies to perform that management process in an efficient manner.
An ICMS is a set of tools to help the corridor’s transportation network managers and operators achieve the
ultimate goal of keeping their networks operating at optimal levels.
“The level of achieved success will be
The ICMS can use existing network infrastructure to facilitate new
subject to the fact that ICM will
functionality. Figure 3 shows examples of the types of
change how we operate and manage
independent systems, each used to manage some aspect of the
transportation systems. Stakeholders
transportation networks in a corridor that an ICMS might integrate.
should be prepared and positioned
The infrastructure used to manage these transportation networks
themselves to change how
includes useful communication systems, archived and near realstakeholders will operate and manage
time data systems, AMS systems, roadside control systems, and
their individual systems under an ICM
other corridor assets. Through integration of these systems, an
environment.”
ICMS can expedite communication and enhance the decisionmaking capability of operators through shared operations,
management, and data as well as by performing analyses that
may not be available without the ICMS. This helps corridor
transportation network operators better understand the conditions
of the systems that they manage both individually and collectively.
Alex Estrella, ICM Manager,
San Diego Association of
Governments
In the example shown in Figure 3, the central integration element is the collaborative management of a set of
networks and systems, accomplished by human interaction and possibly a set of both automated and nonautomated tools. One major automated tool not shown in this figure is the Decision Support System (DSS).
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 9
Chapter 2. Understanding Integrated Management of Transportation Corridors
Figure 3. San Diego ICM Example: Developing Systems for High Performance Corridors
CMS
Transit and
FSP/TMT
Management
CCTV
Freeway
Management
Collaborative Management
Arterial
Management
CMS
Traveler
Information
Services
and Vanpool
CCTV
Incident Management
[Source: San Diego ICM Pioneer Site Kick Off Meeting presentation, October 24, 2006,
unpublished.]
Another way to view an ICMS is as a group of independent systems joined (integrated) by a DSS. The ICMS
would use the DSS component to analyze corridor data and provide recommended congestion mitigation
strategies to corridor managers and operators. Figure 4 is a conceptual depiction of a DSS component for an
ICMS. The U.S. DOT has captured information on DSS efforts across the United States in a report entitled
“Assessment of Emerging Opportunities for Real-Time Multimodal Decision Support Systems in
Transportation Operations: Concept Definition and Current Practice Report.”[10] Additional details on the
information processed in a DSS and the potential improvements a DSS can make in an ICMS are included in
APPENDIX B. Defining the ICMS Decision Support System
The data from the independent network systems can be collected, integrated, and analyzed to provide
operators with the benefit of an automated DSS. The DSS might also employ AMS to offer improvements
(predictive capabilities) to corridor operators, and this can help them make better-informed corridor decisions.
An example of this may include the ability of corridor operators to promote mode shift during severe
congestion involving long delays. Through the ICMS, operators could access DSS information that will tell
them about the availability of capacity on other modes and the likelihood that travelers would be willing to
switch modes. If the likelihood is high and capacity is available, announcements could be made to travelers
that a mode switch may provide a better option for travel. Additionally, the DSS could allow real-time
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 10
Chapter 2. Understanding Integrated Management of Transportation Corridors
monitoring and prediction of the impact of these decisions so operators can change their approach to be more
responsive to real-time changes in the network.
Figure 4. San Diego ICM Example: Future Decision Support System (conceptual)[11]
C orridor Management
T ransportation
C oordinator
IMT MS W eb S ervices
T ransportation
C oordinator
Monitoring S trategies
511
X ML
D ecision
S upport
S ys tem
X ML
C ontrol S trategies *
Arterial
(Quic Net 4+)
T ransit
(R T MS )
Area C oordinators
C onges tion
E vents
C MS
C C TV
S ignal P has ing
IMTMS
Network
S ignal timing
C MS s igning
C C T V control
F reeway E vents
A rterial E vents
R oad c los ures
E V routing
911 (C AD)
B us location
T rain location
E vents
S ecurity C C T V
S chedule
Modify bus s ervice
C reate new routes
R eg ional
T rans portation
Network
C onges tion
E vents
C MS
C C TV
R MS
R MS T iming
C MS s igning
C C T V control
*Us ing tools s uc h as :
•E xpert s ys tems
•G IS
•R eal-time modeling, etc.
F reeway
(AT MS
2005)
Modal C olor S c heme
F reeway
Arterial
T ransit
P ublic S afety
AT IS /511
[Source: Concept of Operations for the I-15 Corridor in San Diego, California, SANDAG, et al. for
U.S. DOT, FHWA-JPO-08-009. 31 March 2008, p. 5-3.]
Analysis, Modeling, and Simulation for ICM
The uses of AMS for ICM, along with the recommended ICM AMS approach, can be found in the ICM AMS
Guide.[12] Lessons learned from the three ICM Pioneer Sites selected for the AMS stage revealed that the
AMS process was extremely beneficial as it was credited with improving the accuracy of the analyses and
provided a more robust knowledge base for evaluating future strategies and investments.
The ICM AMS Guide offers a recommended ICM AMS approach, in a step-by-step format, to help the reader
conduct ICM AMS successfully and effectively. Guidance is provided to assist corridor managers and
analysis/modeling managers in successfully conducting AMS for their own ICM applications. AMS is not
intended to be performed as a one-time, self-contained planning process. Instead, AMS is intended to be an
ongoing, continual improvement process designed to assist practitioners in envisioning, designing, and refining
ICM strategies.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 11
Chapter 2. Understanding Integrated Management of Transportation Corridors
One step detailed in the ICM AMS Guide is how to evaluate existing traffic conditions to better understand the
factors that influence congestion and the frequency with which these factors occur. Evaluating influencing
factors provides the opportunity to identify the best combinations of multiple scenarios that are most
representative of actual conditions. This information can be used to define analysis scenarios that make the
best use of analysis resources. This allows analysis resources to be targeted towards appropriate scenarios
that do not under- or over-estimate the impacts of the ICM strategies.
The information on the impact of the ICM strategies can then be used, in turn, to help determine which
combinations of ICM strategies are likely to be most effective under which conditions. The ICM AMS Guide
also explains how AMS can be used to discern optimum combinations of strategies both to make the ICM
implementation more successful as well as to identify conflicts or unintended consequences inherent in certain
combinations of strategies that would otherwise be unknowable before implementation.
Appendix A of the ICM AMS Guide documents the algorithmic process developed under the ICM program that
is used to calculate key national measures of corridor performance. The algorithms offer a practical and
broadly applicable method of calculation while breaking new ground in the definition of mode-independent, tripbased measures of aggregate corridor performance with explicit consideration of probability-weighted
operational conditions. Appendix A provides a detailed description of how measures of delay, travel-time
reliability, and throughput are calculated from simulation outputs. A brief discussion of travel time variance is
also provided given that travel time variance measures are used in ICM-related benefit-cost calculations.
Managing the Complexity of an ICMS Implementation
Managing the complexity of an ICMS implementation will
not be easy. In most cases, the project will involve
bringing together multiple agencies that perform
operations using diverse methods and include the
integration of their heterogeneous systems. Increased
communication, organization and documentation will be
required to ensure that all project partners understand
and agree upon project expectations and are kept
informed of the status of the project. Systems
engineering is the discipline developed to manage the
complexity of large-scale systems. In particular, systems
engineering is often used in the management of software
intensive projects. It is highly recommended that a
systems engineering approach be used to manage ICMS
implementations. Having a defined process tailored to
the ICMS project will be critical for successful
implementation.
“The Systems Engineering process allowed us
to maintain a structured implementation
approach. This might seem a bit trivial and
obvious, but the implementation of the ICMS is
not like any other project as it touches on
different modes, systems, technologies, and
institutional elements. Following the SE
process has provided the roadmap to not only
assure that we deliver a successful project, but
also the SE process has helped us decipher
‘what-how-why’ items will be achieved and
presenting it in a way that is multiagency/modal focused and integrated.”
Alex Estrella, ICM Manager,
San Diego Association of Governments
The Systems Engineering Guidebook for Intelligent Transportation Systems, Version 3.0 describes a systems
engineering process for ITS projects. Figure 5 below shows an example of the systems engineering process
using the VEE development model. Chapter 3 of this guide provides more details on the systems engineering
process.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 12
Chapter 2. Understanding Integrated Management of Transportation Corridors
Figure 5. Systems Engineering VEE Diagram
[Source: Systems Engineering Guidebook for Intelligent Transportation Systems, Version 3.0, U.S.
DOT. November 2009.]
Working with multiple agencies often means dealing with a mixture of project management processes. Some
of the benefits of using systems engineering processes to manage the implementation of ICMS include
improved control of the project and common terminology, expectations, and understanding of the work being
performed. The Systems Engineering Management Plan
“When working with so many corridor
(SEMP) is developed early in the project process and will be
stakeholders it is critical to have a
agreed upon by all project stakeholders, providing them with a
defined process to guide the work,
harmonized systems engineering process for a successful
foster communication, and manage
project implementation. The SEMP provides a common
expectations. Stakeholders found that
understanding of how the work will be managed and provides
the systems engineering process
traceability from one phase of the project to the next. The SEMP
gave them the tools needed to
also helps to inform stakeholders about key project milestones
manage project efforts and achieve
and what role they will play in the success of those milestones.
ICM goals.”
Additionally, the SEMP identifies decision gates for the project.
These decision gates require agreement from all project
Koorosh Olyai
stakeholders for the project to move forward. With project
Assistant Vice President
controls in place, project stakeholders should feel more
Mobility Programs Development
confident that they know what work needs to be done and how
Dallas Area Rapid Transit
it will be carried out. More details on the SEMP are provided in
chapter 3, section 3.2 of this Guide.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 13
Chapter 3. ICM Implementation Guidance and Lessons Learned
Chapter 3. ICM Implementation Guidance and
Lessons Learned
This chapter provides a detailed description of the ICM implementation process including organization of the effort and
key activities. The implementation process is numbered as sections 1 through 7, which correspond to the following
seven phases:
1.
2.
3.
4.
5.
6.
7.
Get Started
Establish Goals
Plan for Success
Specify and Design
Build and Test
Operate and Maintain
Retire/Replace
This ICM implementation process is generally representative of the systems engineering process followed by the ICM
Pioneer Sites. The systems engineering process thus provides the framework for the guide.
provides a mapping of ICM implementation phases to the systems engineering phases and tasks used in the Systems
Engineering Guidebook for ITS.[13] Table 2 also provides a summary of the activities, products (outputs), staff roles,
and resources and templates associated with each of the phases.
At the beginning of each section, the graphic below is used to identify the phase being described. There is a numbered
block to represent each phase. Note that phases three and four are divided into three parts—each part corresponding
to each major work item. Also, note that the blocks in the graphic below match the phases shown in the columns in
Table 2.
[Source: Research and Innovative Technologies Administration, ITS JPO.]
As explained in chapter 1 under How to Use This Guide, the sections in chapter 3 were designed to be read
independently as each phase of the project progresses. Each section starts with a brief summary of the project phase
and then each phase description contains the following information areas: manage for quality, resources, highlights,
questions to answer, lessons learned, and example. Each section provides opportunities for improving the
implementation process and lessons learned from previous implementations.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 14
Chapter 3. ICM Implementation Guidance and Lessons Learned
Table 2. ICM Implementation Process
[Source: Research and Innovative Technologies Administration, ITS JPO.]
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 15
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
[Source: Research and Innovative Technologies Administration, ITS JPO.]
Get Started (Phase1)
This phase includes the activities conducted to identify and coordinate the participants and information
necessary to plan an ICM project. These activities are described following the guide convention described
previously: manage for quality, resources, highlights, questions to answer, lessons learned, and example.
Manage for Quality – Getting Started
One of the first things that needs to be accomplished when getting started with ICM is to choose a
stakeholder that will manage and lead the work to be performed. The following checklist includes some of
the more important activities for which the Project Lead will be responsible:
Schedule meetings to discuss activities, status, action items, and risks;
Ensure that guidance is made available to those stakeholders that are not familiar with ICM; and
Ensure that all stakeholders understand and are comfortable with the project process.
Getting Started Resources
There are many resources available to assist with getting started with ICM. For information on ICM,
stakeholders should visit the U.S. DOT ICM Web site: http://www.its.dot.gov/icms/. At the ICM Web site,
stakeholders will find a great deal of information on the concept of ICM and its implementation. There is
also an “ICM Knowledgebase” were people can search and find publications on ICM including
presentations, newsletters, and fact sheets as well as AMS results and systems engineering documents
from the ICM Pioneer Sites. Section 3.2.1 of The Systems Engineering Guidebook for ITS contains a
good description on “Interfacing with Planning and the Regional ITS Architecture.”[14] Section 3.9.1 also
provides good details on stakeholder involvement.
Getting Started Highlights
The following activities, also shown in Figure 6 below shows the planning process for getting started with
ICM. The inputs and constraints should be completed and available prior to beginning the activities.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 16
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Under the direction of the stakeholders, either in-house staff or a contractor will execute the activities and
deliver the outputs shown.
Figure 6 below shows the planning process for getting started with ICM. The inputs and constraints
should be completed and available prior to beginning the activities. Under the direction of the
stakeholders, either in-house staff or a contractor will execute the activities and deliver the outputs
shown. The enablers are the mechanisms used to manage and complete the activities successfully and
are described in the following sections:
Foster Champions and Organize Stakeholders
Coordinate with Planning Process
Interface with the Regional ITS Architecture
Develop and Approve Project Charter
Figure 6. Getting Started With ICM
[Source: Noblis for ITS JPO, Modeled after: Systems Engineering Guidebook for ITS, Section 3.2.1,
November 2009]
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 17
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Foster Champions and Organize Stakeholders
Building a team of stakeholders to assist with the planning and design of an ICMS is a critical first step in
moving forward. Metropolitan areas that are considering ICM will likely have formal or informal operations
planning groups from which to build an ICM Team. As a corridor is being considered for ICM, it is
important that all agencies affecting the operation and maintenance of all networks are invited and
participate in the planning of the ICM. The roles and level of involvement may differ, but to be most
effective, the ICM Team should consider all transportation resources (those affecting supply and
demand). Additionally, it is important to invite stakeholders that may simply benefit from the system, to
participate. If stakeholders receive enough benefit, they may be willing to share in long term funding
strategies for the system.
Cast a wide net early in the process, so as not to exclude possible stakeholders early on. The question of
who should be involved should be left to the participants themselves, although it is important to keep all
stakeholders informed throughout the process, even when they are not directly involved. Let the
stakeholders determine their own involvement as the process moves forward. The initial invitees will likely
come from various operations groups and technical committees and should cover the following groups:
Inter-jurisdictional– DOT, Metropolitan Planning Organization (MPO), local
Multimodal– rail, bus, freeway, arterial, freight
Public Safety Services – police, fire and rescue, safety service patrol
Support Services – parking, traveler information systems/511 providers, commuter/rideshare
organizations, media, tolling
As the ICM stakeholder group is being formed, several items regarding how to coordinate efforts should
be considered:
Determine the Lead Agency and Points of Contact (POCs)
Which agency will take the lead on organizing and hosting meetings?
Which agency will provide administrative support, such as note taking and documenting
action items?
Who are the points of contact for the stakeholder group?
Which agency will provide resources or initial funding for preliminary activities?
Determine the mission, activities, and operating procedures
What are the initial activities to be conducted?
What are the interpersonal communication protocols? How do we make sure all
participants are on the same page?
What are the decision protocols? How are decisions made among the participants?
Determine the relationship with existing processes and groups
How will this ICM stakeholder group relate to the existing planning process?
How will it relate to other local/regional operations technical committees?
As the stakeholder group is organized, the champion or champions need to be identified (generally
champions will “self-identify”) to lead the ICM team. In some cases, champions will need to be fostered or
encouraged because of their strategic importance to the success of ICM in the region. This strategic
importance could be related to their role, position, or influence in the corridor. In addition, it may be
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 18
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
beneficial to ensure that all of the key operating agencies in the corridor have a champion, since this will
provide momentum for that agency’s involvement in the project. Ideally, the champion(s) should:
Understand ICM and the concept of corridor operations;
Be able to lead a diverse team;
Possess good communications skills;
Be willing to commit the necessary time to the project; and
Be able to marshal the necessary funding and personnel resources.
The Systems Engineering Guidebook for ITS makes the following points on the role of the champion:
Good leadership includes imparting the vision of the project:
Why it is needed?
How it will help solve current problems?
How it will benefit each of the stakeholder groups?[15]
Coordinate with Planning Process
ICM planning should be effected within the framework of the transportation planning process and guided
by regional priorities. Planning for ICM is an objectives-driven, performance-based approach that can be
thought of as “planning for operations” at the corridor level. Planning for operations is a joint effort
between planners and operators to support improved regional transportation system management and
operations. It requires coordination and collaboration between a number of regional partners, including
planning staff and operations staff from metropolitan planning organizations (MPOs), State departments
of transportation, transit agencies, highway agencies, toll authorities, and local governments. It involves
the consideration of management and operations (M&O) strategies in transportation planning – including
the integration of M&O strategies in the metropolitan and statewide transportation plans. The FHWA
Office of Operations maintains a Web site[16] that lists (and provides links to) a number of documents
that relate to coordinating planning and operations at the State, regional, and local levels. The ICM
planning group should consider these documents in its planning process.
ICM strategies can be simply thought of as M&O strategies with certain characteristics as discussed in
chapter 2: they support the integrated operation of transportation networks within the corridor.
The following list gives the primary elements of the objectives-driven, performance-based approach to
planning for operations.[17]
Regional Goals. Establish goals that focus on efficiently managing and operating the
transportation system.
Operations Objectives. Develop operations objectives—specific, measurable statements of
performance—to include in the Metropolitan Transportation Plan or Long-Range Statewide
Transportation Plan (MTP/LRSTP) that will lead to accomplishing the goal or goals. The
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 19
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Advancing Metropolitan Planning for Operations Desk Reference provides recommendations on
how to phrase these operations objectives.[18]
Performance Measures. Using a systematic approach, develop performance measures, analyze
transportation performance issues, and recommend management and operations (M&O)
strategies.
M&O Strategies. Select M&O strategies within fiscal constraints to meet operations objectives for
inclusion in the MTP/LRSTP and STIP/TIP.
Investment and Implementation. Implement strategies, including program investments,
collaborative activities, and projects.
Monitoring and Evaluation. Monitor and evaluate the effectiveness of implemented strategies and
track progress toward meeting operations objectives.
Before federal funds can be approved and used for implementation, the ICM project(s) must be
programmed on the metropolitan transportation improvement program (TIP) or the statewide
transportation improvement program (STIP). In the early planning phase for ICM, it is likely that planning
funds will be used to support initial activities.
ICM Planning Questions to Consider in Get Started Phase:
1. What data is available in the region to monitor transportation system performance and track
progress toward operations objectives?
2. What are the gaps, problems, and issues in providing transportation system management and
operations across our region?
3. What are the transportation corridors that are best suited to be candidates for ICM deployment?
4. What ICM strategies may be available to help achieve our operations objectives?
5. How can we most effectively integrate ICM strategies with other existing or planned technology
deployments to provide a greater level of service for the customer?
6. How can we define this ICM project or program in terms of functional requirements and
operations concepts?
Key points to consider in planning for ICM:
Conduct ICM planning within the context of the approved transportation planning process;
Take advantage of the data available from the planning process;
Specify goals and measurable objectives that advance operational performance outcomes for the
regional transportation system;
Consider the benefits of incremental deployment of ICM in a series of related projects to
accomplish the ultimate vision of ICM within the corridor;
Consider how ICM will relate to other corridors, services, and systems within the region;
Identify performance measures that allow the region to track progress toward achieving its
objectives; and
Ensure that ICM (and any ICMS built to support it) are captured within the context of the regional
ITS architecture (see section 1.3.3 below).
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 20
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Interface with the Regional ITS Architecture
A regional ITS architecture is defined as “A specific, tailored framework for ensuring institutional
agreement and technical integration for the implementation of ITS projects or groups of projects in a
particular region. It functionally defines what pieces of the system are linked to others and what
information is exchanged between them.”[19]
The regional ITS architecture serves as an important guide for the development of ICM. The regional ITS
architecture shows all of the existing and planned operational transportation systems in a region and how
they will fit together. From a planning perspective, the regional ITS architecture supports the region’s
objectives and the specific needs of transportation planning agencies. It shows how data is collected,
archived, and processed to support transportation planning and performance monitoring.
Components of the regional ITS architecture include:
Scope: Definition begins with a clear statement of the geographic and jurisdictional boundaries, the time
horizon, and the scope of transportation services that are covered by the architecture. The Rule/Policy
leaves a lot of latitude to the region in defining the scope, but suggests that the regional ITS architecture
cover the entire metropolitan area at a minimum. The ICM project or program will likely be considering a
subset of the region, but in some cases the physical corridor boundaries may necessitate the need to
consider multiple regional ITS architectures.
Stakeholders: A list of the traffic agencies, transit operators, public safety agencies, traveler information
providers and other organizations and groups that plan, develop, operate, maintain, and use the regional
transportation system is included in every regional ITS architecture. This broad stakeholder list should
include all of the agencies that are involved in transportation planning, operations, and management as
well as groups that use the transportation system (e.g., fleet operators) or impact its operation (e.g.,
special event venue owner/operators). This list of stakeholders provides a good check to ensure that you
have invited all relevant stakeholders to ICM planning meetings.
Roles and Responsibilities: The regional ITS architecture also defines the high-level roles and
responsibilities of each of the stakeholders that operate and manage the transportation system as part of
an “operational concept” for the region. The roles and responsibilities are short statements like “share
CCTV video feeds with other agencies in the region.”
Inventory: This is a list of the existing and planned components or “elements” of the regional
transportation system. The inventory elements are frequently systems in their own right and include the
operational centers (e.g., a State DOT Freeway Management Center), field equipment (e.g., the dynamic
message signs, CCTV cameras, and signal systems), vehicles (e.g., transit vehicles and public safety
vehicles), and traveler equipment (the devices the traveler uses). Importantly for ICM planning, the
inventory should also include any monitoring and data collection systems that are used by transportation
planners.
Interfaces: A definition of the interfaces between the inventory elements is a focal point of the regional
ITS architecture. Each interface is represented as both an “Interconnect” (indicating whether there is a
connection between the two elements) and as a set of information flows or “architecture flows” that
describe the information that is shared. The architecture flows are also associated with relevant ITS
standards.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 21
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Services: The ITS Services that are included in the regional ITS architecture represent a consensus of
the architecture stakeholders. These ITS Services are implemented through projects.
Project Sequencing: The regional ITS architecture is implemented through many transportation
programs and projects that occur over years or even decades. The regional ITS architecture includes a
sequence that allocates projects to broad timeframes like near- (0-3 years), mid- (3-7 years), and longterm (8+ years). The project sequencing often provides finer granularity than the ITS services, particularly
for near-term projects. Having the knowledge of what ITS projects are coming on line and being
designed is very important to effective ICM planning. This information can be leveraged to consider
opportunities to add ICM-specific objectives and requirements onto ITS projects that are being
implemented. By piggybacking ICM functionality on approved projects, transportation agencies can
reduce the cost of implementing ICM.
Agreements: The regional ITS architecture also includes a list of agreements because institutional
coordination is required to support the technical integration that is shown in the architecture. The list of
agreements should identify the existing and planned agreements in the region that are needed to support
an integrated transportation system. Note that the agreements should extend beyond implementation into
operational agreements that define agency roles and responsibilities for system operation.
All of the architecture components are defined in more detail in the regional ITS architecture Guidance
Document.[20]
The regional ITS architecture provides a very good starting point for ICM planning activities. It is important
to remember that planning and implementing the ICM project(s) may necessitate changes to the regional
ITS architecture to take into account the planned ICMS. This is to be expected and is simply a normal
part of the regional ITS architecture maintenance process.
Develop and Approve Project Charter
The development of a project charter is a recommended practice of the Project Management Institute.
The purpose of the project charter is to formally authorize a project or a phase and to document the
business case and the initial requirements that satisfy stakeholders’ needs and expectations. The
approved project charter identifies the project manager and deputy project manager and formally initiates
the project, in this case the ICM project. The charter provides the project manager with the authority to
apply resources to project activities.
This concept can easily be adapted to the ICM process. The development of the ICM project charter
should be one of the first activities that the ICM stakeholder group embarks upon. The ICM project charter
should be a brief document containing mission and vision statements that reflect the consensus view of
the involved stakeholders and should briefly describe the need for ICM in the corridor. The development
of the charter begins the process of getting the stakeholders to work together to reach agreement as a
group and achieving buy-in from individual agencies on continued participation in the stakeholder group
activities. The ICM charter could be considered a variation of a memorandum of understanding (MOU) or
memorandum of agreement (MOA) and should be signed or approved by all stakeholder agencies. If
necessary, the ICM charter should be revised over time as warranted by changes to the ICM
management structure or stakeholders.
The funding that is authorized at this stage may be limited to what is needed to carry out the initial
planning work, but reflects stakeholder commitment to the ICM project.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 22
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
The ICM Project Charter should include:
The project purpose and a brief ICM vision statement;
Transportation needs to be addressed by ICM in the corridor;
ICM corridor boundaries and high-level project scope;
Project success criteria and milestone approval requirements;
Roles and membership of the ICM corridor stakeholder group;
Assigned project manager and deputy project manager and a clear description of their
responsibilities and authority level;
Approved funding and resource commitment; and
Summary schedule.
Questions to Answer – Getting Started
In getting started with ICM, stakeholders need to make certain consensus decisions to initiate the project.
It is important for the stakeholder group to answer the main questions about the proposed project before
proceeding to subsequent phases of the project. The following is a list of ICM questions to start with:
Has a list of stakeholders been agreed upon and have potential champions been identified?
Have steps been taken to coordinate with the transportation planning process?
Has the ICM Team addressed the interface with the regional ITS architecture?
Was a Project Charter approved by the stakeholders?
Have initial and lifecycle funding issues been discussed?
Lessons Learned – Getting Started
The following lessons apply to this phase of the ICM program:
Stakeholder selection – When initiating an effort to consider ICM for a regional corridor, look to
include all potential stakeholders early in the process. Some agencies and organizations may
choose not to participate, but all should be invited.
Stakeholder involvement – Let potential stakeholders decide what their involvement will be as the
process moves forward, but encourage as broad a participation as possible. Even if agencies or
organizations choose not to participate at the start, keep them informed about the decisions being
made. Initially reluctant partners can prove to be strong participants later on.
Initiate stakeholder agreements – Initiate discussion of partner agreements early and try to
identify the benefits to potential partners that help them justify committing to the project. There is
a need to understand the business models of every partner and how to get them (e.g., tolling, and
parking) involved. You need to find the incentive to get them to commit on day one. Why would
a toll road want congestion eased if that is how they make money? Well, there is also the parking
aspect and a lot of them make money on the parking too. Also, tolling agencies may see benefits
due to reduced incident congestion on the toll roads and improved throughput allowing them to
collect more revenue. You have to find out if they are willing to sign on to the project and do it
early.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 23
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Leadership commitment – Involve executive leaders in facilitating the multi-agency partnerships
vital to the long-term success of ICM. Their support is essential and it is particularly valuable if
one (or more) of those executive leaders becomes a champion for ICM. Leadership turnover
plans should also be considered to get new leadership on board and in support of the project.
Planner and modeler input – Involve transportation planners and modelers, along with the
transportation operations personnel, early in the process. Transportation planners and modelers
can provide input into the performance measures selected and can help the team understand
how best to track system performance against the established goals. Ongoing funding will likely
be tied to performance so this is an important consideration for the project.
Systems engineering training – The ICMS will be a complex system, make sure that stakeholders
receive early training on systems engineering to prepare them for defining the system and
managing its complexity. Use a qualified SE trainer and have a SE 101 course to kick-off the
process. Having a good basic understanding of SE is the most important thing before anything
else starts.
Project skills – These projects require a lot of different skill sets (e.g., traffic engineers, signal
system experts, freeway management experts, software specialists, data specialists, good
operators, good managers, and a strong champion or leader.)
Network operational environments – Holding meetings in the offices of other stakeholders is
helpful to understand the working environment of all stakeholders.
Agency restrictions and limitations – Stakeholders need to be sensitive and try to understand the
restrictions and limitations of other agency partners.
Contracting for success – Consider roles, responsibilities and accountability when selecting prime
and subcontractors. It may be easier for agencies to work with one prime contractor that holds
subcontracts rather than having multiple contractors reporting to them. This may minimize the
some “not in my scope” responses to project requests. Of course, each circumstance is unique,
so this is just one consideration for setting up contracts. Pioneer Site Example –Getting Started
Pioneer Site Example – Getting Started
The Dallas ICM Pioneer Site built its coalition of stakeholders out of the pre-existing institutional
arrangements within the North Texas Council of Governments. The agencies have a history of
cooperation, including efforts on the North Texas Regional ITS Architecture, which facilitated
development of the ICM coalition, and the US 75 Corridor Steering Subcommittee meets on a regular
basis to discuss ICMS planning and deployment activities. Figure 7 below shows the institutional
framework established by the eight stakeholder agencies for the US 75 ICM.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 24
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
Figure 7. US-75 ICM Institutional Framework[21]
Source: Concept of Operations for the US-75 Integrated Corridor in Dallas, Texas, DART, et
al. U.S. DOT, FHW A-JPO-08-004, 30 April 2008.]
The San Diego ICM Pioneer Site project development team was organized out of the existing members of
the I-15 Managed Lanes project. The following paragraph provided by San Diego Association of
Governments (SANDAG) explains the San Diego ICM Project Team within the context of the I-15
Managed Lanes project.
Decision-making authority for matters of policy that affect the I-15 Managed Lanes
Corridor lies with SANDAG’s Board of Directors and is handled by delegation to the
SANDAG Transportation Committee. The Transportation Committee is the body through
which issues are vetted with public involvement and regional transportation issues are
resolved. Detailed issues relative to the I-15 Corridor and the ICM project would be
delegated by the Transportation Committee to SANDAG staff, with guidance provided by
a Technical Working Group established by the SANDAG Board of Directors. The
SANDAG Project Manager (Team Leader) would administer the ICM project with
oversight from the ITS Chief Executive Officer’s Working Group. The involvement of
other stakeholders such as local agencies (cities) and transit operators would be
established through the Technical Working Group. The Project Development Team
would be established through a Project Charter and would meet on a regular basis to
provide the team with guidance and direction, as well as receive and review and
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 25
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 1
comment on project deliverables. The Technical Working Group (TWG) serves as the
primary forum to address project issues, and will be composed of SANDAG staff,
consultants and key stakeholder representatives from the ICM team. When issues
cannot be addressed within the context of the Technical Working Group, the Project
Manager would elevate issues to the ITS CEO Working Group for resolution of issues or
conflicts.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 26
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 2
[Source: Research and Innovative Technologies Administration, ITS JPO.]
Establish Goals (Phase 2)
This phase includes the activities necessary for the stakeholders to gain an understanding of ICM and to
initiate the planning for an ICM project. These activities are described following the guide convention
described previously—manage for quality, resources, highlights, questions to answer, lessons learned,
and example.
Managing for Quality – Establishing Goals
One of the first things that needs to be accomplished when establishing goals for ICM is to choose a
stakeholder that will manage and lead the work to be performed. The following checklist includes some of
the more important activities that the Project Lead will be responsible for:
Schedule meetings to discuss activities, status, action items, and risks;
Ensure that guidance and training is made available to those stakeholders that are not familiar
with ICM; and
Ensure that all stakeholders understand and are comfortable with the project process.
Establishing Goals Resources
There are many resources available to assist with establishing goals for ICM. One excellent resource is
the Advancing Metropolitan Planning for Operations Desk Reference discussed in section 1.3.2. Another
resource that stakeholders should visit for information on ICM is the U.S. DOT ICM Web site:
http://www.its.dot.gov/icms/. At the ICM Web site, stakeholders can find a great deal of information on the
concept of ICM and its implementation. There is also an “ICM Knowledgebase” where people can search
and find publications on ICM, including presentations, newsletters, and fact sheets—plus AMS results
and systems engineering documents from the ICM Pioneer Sites. The Systems Engineering Guidebook
for ITS contains a good description on concept exploration in section 3.3.1, Needs Assessment, and
section 3.3.2, Concept Exploration and Benefits Analysis. In addition, stakeholders can use their own
standard processes for goal setting.
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 27
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 2
Establishing Goals Highlights
The activities shown in Figure 8 are described below in this section under the following sub-headings:
Explore the ICM Concept
Develop Goals, Measurable Objectives, and Data Collection Needs
Analyze System Problems and Identify System (User) Needs
Conduct Feasibility Assessment
Identify Development Support Resources
Figure 8 below provides a framework for establishing the goals of ICM. This framework identifies some of
the inputs and controls needed before beginning the process, activities that should be performed during
the process, and some of the outputs or products that need to be completed before moving to the next
phase of the project. Enablers for this process are identified as those human resources that will facilitate
completion of the activities.
Figure 8. Establishing Goals for ICM
[Source: Noblis for ITS JPO, Modeled after: Systems Engineering Guidebook for ITS, Section 3.3.1,
November 2009]
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 28
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 2
Explore the ICM Concept
ICM involves coordinating transportation management activities and processes among those agencies
within a corridor whose actions affect how effectively people and goods can move on the transportation
networks within that corridor. One of the first things to accomplish during this phase is the establishment
of an ICM concept exploration working group. This group works best if it includes a representative set of
relevant agency decisionmakers and has the resources needed to conduct a reasonable exploration of
ICM concepts for the corridor.
The concept exploration working group must select and define a candidate corridor within which agencies
can implement ICM. A candidate corridor can be of any size or type, but the U.S. DOT’s research to date
has focused on urban corridors in large metropolitan areas. To select and define a candidate ICM
corridor with specific geographic boundaries, the working group must select for the following factors:
A major transportation network (roadway) with heavy traffic that is congested during peak travel
periods must exist;
Alternate transportation networks – at a minimum, one or more roadway networks and one or
more transit networks, with periods of unused or underused capacity – must exist within the
corridor (to handle diversion from the main, congested network or networks);
Networks within the corridor must have (or must plan for implementing) real-time or near-real-time
data collection; and
Transportation network operators within the corridor must have a culture of interagency
cooperation and collaboration (Note: while this is not mandatory, having this collaborative culture
facilitates the establishment of the necessary inter-agency agreements that make ICM possible, if
they do not already exist).
The working group should propose the geographic boundaries of a corridor that encompasses all of the
above factors to the stakeholders considering ICM.
Once the working group has identified a candidate ICM corridor, it should identify the transportation
problems or issues that exist and consider how concepts within the ICM strategic areas might address
these problems and issues.
As Appendix A indicates, the four major strategic areas of ICM include:
Demand management – which addresses usage patterns for the corridor’s transportation
networks. Generally, travelers driving in to work from suburban or ex-urban locations to work
locations within the corridor and then making the return trip after work to their homes cause
congestion in urban corridors. Building more roads or widening existing roads is a congestionmitigation strategy that has rarely proven successful in the long term. While it may provide shortterm relief, ultimately growth along the travel corridor leads to the same or greater congestion
along those roads. While the overall approach to implementing ICM in a corridor might include
road construction, the working group should consider other ways of addressing demand. These
might include such ideas as high-occupancy vehicle (HOV) or high-occupancy toll (HOT) lanes,
incentives to encourage ride-sharing, closing off sections of the urban area to vehicles,
encouraging telework, or congestion pricing. Some of these approaches could become part of
the overall ICM strategy for the corridor.
Load balancing – which addresses how travelers use the networks in a corridor. The working
group can examine such ideas as mode shift (e.g., having drivers become transit riders), use of
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 29
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 2
reversible lanes during peak travel times, use of roadway shoulders as travel lanes to increase
capacity during peak travel times, ramp metering, and other similar ideas to balance the traffic
loads on corridor transportation networks. The working group can also consider options that add
short-term capacity to a network (e.g., adding additional train cars to a transit train during peak
demand periods) or valet parking at some facilities to move people through the facility faster.
(One can consider some of these possible approaches as being either demand management or
load balancing; the category is not important, but the potential positive impact of the approach is.
There are also longer term load-balancing options that can involve some capital projects, such as
building roads that allow travelers a shorter route to some destinations or providing light-rail
transit options for certain heavily congested corridors. )
Event response – which deals with how the combined transportation network managers respond
to both planned and unplanned events (incidents) that affect the capacity of or the demand on the
corridor’s transportation networks. The most successful approaches, as indicated by the actual
experiences of the Pioneer Sites, deal with establishing pre-coordinated response plans that
represent what the corridor’s stakeholders consider the most effective manner of dealing with
likely events (planned or unplanned). Usually, the likelihood of an event is determined from the
historical record of events within the corridor and the experience of the corridor’s transportation
managers.
Capital improvement – which deals with upgrades to corridor facilities. This could include
roadway, transit, and parking construction projects, but more likely will focus on the increased use
of technology within the corridor to facilitate the coordinated management of the corridor’s
transportation networks. One type of capital improvement the concept exploration working group
should consider is the development of an ICMS, a system to support ICM decisions.
U.S. DOT research in ICM and other congestion management initiatives has identified a number of
control strategies or tactics that agencies can apply in strategic areas covered by ICM. The Pioneer AMS
Sites modeled a representative sample of these. The control strategies modeled included:
Earlier dissemination and information sharing among agencies;
Parking information at park and ride lots;
Freeway traveler information (pre-trip and en-route);
Arterial traveler information (pre-trip and en-route);
Transit traveler information (pre-trip and en-route);
Signal retiming on arterials or frontage roads during incidents;
Ramp meter retiming during incidents;
Coordinated signal and ramp meter operation;
System wide coordinated ramp metering;
HOT lane (congestion pricing);
HOV lane (changing minimum number of occupants);
Opening HOV/HOT lanes during incidents;
Dynamic transit re-routing;
Transit capacity expansion during special events; and
U.S. Department of Transportation
Office of the Assistant Secretary for Research and Technology
Intelligent Transportation Systems Joint Program Office
Integrated Corridor Management: Implementation Guide and Lessons Learned | 30
Chapter 3. ICM Implementation Guidance and Lessons Learned
Phase 2
Arterial signal priority for transit.
During concept exploration, it is premature for the working group to decide which control strategies
agencies might use in the defined corridor. However, what the working group can determine at this point
is what data is needed to assess the potential impact of potential control strategies within the corridor.
The working group can also assess whether the data needed is actually available or can be obtained with
a reasonable expenditure of resources. The ICM AMS Guide[22] provides some guidance on what data
is required for different AMS activities. The working group may also choose to initiate discussion on how
to characterize overall corridor performance rather than individual network performance and potential
implications for data collection. Goals, objectives, and performance measures are discussed in more
detail in Section 2.3.2, below.
If the region cannot afford to implement the type of AMS effort performed at the Pioneer AMS Sites, it
should consider a more limited form of AMS. Some AMS work is needed to assess the potential impact
of control strategies that the working group is considering for the corridor. Without any AMS,
stakeholders could decide to implement control strategies that have limited value and benefit within the
corridor.
In this phase, it is also helpful to review the regional ITS architecture to determine what ITS projects the
region plans to initiate (and when) and which systems the region has scheduled for upgrades.
Additionally, many regional ITS architectures include current operating agreements among agencies and
identify ITS standards used in the region. These agreements and standards help identify constraints on a
proposed ICMS.
The most common documents that come out of the concept exploration activity are the description of the
proposed corridor and its boundary, a description of data needs for AMS, and a list of potential ICM
control strategies that the working group will explore further while performing the corridor needs analysis.
Note that one does not perform concept exploration and needs analysis in a sequential manner. There is
considerable back and forth between the two activities as the working group considers how it can best
resolve transportation problems and issues within the corridor.
Develop Goals, Measurable Objectives, and Data Collection Needs
Having explored the ICM concept, identified the transportation problems and issues within the corridor,
and examined possible control strategies for addressing those problems and issues, the next step for the
working group is to define an initial set of goals that it wo...
Purchase answer to see full
attachment