- A project manager at Global Design Corporation has collected the following data on the size of software programs and the length of programming time. The company is bidding on a new system that is estimated to consist of 300,000 lines of code. Use the data to find the correlation function of coding time to the program size and estimate the number of days it would take to code the system.
Module | Size in 1000 lines of code (KLOC) | Number of days to code |
1 | 160 | 70 |
2 | 158 | 66 |
3 | 150 | 70 |
4 | 135 | 59 |
5 | 178 | 72 |
6 | 170 | 63 |
7 | 158 | 69 |
8 | 138 | 65 |
9 | 200 | 72 |
10 | 195 | 68 |
11 | 189 | 65 |
12 | 173 | 68 |
13 | 159 | 70 |
14 | 163 | 55 |
15 | 150 | 66 |
16 | 140 | 65 |
17 | 206 | 73 |
18 | 144 | 64 |
19 | 157 | 70 |
20 | 183 | 74 |
21 | 195 | 75 |
22 | 190 | 77 |
23 | 182 | 69 |
24 | 152 | 65 |
25 | 174 | 69 |
Unformatted Attachment Preview
Purchase answer to see full attachment

Explanation & Answer

Add me 40 minutes
Attached. Please let me know if you have any questions or need revisions.
4)
A project manager at Global Design Corporation has collected the following data on the
size of software programs and the length of programming time. The company is bidding on
a new system that is estimated to consist of 300,000 lines of code. Use the data to find the
correlation function of coding time to the program size and estimate the number of days it
would take to code the system.
Size in 1000
lines of code
(KLOC)
Mod...