STORY | ASK MAGA ZINE | 47
Title
By
Photo Credit: Rick Berk
Intro
The Leonard P. Zakim Bunker Hill Bridge, part of the Big Dig
project in Boston, is the widest cable-stayed bridge in the world.
Learning from a Mega Project
By Virginia Greiman
48 | ASK MAGA ZINE
Boston’s Central Artery/Tunnel Project, commonly known as
the Big Dig, was the largest, most complex, and most technically
challenging highway project in American history. Larger than the
Panama Canal, the Hoover Dam, and the Alaska Pipeline projects,
it was built through the heart of one of the nation’s oldest cities. Its
list of engineering firsts include the deepest underwater connection
and the largest slurry-wall application in North America,
unprecedented ground freezing, extensive deep-soil mixing
programs to stabilize Boston’s soils, the world’s widest cable-stayed
bridge, and the largest tunnel-ventilation system in the world.
Interstate 93 tunnel in Boston, part of the Big Dig.
The Big Dig is also famous for cost increases. Its initial estimated
cost was $2.56 billion. Estimates increased to $7.74 billion in
1992, to $10.4 billion in 1994, and, finally, $14.8 billion in
2007—more than five times the original estimate. The reported
reasons for the cost escalation included inflation, the failure
to assess unknown subsurface conditions, environmental and
mitigation costs, and expanded scope. Mitigation alone required
1,500 unanticipated, separate agreements.
The Big Dig was led by Bechtel/Parsons Brinckerhoff, one of
the largest and most experienced teams in infrastructure design
and construction. Extensive environmental feasibility studies,
risk assessments, and other documentation were completed
prior to the project’s start. Nonetheless, costs increased across
all contracts throughout the project’s life cycle despite enormous
efforts to transfer, mitigate, or avoid risk and contain costs.
In other words, things can go dramatically wrong despite
the best efforts. Few infrastructure projects have used as
many innovative tools and programs to control project risk
and cost as the Big Dig. These included an owner-controlled
insurance program that saved $500 million by providing group
coverage for contractors, subcontractors, and designers and an
unprecedented safety program; a cost-containment program that
saved $1.2 billion; an integrated audit program that identified
and mitigated existing and potential overruns and delays; a labor
agreement that established a no-strike, no-slowdown guarantee
for the life of the project; a quality-assurance program that was
recognized by the Federal Highway Administration as one of
five noteworthy accomplishments; and a dispute-resolution
process that avoided extensive litigation costs.
Causes of Cost Escalation
To address major problems in mega-project management,
Boston University, through its Mega-Project Research Program,
has begun researching mega projects to help understand current
practices, develop new practices and frameworks, and learn how
to prevent or reduce risks before they cause serious problems
or even project failure. Our research on the Big Dig has
shown us that no single catastrophic event or small number of
contracts caused costs to escalate. Multiple decisions by project
management across all contracts contributed to the increases.
The critical cause was a lack of experience and knowledge about
dealing with the complexity and uncertainty that giant projects
bring with them.
Using preliminary Big Dig data, we studied the impact of
inflation, often claimed to be a major cost-escalation factor. The
Big Dig reported that about half the cost growth was caused by
inflation, but official inflation rates over the life of the project
do not support the claim. Some of the increase can be attributed
to an unrealistic initial cost estimate. Research shows that
mega-project costs are consistently underestimated, a practice
often attributed to the desire of project advocates to have their
projects approved.
Design and Construction Risks
The most difficult problems on the Big Dig involved the means
and methods used to address issues raised in the project’s
design and drawings, and the failure to properly account for
subsurface conditions during the construction process. Project
documents show that the challenges of subsurface conditions
were substantially underestimated. The sheer size of this project
and the fact that construction occurred in a busy city resulted in
having to deal with many unanticipated conditions and a large
volume of claims and changes.
The surprises included uncharted utilities, archeological
discoveries, ground-water conditions, environmental problems,
weak soil, and hazardous materials. The project faced safety and
health issues, frequent design changes, and changes in schedules
and milestones. The unexpected discovery of 150-year-old
revolutionary-era sites and Native American artifacts was one
surprise complication and source of delays, requiring approvals
from yet another diverse set of stakeholders, including historical
and preservation organizations and Native American groups.
Photo Credit: Rene Schwietzke
ASK MAGA ZINE | 49
50 | ASK MAGA ZINE
True integration calls for a design-build model from the beginning of
the project. … Under a design-build model, designer and contractor are
retained at the same time, developing a strong working relationship from
the start through shared goals and methodology.
Underground Utility Protection
To protect against losses caused by the disruption and failure
of underground utilities, a Big Dig utility program relocated
29 miles of gas, electric, telephone, sewer, water, and other utility
lines maintained by thirty-one separate companies in 1996. Some
of this infrastructure was more than 150 years old; a complete
lack of knowledge on the age, condition, and location of most
of the utilities required submission of “as-built” drawings by all
project contractors—drawings of existing conditions rather than
planned or proposed construction. The project had to deal with
utilities that were shown on as-built drawings but never installed,
and damage and flooding caused by underground sewer pipes
not identified on the drawings. With large buildings located
within feet of construction, the risk was high that damage to
the infrastructure would shut down the operations of Boston’s
major financial centers. One wrong move could have shut down
the Federal Reserve Building and affected the country’s financial
system for days, months, or even years.
Photo Credit: adm
The Big Dig during construction.
During the span of the project, 5,000 miles of fiber-optic
cable and 200,000 miles of copper cable were installed. This
required more than 80,000 hours of construction and 5,000
construction workers operating 24/7. Between 1996 and 2000,
the rate of utility damage decreased 86 percent, with cost savings
approximated at $50 million. Despite many problems and risks,
the utility program improved safety, quality, schedule, budget,
insurance costs, and public relations.
Delayed Integrated Project Management
The Big Dig relied heavily on a collaborative, integrated projectmanagement team that involved all participants in decision
making. Unfortunately, the Big Dig’s project organization
was not fully integrated until July 1, 1998, when design of
the project was 99 percent complete and construction was
45.9 percent complete. If there is a single cause for the massive cost
escalation on the Big Dig, it probably involves the management
of the project’s complex integration.
Integration problems were exacerbated by the project’s
organizational structure, which separated design from
construction through its traditional design-bid-build model and
required managing thousands of stakeholders. True integration
calls for a design-build model from the beginning of the project.
Because contracts were negotiated separately with designers and
contractors, there was little room for collaboration among the
project’s most important stakeholders. Under a design-build
model, designer and contractor are retained at the same time,
developing a strong working relationship from the start through
shared goals and methodology.
Problems in integration resulted in part from the sheer
number of internal and external stakeholders, their interactions,
and the ever-changing dynamics of managing the relationships.
Each of the Big Dig’s 110 major contracts involved intensely
complicated technical, legal, and economic issues and numerous
processes and procedures as well as a complex regulatory scheme.
The Big Dig may have suffered not from too few processes
and procedures, but too many complex processes that made it
difficult to monitor and enforce in a uniform manner.
In the early phases of the project, there was little
communication between and among many of the internal and
external stakeholders, other than an impressive outreach to the
local community, particularly residents living close to several of the
project’s major worksites. Community and social costs were vastly
underestimated on the Big Dig. No one ever envisioned the full
cost of dealing with the media, community interests, numerous
regulatory agencies, auditors, and neighborhood stakeholders.
The government served in a dual role as regulator and owner
of the Big Dig. The project organizational structure required
that some managers report directly to the governmental
owner, while other managers reported to the project’s design
and construction program manager. A truly integrated project
should centralize decision making and accountability for all core
functions of the project.
The Value of Partnering
The concept of “partnering” was first used by DuPont Engineering
on a large-scale construction project in the mid-1980s, and the
U.S. Army Corps of Engineers was the first public agency to use
partnering in its construction projects. Partnering is now widely
used by numerous government and construction entities around
the world. It involves an agreement to share project risks and
to establish and promote partnership relationships. Partnering
is a team problem-solving approach intended to eliminate the
adversarial-relationship problems between owner and contractor
by focusing on mutual interests with the help of a neutral
facilitator. On the Big Dig, partnerships were used to improve
schedule adherence, quality, safety, and project performance, as
well as to reduce costs, claims, disputes, and litigation.
Partnering at the Big Dig was initially implemented in
1992, primarily on construction contracts, but its success in
construction led to its use elsewhere. Almost one hundred
partnerships existed on the Big Dig, based on contract values
Signs from the Big Dig construction area.
ranging from $4 million to half a billion dollars. Though
partnering is not always contractually required, on the Big Dig
it was included in all construction contracts with a duration of
at least one year and a value of $1 million or more.
Partnering sessions were held on a regular basis to discuss
project needs, to resolve problems, and to improve controls.
Partnering activities included leadership training, seminars, and
executive meetings. Federal and state government officials and
the contractors’ project management teams met regularly with an
independent expert to assist in developing a single, integrated team.
Sharing knowledge, risk, and liability, partnering reduced the cost
of contractor claims, increased the number of value-engineering
savings proposals, and helped keep projects on schedule.
Here’s one example. Big Dig leaks, which delayed
construction, often had several causes and flow paths. Assessing
responsibility for leaks in the Fort Point Channel tunnel area,
government lawyers, aided by an independent expert engineer
with substantial marine geotechnical experience, spent more
Photo Credit: Stephen Gore
ASK MAGA ZINE | 51
52 | ASK MAGA ZINE
Partnering requires focus on
determining the root cause of
problems, not assessing blame.
than two thousand hours trying to establish the exact cause
of the leak, but could not do so with certainty. The leak was
attributable to unexpected site conditions and to contractor
performance issues compounded by pressure to complete the
job quickly. To avoid costly litigation, the Metropolitan Transit
Authority decided to mediate the issue before two sitting
judges on the Armed Services Contract Board of Appeals.
The mediation process took three months and succeeded in
convincing the parties that liability should be shared between
the owner and the contractor.
Given the scope and complexity of the Big Dig, experts have
concluded that the project would have been simply unmanageable
without partnering. Though the benefits of partnering on the
Big Dig have not been quantified, there is sufficient data to
support the conclusion that partnering contributed significantly
to the reduction of claims and the avoidance of expensive and
time-consuming litigation.
These are the most important lessons about partnering
learned from the Big Dig experience:
• Partnering requires focus on determining the root cause of
problems, not assessing blame.
• Subcontractors should be included in the partnering
sessions; they can be crucial to the success of the project
and help balance the teams.
• R isk should be shared jointly among partners whenever
possible to encourage innovation and continuous
improvement, particularly where the technology is new,
the risks are unknown, and the stakes are high. On the Big
Dig, risks were shared among the owner and contractors
to facilitate tunnel jacking, deep underwater connections,
and technology interfaces between contractors.
• Teaching problem-solving skills is a major benefit of
partnering.
• Partnering should never replace independent and rigorous
oversight of the project.
Learning from the Big Dig
Mega projects will always struggle with unforeseen events,
massive regulatory requirements, technical complexities,
community concerns, and a challenging political environment.
What we have learned from the Big Dig can help future large
projects. Of the many lessons this huge undertaking has
provided, these are the major ones:
• Project integration is critical to success.
• Goals and incentives must be mutual and built into
contracts throughout the project life cycle to ensure
quality, safety, financial soundness, and a commitment to
meeting budget and schedule.
• Continuous improvement and rigorous oversight are both
essential.
• Doing things as they have always been done does not work
for complex projects that require constant innovation and
a culture of collaboration. ●
Virginia Greiman is an assistant professor at Boston
University and former deputy general counsel and risk manager
of Boston’s Central Artery/Tunnel Project.