Consider the table below, Network Diagram Data for a Small Project. All duration

User Generated

ffnzfba

Business Finance

Description

 Consider the table below, Network Diagram Data for a Small Project. All duration estimates or estimated times are in days; and the network proceeds from Node 1 to Node 9.

  1. Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter. MS Powerpoint or Visio are good tools for this task.
  2. Identify all of the parts on the network diagram and note how long they are, using Figure 6-8 in your text as a guide for how to represent each path.
  3. What is the critical path for this project and how long is it?
  4. When is the earliest possible time that this project can be completed?
  5. Enter the information into MS Project.

Activity

Initial

Node

First

Node

Estimated

Duration

A

1

2

2

B

2

3

2

C

2

4

3

D

2

5

4

E

3

6

2

F

4

6

3

G

5

7

6

H

6

8

2

I

6

7

5

J

7

8

1

K

8

9

2

Example AOA diagram and Gantt Chart.


AOA Diagram.jpg 


Gantt Chart.jpg 

Unformatted Attachment Preview

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

This question has not been answered.

Create a free account to get help with this and any other question!

Related Tags