WHAT IS THE ERALY START DATE - HOW TO CALCULATE IT

Jan 21st, 2015

Early start date of an activity is the maximum of early finish time of all its predecessor activities.

For example 1-2, 1-3,2-3,3-4

And if durations are respectively 4, 5,3, 3

then early start of 3-4 is the maximum of 5 and 4+3 or 7


Jan 21st, 2015