Material Requirements Planning Part 4

Question Description

I need an explanation for this Business question to help me study.

Utilizing the Step-by-Step MRP Calculation Process, students will solve the following MRP problem given: Product A is an end item and is made from two units of B and four of C. B is made of three units of D and two of E. Product C is made of two units of F and two of E. Product A has a lead-time of one week. Products B, C and E have lead-times of two weeks. Products D and F have a lead-time of three weeks.

a. Show the bill of material (product structure tree). b. If 100 units of A are required in week 10, develop the MRP planning schedule, specifying when items are to be ordered and received. There are currently no units of inventory on hand.

Student has agreed that all tutoring, explanations, and answers provided by the tutor will be used to help in the learning process and in accordance with Studypool's honor code & terms of service.

Final Answer

here is attached file of your assignment which is in excel format

B (2)
D (3)

E (2)

A (1)

B (2)

C (4)
E (2)

F (2)

E (2)

MRP
Indented Bill of Materials
Item name

Level

A
B
D
E
C
E
F

0
1
2
2
1
2
2

Distinct items

1
2
3
2
4
2
2

A
B
D
E
C
E
F

6

A
Week 0
Gross requirements
Scheduled receipts
On Hand Inventory
NET POQ Req
Planned receipts
Planned orders

B
Week 0
Gross requirements
Scheduled receipts
On Hand Inventory
NET POQ Req
Planned receipts
Planned orders

C
Week 0
Gross requirements
...

Harsh V (108)
University of Virginia

Anonymous
I was on a very tight deadline but thanks to Studypool I was able to deliver my assignment on time.

Anonymous
The tutor was pretty knowledgeable, efficient and polite. Great service!

Anonymous
Heard about Studypool for a while and finally tried it. Glad I did caus this was really helpful.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4