A) Two manufacturing facilities are integrating their inventory management systems as a result of operations consolidation. Preliminary analysis and interviews with all parties involved resulted in the following project information. All times are in weeks.

Your task is to identify the following:

  1. Critical path
  2. Total project completion time
ACTIVITYIMMEDIATE PREDECESSORSTIME (IN WEEKS)
A-3
BA1
CA2
DB,C3
EC5
FC3
GE7
HE,F5
ID,G,H8

B) Zentaur, Inc. started creating a new digital imaging system. They found out that their has a similar product under study, but has not yet been able to begin production. Because of the competitor’s action, top managers have asked for a speedup of R&D activities so that Zentaur can produce and market their system at the soonest possible date. The predecessor information and activity time estimates in months are shown below.

Your task:

  1. Identify the critical path
  2. Compute activity slack time
  3. Identify project completion time
ActivityImmediate PredecessorsOptimistic TimeMost Probable TimePessimistic Time
A--11.55
BA345
CA123
DB,C3.556.5
EB4512
FC,D,E6.57.511.5
GE59

13

Please identify your answers clearly.

Examples:

A.1) Critical Path is: ----

A.2) Total project completion time is: ----

For Item B, your answers should be labeled:

B.1) Critical Path:

B.2) Slack time for each activity: (you should have the slack times for all activities in this section)

B.3) Project completion time

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Hello,

Project Management
Question One.
Project implementation by the two manufacturing companies
Question Two
Project on new digital system by Zentaur Inc.


Running head: PROJECT MANAGEMENT

Project Management
Student’s Name
Institutional Affiliation

1

PROJECT MANAGEMENT

2
Project Management

Question One.
Action on Node Diagram
The action on node diagram below depicts the implementation project on an inventory
management systems as part of co...


Anonymous
Excellent! Definitely coming back for more study materials.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4

Similar Content

Related Tags