Decision Modeling and Analysis

Business & Finance
Tutor: None Selected Time limit: 1 Day

The “forward pass” determines the earliest start and finish times for activities in a project. The “backward pass” establishes latest start and finish times

True or False

Feb 15th, 2015

the answer is True.The “forward pass” determines the earliest start and finish times for activities in a project. The “backward pass” establishes latest start and finish times

Feb 15th, 2015

Studypool's Notebank makes it easy to buy and sell old notes, study guides, reviews, etc.
Click to visit
The Notebank
...
Feb 15th, 2015
...
Feb 15th, 2015
Dec 3rd, 2016
check_circle
Mark as Final Answer
check_circle
Unmark as Final Answer
check_circle
Final Answer

Secure Information

Content will be erased after question is completed.

check_circle
Final Answer