Decision Modeling and Analysis

label Business & Finance
account_circle Unassigned
schedule 1 Day
account_balance_wallet $5

The “forward pass” determines the earliest start and finish times for activities in a project. The “backward pass” establishes latest start and finish times

True or False

Feb 15th, 2015

the answer is True.The “forward pass” determines the earliest start and finish times for activities in a project. The “backward pass” establishes latest start and finish times