​For your project, you are to do the following as discussed in class:

User Generated

zrrzb

Engineering

CONSTRUCTION ECONOMICS

Morgan State University

Description

For your project, you are to do the following as discussed in class:

1. Discuss and Identify the type of Delivery Method you will use for your project and why?

2. Describe the Project Management Organization Method for your project

3. Identify your project team members and their responsibilities

4. Identify the Contract Documents for your project as well as the contract pricing methods you are using for your project

5. Identify the types of insurance and bonds to be provided for your project

6. Provide the Work Breakdown Structure for your project

7. Provide a Cost Estimate of Your Project as necessary

8. Describe what Partnering and Team Building Program for your project and how this partnering/team group is to be accomplished.

9. How do yo intend to work with subcontractors and your subcontractor management program for your project.

10. Describe your Material Management Program for your project.

11. Provide in your report the Document and Record Keeing Program for your project.

Submit your full report bound on or before the last day of class on August 11, 2017 the new date for final examination.

PROJECTS SELECTIONS:

10. Construction of a University Library

This is an important assignment for you. You are to make a selection of a project topic and do your research and commence on your project assignment responsibilities during class time on Tuesday, August 1, 2017 and Thursday, August 3, 2017.

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

Surname 1
Prepared by (Your Name)
Submitted To (Professor’s Name)
Course Number
Date
PROJECTS SELECTIONS
Construction of the University Library
Step one
I will use the Design-Build (DB), which comprises one design builder (entity) and one
contract with the owner to provide both the engineering/architectural design services as well as
construction. In this method, the design builder is tasked with designing as well as constructing
the project so as to meet the standards of performance set forth by the owner in the contract. In
relation to any prescriptive specifications or designs, the design build is charged with the duty of
discovering inconsistency between the performance standards and prescriptive requirements
while the owner is responsible for the expense to reconcile the inconsistent standards.
Step two

Critical chain/path: The method mainly focuses on solving resource problems. Every
project usually has a particular set of key elements known as a critical chain or critical path
method devotes enough resources to this critical path while devoting adequate resources to other
resources when required. The setup best for resource heavy teams or those with adequate
flexibility in their team members’ individual skill sets.

Step Three

Surname 2
Project Man...