Course Project: Part I
Consider the following scenario: You are the safety manager for a team that is working to complete a 10-story addition to a hospital. The framework of the addition will be steel and concrete. The floors will be formed and poured with reinforced concrete on metal decking. The outside will require brick and glass window installation and installation of a standing seam metal roof. The interior will consist of metal stud framing with drywall and tile floors. The building will be centrally cooled and heated with a heating, ventilation, and air condition (HVAC) mechanical system, and it will need a new electrical supply source.
The electrical rooms will be located in the southeast corner of each floor near the stairwell. Plumbing and fire suppression systems must be installed. There will be a bank of elevators in the main entrance/northside center and a service elevator in the back/southside center. There is suspected asbestos in the flooring and piping where the new addition connects to the existing structure. A new entrance must be constructed off the side street/northside, with a driveway, sidewalks, drainage, lighting, and landscaping installed.
Unformatted Attachment Preview
Purchase answer to see full attachment
Explanation & Answer
View attached explanation and answer. Let me know if you have any questions.
SITE-SPECIFIC SAFETY PROGRAM (SSSP)
Project Name and Number
General
Client: Victoria General Hospital
Date Prepared: 14/05/2022
Project: 10 Story Building
Site Address: 11 Dunsmuir Street
Project Description
Project Start/End Dates
Project Location
General Scope of Work,
Project Description,
Identification of Stakeholders
Logical Sequence of Work
01/06/2022 to 21/09/2023
British Columbia
The project involves construction of a 10 story hospital
structure addition with heating, ventilation and air conditioning
(HVAC), standing seam metal roof, electrical, plumbing,
mechanical system and telecommunications system. Elevator
entrances on north and south side. The site amenities are
inclusive of car parking, ambulance entrance, rooms for
physical therapy and outdoor area.
•
•
•
•
•
Site mobilization inclusive of setting the office trailers
and beginning of project
Construction beginning with parking, roadway, loop
road and new diversion channel
Building framework construction with steel and
concrete, installation of pipes and utilities
Interior works including HVAC system, electrical,
plumbing, fire suppression and building facilities.
Finishing works including paint and tilework.
Schedule
Proposed Start Date:
Duration:
Working Hours:
01/06/2022
15 months
8am to 5pm
Overtime Hours:
5pm to 8pm
Access to Work Area
Description of parking, entrances, and other work areas. Include any restrictions, areas prohibited, etc.
Drive through parking for stopping/parking a vehicle
Back in parking provided as secondary parking
Main entrance/exit to site through north gate
Backward (emergency) entrance/exit provided at south gate
Restriction to asbestos area connecting to old building
Project Support Features, Site Control, and Logistics
Check all of the following faci...