problem solving with percentage

label Mathematics
account_circle Unassigned
schedule 1 Day
account_balance_wallet $5

A library expansion began in 2002 was expected to cost 101 million by 2006 the estimated cost was 38 million over budget. By what percent did the actual cost exceed the initial estimate

Mar 31st, 2015

expected cost=101 million

estimated cost over budget=38 million

% excess=excess divide by original expected times 100

38000000/101000000*100=37.62%

Mar 31st, 2015