Renmin University of China Advisory Letter Construction Law Paper

User Generated

Gg2021

Law

Renmin University of China

Description

Unformatted Attachment Preview

Scenario: Seokyo JSC (“the Contractor”), a company incorporated under the laws of the Republic of Korea, entered into a contract (“the Construction Contract”) with Humberstone Salitrera SRL , (“the Employer”), a company incorporated under the laws of the Republic of Chile on 31 March 2013 for the “…design and construction of a 2 MTPA granular potassium nitrate fertiliser plant …” (“the Works”) at the former Humberstone and Santa Laura Saltpeter Works (“the Process Plant”) in the Atacama desert, Chile. The Accepted Contract Amount was USD $ 175,000,000.00 and the Time for Completion was 31 March 2016. The Construction Contract was based upon an amended FIDIC Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant and for Building and Engineering Works, designed by the Contractor 2017 form of contract1. The Engineer named in the Contract Data was “Senora Emilia Shackleton, Room 51S72W PO Box Puerto Natales 6160000, Magallanes y la Antártica Chilena, Chile” who was also a majority shareholder in Humberstone Salitrera SRL. 1 Although not possible given the chronology, in order to make the assignment as industry relevant as possible and to reflect the latest versions of standard forms of contract please take the above statement as factually correct Brief details of the Construction Contract and other agreements entered into by the parties are set out below: a. An Engineering and Project Management Services contract (“Project Management Contract”) dated 25 December 2012 between the Employer and PMC Inc (“the Project Manager”), an engineering and project management company for the provision of Front End Engineering and Design (“FEED”), Project Management and Project Control Services (“the Services) in respect of the Process Plant that was executed under hand. b. The Construction Contract was similarly executed under hand and the Commencement Date referred to in clause 8.1 was 1 June 2013. c. The Contractor provided an “On-Demand” Performance Guarantee (“Performance Guarantee”) in the Employer’s favour relating to the Construction Contract issued by the Bank of Argentina in the sum of USD $ 10,000,000, which, according to its terms, “…expires upon the issue of a Taking Over Certificate…” 1. Under clause 1 the Project Manager was required to provide a Front End Engineering and Design (“FEED”) for the Process Plant and agreed “…to use the skill, care, judgement and supervision necessary to ensure that the Works are of good quality and meet the Performance Criteria set out in the Construction Contract that one would ordinarily expect an experienced and competent professional engineering organisation to provide, up to the point of commercial operation of the Works…” 2. Under clause 2 the Project Manager was required to “…address all Contractor requests for further information relating to inadequacies or ambiguities in the FEED…” 3. Under clause 3 the Project Manager was to provide “…advice and assistance to the Employer on commercial issues, contract administration and general claims support up to the point of commercial operation…” 4. Under clause 4 the Project Manager was to “…provide evidence of Professional Indemnity insurance to a limit of indemnity of USD $ 10,000,000 each and every claim…” 5. Delete paragraph 1 of clause 4.1 of the standard FIDIC Conditions. Insert: “…When completed the Works shall perform as per the requirements of the Construction Contract so as to ensure a service life of 25 years without planned or unplanned replacement…” 6. Clause 4.2 of the FIDIC Conditions has been deleted in its entirety. 7. new clause has been inserted into the Construction Contract at clause 22 which states: “…The Employer and the Contractor agree that the Contracts (Rights of Third Parties) Act 1999 shall not apply to this agreement. Therefore any person who is not a party to this agreement cannot enforce any term of it in their own right…” 8. new clause has been inserted into the Construction Contract at clause 23 which states: “…This agreement and any dispute or claim arising out of or in connection with it or its subject matter or formation (including non-contractual disputes or claims) is governed by and will be construed in accordance with the laws of England and Wales…” 9. new clause has been inserted into the Construction Contract at clause 24 which states: “…Each party hereby irrevocably submits to the exclusive jurisdiction of the courts of England and Wales to settle any dispute or claim that arises out of or in connection with this agreement its subject matter or formation (including non-contractual disputes or claims)…” 10. Under clause 1 of the Performance Guarantee the Bank of Argentina undertook to pay the Employer: "... on receipt of your first demand on us in writing stating that the Contractor has not performed its obligations in conformity with the terms of the Construction Contract…" 11. Under clause 2 of the Performance Guarantee it states “…this guarantee expires upon the issue of a Taking-Over Certificate…” Relevant provisions from each of these agreements are set out below. The Project Management Contract: The Project Management Contract included the following relevant provisions: The Construction Contract The Construction Contract contained certain insertions and / or amendments as agreed between the parties as set out below. Save in respect of the above amendments please refer to the FIDIC Conditions of Contract for Plant and Design-Build for Electrical and Mechanical Plant and for Building and Engineering Works, designed by the Contractor 2017 form of contract for its full terms and their true meaning and effect. The “On Demand” Performance Guarantee: Extracts from the terms of the Performance Guarantee between the parties are set out below. Chronology Performance Of The Works Between June 2013 and June 2016 the Contractor carried out the Works. Throughout the course of the Works the Contractor repeatedly complained of the Project Manager’s lack of response to a number of requests for additional information relating to inadequacies and ambiguities in the FEED for which the Employer was responsible and bore the risk. At no time however did the Contractor notify the Engineer named under the Contract of any delay and additional cost. The Works were put into commercial operation on 31 August 2016 by the Employer on the advice of the Project Manager. Subsequent Events: Following issues with output of the Works and a drop in market prices for fertiliser, the Performance Tests were never successfully completed for the Works, the Taking Over Certificate was never issued and the Contractor was never paid its final Application For Payment. Despite several requests by the Contractor, the Employer has never returned the Performance Guarantee to the Contractor. The Works, whilst having a number of performance issues, have remained in commercial operation albeit at a much reduced output. Following the recent upsurge in the market price of fertiliser, the Employer contacted the Contractor on 20 May 2022 seeking its assistance in optimising the performance of the Works. The Contractor has refused, stating that it requires payment of its final Application For Payment plus a return of the Performance Guarantee prior to providing any further support to the Employer. Defective Works: The Employer writes to the Contractor on 6 July 2022 stating: “…we hereby put you on notice of a claim for damages in the sum of USD $ 15,000,000 relating to the Contractor’s breaches of the Construction Contract and the substantial liabilities it has to the Employer in respect of latent defects which have now manifested themselves in terms of performance of the Works…” Contractor’s Response: The Contractor replies to the above letter from the Employer on 13 July 2022 copying in the Project Manager and the Engineer named under the Contract stating: “…we are astonished to receive your letter dated 6 July 2022. At no time have we ever been advised that there are any defects in respect of the Works. Whilst we accept that the Works were never fully optimised, this was due to the failure of your Project Manager to provide clarifications relating to the FEED for the Process Plant. Furthermore, we have never received final payment for the Works and the Engineer has failed to issue a Taking Over Certificate despite the Works having been in commercial operation for a number of years. Whilst we are happy to assist you in optimising the Works, we firstly require that you pay our final instalment and return the Performance Guarantee prior to any discussions taking place…” Task Description Please Note: A. It is possible that you may believe as a result of your own personal expertise and knowledge that the events, as described above, would not have occurred as represented and / or the contractual arrangements / terms of various documents were inappropriate. However, such issues are not relevant to the task in hand, which is to interpret the legal implications of the facts as set out in the brief. You are being asked to adopt the role of a legal advisor (based on limited information) and not that of a technical expert. B. It may be that the same issues arise in more than one of the task elements. If so, you need only deal definitively with the issue (e.g. by giving full case law/statutory references and argument etc.) the first time that it occurs. If it arises again, you can then deal very briefly with it. C. The applicable law in relation to all of the agreements is that of England & Wales. D. You should assume you are considering the matter as of 26 August 2022. Tasks 1. Adopting the role of legal advisor to the Employer, write a detailed letter of advice to your client in which you particularise, so far as possible from the information with which you have been provided, the claims which the Employer may be able to pursue against the Contractor and the Project Manager. When doing so, it is important to identify the legal / factual nature and the origin of any such claims. Do not seek to anticipate any defences that the Contractor may raise. Your letter of advice must set out in detail the legal arguments that the Employer could pursue (on current information) in respect of the Contractor and the Project Manager and any actions your client may want to take. Include discussion of whether, and if so how, your client may be able to seek redress from others including the possibility of funding from insurers. Support your answer by reference to properly cited legal authority. [50%] 2. Adopting the role of legal advisor to the Contractor, write a detailed letter of advice to your client setting out in detail the defences available to your client (on current information) in relation to the claims against the Contractor identified in Task 1. When doing so, it is important to identify the legal / factual nature and the origin of any such defences. Your letter of advice must set out in detail the legal arguments that your client could adopt and any actions your client may want to take. Include discussion of whether, and if so how, your client may be able to seek redress from others. Support your answer by reference to properly cited legal authority. [50%]
Purchase answer to see full attachment
Explanation & Answer:
4000 Words
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

View attached explanation and answer. Let me know if you have any questions.

1

Advisory Letter to Employer on FIDIC Conditions of Contract 2017

Student’s name
Institution affiliation
Professor’s name
Course code
Date done

2

TASK 1
Introduction
FIDIC conditions of contract for plant and design building for Electrical and Mechanical
plants and Engineering works designed by the contractor 2017 form of contract is considered to
being international jurisdiction set of laws to govern construction contracts. In England, FIDIC
conditions are widely used in partnership with the country's laws to dictate construction contract
agreements. FIDIC conditions are internationally preferred to other contract governing bodies as
it allows supplementation of the already set rules with specifically agreed contract provisions. For
instance, an agreement between Seokyo JSC (contractor) and Humberstone Salitrera SRL (the
employer) involved additional clauses 22 and 23 in the FIDIC conditions of the contract. The
above-mentioned contractual agreement was based on the guidelines of FIDIC conditions 2017.
However, the contractual work is presented to have failed due to a breach of the agreement by the
contractor and the project manager. The violations noted concerning FIDIC conditions of contract
include failure of the contractor and project manager to fulfil their obligations, violation of the
agreement to provide 25 years of lifespan work by the contractor, fail the test of completion caused
by the contractor's negligence, breach of communication obligation by the project manager and
breach of assistance to the contractual obligation by the project manager. Various options that the
employer can use to reimburse for the loss and damages are also provided. They include: entitling
available remedies to external parties under expenses of the contractor, order of further tests in the
case of the failed test under contractor's expense, termination of the contract by the employer, the
intervention of Dispute Avoidance and Arbitration, making of payment claims and carrying out
further discussions between parties to avoid dispute.
FIDIC conditions of contract for plant and design building for Electrical and Mechanical
plants and Engineering works designed by the contractor 2017 form of contract one stipulates the

3

roles of a contractor in a construction contract to attain the best result in the construction. The
agreement between Seokyo JSC (the contractor) and Humberstone Salitrera SRL (the employer)
concerning the FIDIC conditions of the contract requires the contractor to oversee construction
activities as stated in clause 4.1 (contractor’s general obligation) of the FIDIC yellow book.
According to clause 7 of FIDIC 2017, which governs the contractor’s testing of the construction
resources and plant, under sub-clause 7.4, the contractor should give a notice to the engineer for
further actions such as additional testing as required in clause 13 (variations and adjustments) of
FIDIC 2017. However, the contractor, Tokyo JSC, failed to notify the engineer of the shortcomings
and opaque nature of the FEED information. Moreover, the contractor could not report additional
costs and delays to the engineer. These negligent actions affected the construction of the 2 MTPA
granular potassium nitrate fertilizer plant, manifested in its commercial operation output. The
contractor should be held accountable for the loss incurred by the employer.
After stating the requirements and expectations of the contract and in the agreement of the
same from the contractor, the employer is entitled to the right to hold the contractor accountable if
the requirements are not dully fulfilled. In the contract agreed upon by Seokyo JSC and
Humberstone Salitrera SRL, one of the contractor’s obligations agreed upon was to produce
quality work capable of ensuring a service lifespan of up to 25 years without any replacement to
the amenity. This is similar to clause 4.1 in paragraph one of the FIDIC 2017, which obliges the
contractor to accomplish the work according to the contract agreement or to suit the employer's
requirements. The failure of the a2 MTPA granular potassium nitrate fertilizer plant, which was in
the construction agreement, clearly indicates a breach of the agreement. Having agreed to 25 years
of self-service provision by the plant, this period should be considered the Defects Notification
Period. It is, therefore, right for the Employer, Humberstone Salitrera SRL, to notify the contractor

4

of the defects and request immediate action on the same as done on 20 May 2022 by the employer.
Tokyo JSC's refusal to act on the employer's request is a breach of article 11, sub-clause 11.1
subparagraph (b) of FIDIC 2017 conditions, which states that the contractor should perform
prerequisite work to remedy the defects noted by the employer before the Defects Notification
Period expires. Furthermore, the employer should not incur any cost during the remediation of the
defects resulting from the contractor's negligence. This is covered in sub-clause 11.2 (cost of
remedying defects) paragraph one, subparagraph (a), (b), (c), and (d). Failure to remedy the defects
entitles the employer the right to give a notice stating the exact period by which the defects should
be remedied as directed in sub-clause 11.4 paragraph 2. This sub-clause (11.4) through
subparagraph (a) allows the employer to offer the remediation of the defects to other parties, but
the entire activity is under the contractor's cost.
Tests of completion are the specified tests agreed in the contract, which are run before the
employer takes over the work defined by the agreement. Tests on completion are mandatory for
contractual work to assure the employer that the job is satisfactory and efficient and can be taken
over for commercial purposes, as stated in clause 10. According to sub-clause 9.1 of FIDIC
conditions of the contract of 2017, the contractor must provide documentation of the general work
and its maintenance and operational guides per sub-clause 4.1(d) requirements. The failure of the
a2 MTPA granular potassium nitrate fertilizer plant under construction by contractor Seokyo JSC
was caused by issues related to the plant's output. This suggests that its failure is a result of a fault
in construction caused by the contractor. The employer has the right, through the engineer, to order
an additional test concerning clause 9.3 of FIDIC. If the retest requires added cost, sub-clause 2.5,
which needs the contractor to reimburse the costs to the employer, should be revisited. Other ways
to handle the failure of the test of completion are by terminating the contract and rejecting the

5

work. This is if the failure significantly costs the employer. This law is defined in sub-clause 9.4
(b) of the FIDIC conditions of contract 2017. This method has been noted to be popularly used in
England.
Communication is an essential aspect of prioritizing construction contracts. It forms the
basis of cooperation (a requirement in contracts under sub-clause 4.6) between parties in the
agreement. These parties need to communicate efficiently to run the operations smoothly. Poor
communication may result in poor outcomes at the end of the work. The contract between Seokyo
JSC and Humberstone Slitrera SRL featured a requirement by the employer bounding the project
manager, PMC Inc., to provide any advisory and Front End Engineering and Design (FEED)
communications during the construction. The agreement stated; that the project manager shall
provide FEED for the process plant and use judgment, skill, care, and supervision to ensure good
quality of the construction in the contract. However, the contractor complained due to a lack of
response from the project concerning unclear information in FEED. This was significant jeopardy
to the plant's construction, as the contractor in the letter dated 13 July 2022 states. In this case, the
project manager breached FIDIC guides under sub-clause 1.3 and the contract agreement. Subclause 1.3 (notices and other communications) through paragraph 1 governs clarity in
communication and notifications. Response, advisory stand, decisions, and requests are some
highlighted forms of communication in the contract conditions. The project manager should
therefore be held responsible for not fulfilling his duty per the agreement. It is clear that the project
manager withheld and delayed the information. This is against sub-clause 1.3 (3).
The project manager in the Seokyo - Humberstone agreement is a type of assistance in the
construction contract. The project manager henceforth, as agreed in the contract, was to offer
service to the contractor concerning the construction plant. Under sub-clause 2.2 (assistance), the

6

employer is allowed to hold accountable and take legal actions or termination decisions to any the
aid of the contractor who fails to perform his duties as it is his (the employer) responsibility to
ensure the contractor gets whatsoever needed support. Nonresponses to the contractor's requests
indicate that the project manager failed to perform his assistance duties, affecting the entire
construction.
The employer, Humberstone Salitrera SRL, has suffered loss and dissatisfaction in his
work due to the negligence of the project manager and the contractor hired to construct the fertilizer
plant. He should take legal action. The employer should seek the intervention of the Dispute
Avoidance and Adjudication Board. The board reputes any dispute arising between parties to a
contract. Having a new clause inserted in the agreement as clause 24, which bounds every party to
irrevocably submit to the jurisdiction of the court of England and Wales for any dispute arising,
the parties have no option other than to present themselves for a hearing regarding the ruling of
England and Wales laws. The contractor has no right to defy the claim posted by the employer on
6 July 2022. Suppose the DAAB rules favour the contractor, and the employer has the right under
sub-clause 21.6 (arbitration) to involve international arbitration agencies. However, the arbitrator's
ruling will be made in language and law defined in the contract as directed in sub-clause 21.6 (c).
In this case, it will be done following the laws of England and Wales.
The employer may also give a notice to Senora Emilia Shackleton, the engineer claiming
payment from the contractor and the project manager for being key contributors to the failure of
the plant under construction. This is directed in sub-clause 20.2 (claims for payment and EOT) and
20.2.1 (notice of a claim). The employer also is entitled to an extension of the Defects Notification
Period following the improper working of the plant. The entitlement is per clause 11.3 (extension
of defects notification period). Extension of DNP delays the issuance of a certificate of comple...


Anonymous
This is great! Exactly what I wanted.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4

Similar Content

Related Tags