Week 5 "Human Resource Planning" 10 Questions

User Generated

fnwn1982

Business Finance

Description

Question 1

Quality is achieved by meeting scope and by not?

Disappointing the customer

Jeopardizing cost benefit ratio

Exceeding scope

Overestimating budget

Question 2

There are two types of costs tied to quality. The first is cost to conformance to quality and the second is?

Cost benefit analysis

Benchmarking performance

Design of experiments

Cost of nonconformance to quality

Question 3

There are a number of tools and techniques that can be utilized to plan for quality. All of the following are quality planning tools except?

Brainstorming

Delphi process

Affinity diagrams

Matrix diagrams

Question 4

The quality management plan addresses the following three areas; Quality control, quality assurance, and ?

Quality checklist

Cost of quality

Quality improvement

Quality boundaries

Question 5

These charts show the categorization of problems from largest to smallest?

Pareto diagrams

Control charts

Scatter diagrams

Cause-and-effect diagrams

Question 6

1.

Contracts and grievances with unionized groups are constraints. Additionally, unions are also?

Vendors

Stakeholders

Limitations

Employees

Question 7

This hierarchical chart decomposes the project by the types of resources it contains?

Organizational chart

Responsibility assignment matrix

RACI chart

Resource breakdown structure

Question 8

A chart that uses the activities of responsibility, accountability, consult and inform?

Organizational chart

Responsibility assignment matrix

RACI chart

Resource breakdown structure

Question 9

Team development as described by Tuckman only included four stages. The fifth stage added to the forming, storming, norming, and performing stage sequence is?

Adjourning

Rewarding

Recognizing

Reassigning

Question 10

This approach smooths out the conflicts by minimizing the perceived size of the problem. It is a temporary solution but can calm team members.

Ouchi’s theory Z

Coercive power

Authority power

Smoothing

Unformatted Attachment Preview

QUESTION 1 Quality is achieved by meeting scope and by not? Disappointing the customer Jeopardizing cost benefit ratio Exceeding scope Overestimating budget QUESTION 2 There are two types of costs tied to quality. The first is cost to conformance to quality and the second is? Cost benefit analysis Benchmarking performance Design of experiments Cost of nonconformance to quality QUESTION 3 There are a number of tools and techniques that can be utilized to plan for quality. All of the following are quality planning tools except? Brainstorming Delphi process Affinity diagrams Matrix diagrams QUESTION 4 The quality management plan addresses the following three areas; Quality control, quality assurance, and ? Quality checklist Cost of quality Quality improvement Quality boundaries QUESTION 5 These charts show the categorization of problems from largest to smallest? Pareto diagrams Control charts Scatter diagrams Cause-and-effect diagrams QUESTION 6 1. Contracts and grievances with unionized groups are constraints. Additionally, unions are also? Vendors Stakeholders Limitations Employees QUESTION 7 This hierarchical chart decomposes the project by the types of resources it contains? Organizational chart Responsibility assignment matrix RACI chart Resource breakdown structure QUESTION 8 A chart that uses the activities of responsibility, accountability, consult and inform? Organizational chart Responsibility assignment matrix RACI chart Resource breakdown structure QUESTION 9 Team development as described by Tuckman only included four stages. The fifth stage added to the forming, storming, norming, and performing stage sequence is? Adjourning Rewarding Recognizing Reassigning QUESTION 10 This approach smooths out the conflicts by minimizing the perceived size of the problem. It is a temporary solution but can calm team members. Ouchi’s theory Z Coercive power Authority power Smoothing
Purchase answer to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Please find attached. Thank you.

Outline

Introduction

Body

Conclusion


QUESTION 1
Quality is achieved by meeting the scope and by not?
Disappointing the customer
QUESTION 2
There are two types of cost tied to quality. The first is cost to conformance to quality and
the second is?
Cost ...