Can this be done by Saturday

User Generated

funrlrf

Writing

BUS 375 project management

Description

  • This assignment consists of two (2) parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for.Part A: Project Schedule
    (Submit as one [1] Microsoft Project file)
    1. In Assignment 2, you developed a project plan. Now, using the information from your project proposal, create a multi-level work breakdown structure (WBS) and detailed project schedule.
      Your project must include the following criteria:
      • The project must consist of at least twenty-five (25) tasks.
      • Each task must contain a start date, a finish date, and have main staffing and non-staffing resources assigned.
      • Assume that your work activities are completed during normal weekdays (no weekend work) under normal conditions (8 hours per day).
      • In terms of holidays, you can assume no work will be done the following days: New Year’s Day, President’s Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year’s Eve.
    Part B: Written Response
    (Submit as a Microsoft Word file)Write a one to two (1-2) page response in which you:
    1. Analyze your project in terms of project completion, critical path, and slack / float. Specifically, be sure to answer the following:
      • When will the project be completed?
      • What is the critical path for the project?
      • How much slack / float is in your project? What activities have the greatest slack / float?
    2. Summarize the recommendations or improvements you would make to your project schedule. Specifically, be sure to answer the following:
      • Identify the top three (3) activities that you believe could impact the project completion date.
      • What additional activities would you add to this project to make it more complete, from a project management viewpoint?
    3. Format your assignment according to the following formatting requirements:
      • Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

Running head: WRITTEN RESPONSE

1

Written Response
Institution Affiliation
Date

WRITTEN RESPONSE

2
Part B: WRITTEN RESPONSE

This is a response to the project that is scheduled to facilitate an effective and efficient
election which reduces the chances of rigging results. Therefore, in this direction, I recommend
the project to be completed by 6th April to ensure that the university has almost two months to be
ready for an election. The recruitment of the supervisors as well as the subordinates is the critical
path of the entire project. This is because the project requires numerous staff members to
facilitating its effectiveness. The personnel is supposed to have the ability to comprehend
advanced knowledge of operating the advanced electronic gadgets. The action of recruiting the
personnel required for an efficient election have the most float whereas training them has a high
slack. This is because it is challenging to get the appropriate staff to train and training could be
delayed due to thorough scrutiny when recruiting staff.
There are various activities of the project with the capability of influencing the date of
completion. They comprise of recruiting, training, and registering of voters. This is because
recruiting involves interviews and evaluation of candidates to get the most qualified individuals
for the tasks required. Training could also be lengthy as it involves assisting the staff to deal with
forecasted challenges (Budurushi, Renaud, Volkamer, & Woide, 2016). Registering of the voters
could also derail the project as people tend to be reluctant to register and end up requesting for
additional time. There is a need to include an overall evaluation process since it would assure the
efficiency of the project making it more complete. Errors would be corrected, and this would
increase efficiency. Appointing of external observers would also be suitable ...