PMAN635 Spring 2020
PMAN635 Session 9 IA-9
Name:
Problem: Given the information provided below (predecessors, normal time, normal cost, crash
time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for a
nine-activity (a to i) project) answer the questions (a) through (e) using this template.
Activity
Predecessor
Normal
Time
Normal
Cost
Crash
Time
Crash Cost
a
-
4
$ 50
2
$ 150
b
A
4
$ 40
2
$ 200
c
B
7
$ 70
4
$ 160
d
c, f
2
$ 20
1
$ 50
e
C
3
$ 30
2
$ 100
f
B
8
$ 80
5
$ 290
g
d, e
5
$ 50
3
$ 100
h
F
6
$ 60
2
$ 180
i
g, h
3
$ 50
3
$ 50
(a). Create the network diagram in the application of your choice and then insert a screenshot of
the diagram here. The diagram can be created easily in MS Word using the Insert Shapes
function. Alternatively, you can post an excel file with the network diagram rather than post it in
the space below.
Identify the critical path or critical paths (remember, there may be more than one) of the
network, the time, and cost of the normal level of activity for the project:
The critical path (or paths) is: abfdgi and a-b-c-d-g-i, and abcegi
15 18
0 e
8 15 15 3 18
0 c
0 4 4 8 8 7 15 18 23
0 a 0 b 0 g
0 4 4 4 4 8 16 18 18 4 23
0 d
16 2 18 23 26
0 i
8 16 23 3 26
0 f 16 22
8 8 16 1 h
17 6 23

Sign up to view the full document!

lock_open Sign Up
Showing Page:
2/3
PMAN635 Spring 2020
The project duration:_4 days + 4 days + 7 days + 3 days + 5 days + 3 days = 26 days
The project cost is: _$ 50 + $ 40 + $ 70 +$ 20 + $ 30 + $ 80 +$ 50 +$ 60 + $ 50 = $ 450_
(b). Calculate the crash cost-per-day. Enter your response to question 1(b) in the table provided
below
Activity
Normal Time
Normal Cost
Crash Time
Crash Cost
Crash Cost/Day
1
a
4
$ 50
2
$ 150
15050
4−2
= $ 50
b
4
$ 40
2
$ 200
20040
4−2
= $ 80
c
7
$ 70
4
$ 160
16070
7−4
= $ 30
d
2
$ 20
1
$ 50
5020
2−1
= $ 30
e
3
$ 30
2
$ 100
10030
3−2
= $ 70
f
8
$ 80
5
$ 290
29080
8−5
= $ 70
g
5
$ 50
3
$ 100
10050
5−3
= $ 25
h
6
$ 60
2
$ 180
18060
6−2
= $ 30
i
3
$ 50
3
$ 50
-
(c). Find the optimal way to crash the project by one day.
What is the projected project cost? = $ 450 + $ 25 = $ 475
What is the projected project duration? = 26 days 1 day = 25 days
What is the critical path (or paths)? = abfdgi, and abcegi, and a-b-c-d-g-i
What task or tasks were crashed? Task g was crashed.
Explain the results of your calculations.
All the paths after crashing task g by one day are critical. Crashing task g reduces it to 24 days at
a cost of $475. Activity g has the best optimal way to crash the project and only costs $25.
(d). Find the optimal way to crash the project by two days.
What is the projected project cost? = $ 475 + $ 25 = $ 500
What is the projected project duration? = 26 days 1 day 1 day = 24 days
What is the critical path (or paths)? abfdgi and abceg-i
What task or tasks were crashed? Task g was crashed by two days.
Explain the results of your calculations.
It is possible to crash both task g and task a by one day each concurrently. Task g,
however, has the least crash cost per day (25). The rest of the activities will cost the company a
lot of money to crush them.
1
Assume that each task’s crash costs are linear, i.e., that each day a task is crashed has an equal cost.

Sign up to view the full document!

lock_open Sign Up
Showing Page:
3/3

Sign up to view the full document!

lock_open Sign Up
Unformatted Attachment Preview
PMAN635 Spring 2020 PMAN635 Session 9 IA-9 Name: Problem: Given the information provided below (predecessors, normal time, normal cost, crash time (the minimum duration) and crash cost (the cost if crashed to the minimum duration) for a nine-activity (a to i) project) answer the questions (a) through (e) using this template. Activity Predecessor Normal Time a b c d e f g h i A B c, f C B d, e F g, h 4 4 7 2 3 8 5 6 3 Normal Cost $ $ $ $ $ $ $ $ $ 50 40 70 20 30 80 50 60 50 Crash Time Crash Cost 2 2 4 1 2 5 3 2 3 $ $ $ $ $ $ $ $ $ 150 200 160 50 100 290 100 180 50 (a). Create the network diagram in the application of your choice and then insert a screenshot of the diagram here. The diagram can be created easily in MS Word using the Insert Shapes function. Alternatively, you can post an excel file with the network diagram rather than post it in the space below. 0 4 0 a 0 4 4 ...
Purchase document to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Anonymous
This is great! Exactly what I wanted.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4