QUIZZER IN COST ACCOUNTING
Job Order Costing
The work in process account of the Malinta Company which uses a job order cost system follows: Work in Process
April 1 Bal 25,000
Direct materials 50,000
Direct Labor 40,000
FO applied 30,000
Finished Goods 125,450
Overhead is applied to production at a predetermined rate, based on direct labor cost. The work in process at April 30
represents the cost of Job No 456, which has been charged with direct labor cost of P3,000 and Job No 789, which has
been charged with applied overhead of P2,400.
1.
The cost of direct materials charged to Job No. 456 and 789 amounted:
a. P8,700
c. P4,500
b. P7,600
d. P4,200
2.
The prime cost during the month amounted to;
a. P70,000
c. P120,000
b. P90,000
d. P145,000
The following cost data pertain to Matatag Company for March 2000
March 1
March 31
P40,000
P50,000

Sign up to view the full document!

lock_open Sign Up
Showing Page:
2/25
25,000
35,000
60,000
70,000
March 1-31
P120,000
108,000
378,000
3.
The cost of goods manufactured during March was;
a. P378,000
c. P398,000
b. P388,000
d. P425,000
4.
The amount of materials purchased for the month was:
a. P50,000
c. P180,000
b. P170,000
d. P220,000
Hamilton Company uses a job order costing. Factory overhead is applied to production at a budgeted rate of 150% of
direct labor costs. Any overapplied or underapplied factory overhead is closed to the cost of good sold account at the
end of the month. Additional information is available as follows:
Direct Materials
P4,000
Direct Labor
2,000
Factory overhead applied
3,000
P9,000
Jobs 102,103 and 104 were started during February. Direct materials requisitions for February totaled P26,000. Direct
labor costs of P20,000 were incurred for February. Actual factory overhead was P32,000 for February. The only job
still in process at he end of February was Job No 104, with costs of P2,800 for direct materials and P1,800 for direct
labor

Sign up to view the full document!

lock_open Sign Up
Showing Page:
3/25

Sign up to view the full document!

lock_open Sign Up
End of Preview - Want to read all 25 pages?
Access Now
Unformatted Attachment Preview
 QUIZZER IN COST ACCOUNTING Job Order Costing The work in process account of the Malinta Company which uses a job order cost system follows: Work in Process April 1 Bal 25,000 Direct materials 50,000 Direct Labor 40,000 FO applied 30,000 Finished Goods 125,450 Overhead is applied to production at a predetermined rate, based on direct labor cost. The work in process at April 30 represents the cost of Job No 456, which has been charged with direct labor cost of P3,000 and Job No 789, which has been charged with applied overhead of P2,400. 1. The cost of direct materials charged to Job No. 456 and 789 amounted: a. P8,700 c. P4,500 b. P7,600 d. P4,200 2. The prime cost during the month amounted to; a. P70,000 c. P120,000 b. P90,000 d. P145,000 The following cost data pertain to Matatag Company for March 2000 March 1 March 31 Materials P40,000 P50,000 Work in Process 25,000 35,000 Finished Goods 60,000 70,000 March 1-31 Direct Labor Cost P120,000 Factory Overhead applied 108,000 Cost of good sold 378,000 3. The cost of goods manufactured during March was; a. P378,000 c. P398,000 b. P388,000 d. P425,000 4. The amount of materials purchased for the month was: a. P50,000 c. P180,000 b. P170,000 d. P220,000 Hamilton Company uses a job order costing. Factory overhead is applied to production at a budgeted rate of 150% of direct labor costs. Any overapplied or underapplied factory overhead is closed to the cost of good sold account at the end of the month. Ad ...
Purchase document to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Anonymous
Great study resource, helped me a lot.

Studypool
4.7
Trustpilot
4.5
Sitejabber
4.4