INF337: Integrated Cost & Schedule Control

SoccerBoss
Category:
Business & Finance
Price: $5 USD

Question description


Work Breakdown Structure

See page 33 of the text for a graphic example of a work breakdown structure (WBS) hierarchy. Create a three level product-based WBS from a project you have managed or have experience with as a team member and present a graphic representation of your WBS hierarchy. A description of the following components and how each relates to the WBS must be included:

  • Three main deliverables,
  • A unique numbering scheme, and
  • Three work packages.
Lastly, provide a one- to three-sentence project objective to describe the focus of this WBS.

Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1821 tutors are online

Related Business & Finance questions

12/04/2013
10/14/2013
10/13/2013
10/13/2013
10/13/2013
10/13/2013

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors