network diagram, AON showing two clear paths and the critical path

Price: $5 USD

Question description

A – Survey Site
B – Install Sewer and Storm DrainageA
C – Install Gas and Electric Power Lines A
D – Excavate Site for Spec HouseB, C
E – Pour FoundationD
Chart 3.1 Building a House, Predecessors

Your assignment is to:

  1. Construct a network diagram for this project using MS Project or MS Word and the data on the chart above. Your diagram should include two logical sequential paths to completion and all nodes should be labeled. If you are using MS Word, you will need to use a combination of textboxes and arrows to create the network diagram.
  2. Create an AON (Arrow on Node) network activity diagram illustrating the project activities with two paths to complete the project and a defined critical path. Again if you’re using Word you will use textboxes and arrows to create an AON network activity diagram.
  3. Explain your rationale for creating each path in the AON network activity diagram by using the notes feature in MS Project or in MS Word if that’s where you created the diagrams. Your rationale should be at least 100 words and should demonstrate project management best practices (a forward path).

Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1820 tutors are online

Brown University

1271 Tutors

California Institute of Technology

2131 Tutors

Carnegie Mellon University

982 Tutors

Columbia University

1256 Tutors

Dartmouth University

2113 Tutors

Emory University

2279 Tutors

Harvard University

599 Tutors

Massachusetts Institute of Technology

2319 Tutors

New York University

1645 Tutors

Notre Dam University

1911 Tutors

Oklahoma University

2122 Tutors

Pennsylvania State University

932 Tutors

Princeton University

1211 Tutors

Stanford University

983 Tutors

University of California

1282 Tutors

Oxford University

123 Tutors

Yale University

2325 Tutors