network diagram, AON showing two clear paths and the critical path

Anonymous
Category:
Management
Price: $5 USD

Question description

ActivityPredecessors
A – Survey Site
B – Install Sewer and Storm DrainageA
C – Install Gas and Electric Power Lines A
D – Excavate Site for Spec HouseB, C
E – Pour FoundationD
Chart 3.1 Building a House, Predecessors

Your assignment is to:

  1. Construct a network diagram for this project using MS Project or MS Word and the data on the chart above. Your diagram should include two logical sequential paths to completion and all nodes should be labeled. If you are using MS Word, you will need to use a combination of textboxes and arrows to create the network diagram.
  2. Create an AON (Arrow on Node) network activity diagram illustrating the project activities with two paths to complete the project and a defined critical path. Again if you’re using Word you will use textboxes and arrows to create an AON network activity diagram.
  3. Explain your rationale for creating each path in the AON network activity diagram by using the notes feature in MS Project or in MS Word if that’s where you created the diagrams. Your rationale should be at least 100 words and should demonstrate project management best practices (a forward path).

Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1831 tutors are online

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors