Contracting Management

Sigchi4life
Category:
Management
Price: $5 USD

Question description

1. The contracting officer can, at his discretion, elect not to terminate a defaulted contractor.

a. True

b. False


2. The only ground to terminate a contractor for default that does not require a cure notice is:

a. Failure to deliver

b. Failure to make progress

c. Failure to perform any other contractual condition

d. They all require a cure notice


3. The Loss Formula

a. Allows the contractor to recover his losses

b. Allows the government to recover it losses

c. Cause the contractor to sustain the same loss position it had prior to termination 

d. All the above


4. The total cost claim approach is not favored because:

a. It will yield large awards to the contractor

b. It does not take into account contractor cause additional costs

c. It doesn't take into account the government estimates

d. It doesn't allow for excusable delay


Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1819 tutors are online

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors