Percent of Total Overhead Cost allocated between 2 products.

SoccerBoss
Category:
Accounting
Price: $15 USD

Question description

Using the plantwide overhead rate, what percentage of the total overhead cost is allocated to Product Y and Product Z?


Activity Cost PoolActivity MeasureEstimated Overhead CostExpected Activity
 Machining Machine-hours$242,400  12,000 MHs
 Machine setups Number of setups$114,400 220 setups
 Production design Number of products$86,000 2 products
 General factory Direct labor-hours$302,400  14,400 DLHs
Activity MeasureProduct YProduct Z
 Machine-hours7,200  4,800  
 Number of setups40  180  
 Number of products1  1  
 Direct labor-hours8,200  6,200  

Tutor Answer

(Top Tutor) Daniel C.
(997)
School: University of Virginia
PREMIUM TUTOR
Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1822 tutors are online

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors