Problem 6-6

Twelve tasks, with times and precedence requirements as shown in the following table, are to be assigned to workstations that have a fixed machine cycle time of 1.5 minutes. Two heuristic rules will be tried: (1) greatest positional weight, and (2) greatest number of following tasks.

In each case, the tiebreaker will be shortest task time.


Task Length
(minutes)
Immediate
Predecessor
a 0.1 -
b 0.2 a
c 0.9 b
d 0.6 c
e 0.1 -
f 0.2 d, e
g 0.4 f
h 0.1 g
i 0.2 h
j 0.7 i
k 0.3 j
l 0.2 k
b. Assign tasks to stations under each of the two rules.
(1) greatest positional weight (shortest task time as tiebreaker)
Work Station Tasks
I

 
II
 
III
 
(2) greatest number of following tasks (shortest task time as tiebreaker)
Work Station Tasks
I
 
II
 
III
 
c.

Compute the percentage of idle time for each rule. (Round your answer to 2 decimal places. Omit the "%" sign in your response.)

 
  Percentage of idle time

Tutor Answer

(Top Tutor) Daniel C.
(997)
School: Boston College
PREMIUM TUTOR
Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1819 tutors are online

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors