project management MRP

Sigchi4life
Category:
Management
Price: $50 USD

Question description

John needs 40 Eternal Light flashlights by week 6. Each Eternal Light flashlight requires 3 bulbs, and each bulb requires 3 filaments. There are 90 bulbs and 10 filaments in beginning inventory. John ordered an additional 20 bulbs and they are arriving in week 2. The lead time for the flashlights is 2 weeks, the lead time for the bulbs is 2 weeks, and the lead time for the filaments is 1 week. Please prepare

A. The Product Structure Tree

B. A Material Requirements Plan for the flashlights, bulbs and filaments


Tutor Answer

(Top Tutor) Daniel C.
(997)
School: UC Berkeley
PREMIUM TUTOR
Studypool has helped 1,244,100 students
Ask your homework questions. Receive quality answers!

Type your question here (or upload an image)

1823 tutors are online

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors