Review a Project Schedule and Evaluate (Bid with 1 hour ..for tutor Taliatech)

Anonymous
timer Asked: Nov 7th, 2016

Question description

In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below.

ActivityTaskPredecessorsDurationActivity Cost
ASign ContractNone5 days$5,000
BDesign SurveyA3 days$1,500
CIdentify AudienceA7 days$1,000
DRun SurveyB, C30 days$6,000
EAnalyze ResultsD5 days$3,000
FCreate PresentationE5 days$1,000
GPresent to ClientE, F2 days$3,000
  • Reconfigure the chart above into a critical path diagram for project scheduling similar to the diagram shown in this module's lecture.
  • What is the duration of the project?
  • How much slack is currently available in the non-critical path?
  • How long are the project and feeder buffers?

Studypool has helped 1,244,100 students
flag Report DMCA
Similar Questions
Hot Questions
Related Tags
Study Guides

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors