Project Management Problems

Anonymous
label
Management
timer
Asked: Nov 20th, 2016
Question description
There are 5 problems that i need help to solve (i.e., to calculate the net present value and the simple payback, project priority matrix, project network, Gantt Chart, earliest, midpoint and latest estimated time, cost, BAC for the project). See attach for specific detials/description of the problems
Problem #1
Project Selection at Nova Western, Inc.
Phyllis Henry, vice president of new product development, sat at her desk, trying to make sense
of the latest new project proposals she had just received from her staff. Nova Western, Inc., a
large developer of business software and application programs, had been experiencing a
downturn in operating revenues over the past three quarters. Their consensus opinion was that
Nova Western needed some new product ideas, and fast.
The report Phyllis was reading contained project screenings conducted by two independent
groups within the new product development department. One project, code-named Janus, was
championed by the head of software development. The other project idea, Gemini, had the
support of the business applications organization. Phyllis’s original charge to her staff was to
prepare an evaluation of both projects in order to decide which one Nova Western should
support. Because of budget restrictions, there was no way that both projects could be funded.
The first evaluation team used a weighted scoring model, based on the key strategic categories at
Nova Western, to evaluate the two projects. However, Phyllis was also presented with financial
analyses of the two projects by her second team of evaluators. Their evaluation assumed a
required rate of return of 18%, including anticipated inflation, over the lives of the two projects.
Nova Western’s client is very concerned about being first to market after the successful
completion of this new project. They are very concerned about the project scope and
deliverables and are not interested in any changes. Budget is always a concern but there are
budget and management reserve funds available just in case additional resources are needed.
The data the project selection teams collected are shown on the next page:
Project Janus
Category
1. Strategic fit
2. Probability of technical success
3. Financial risk
4. Potential profit
5. Strategic leverage
Importance
3
2
2
3
1
Score
2
2
1
3
1
Weighted
Score
Total Score
Initial investment
Life of the project
Anticipated stream of future cash flows:
Year 1
Year 2
Year 3
Year 4
Year 5
Calculated NPV
Simple Payback
$250,000
5 years
$50,000
$100,000
$100,000
$200,000
$75,000
Project Gemini
Category
1. Strategic fit
2. Probability of technical success
3. Financial risk
4. Potential profit
5. Strategic leverage
Importance
3
2
2
3
1
Score
3
2
2
3
2
Total Score
Initial investment
Life of the project
Anticipated stream of future cash flows:
Year 1
Year 2
Year 3
Calculated NPV
Simple Payback
Weighted
Score
$400,000
3 years
$75,000
$250,000
$300,000
A. Complete the tables on the preceding page. Use the weighted scoring model to score
each project. Use the financial selection models to calculate the net present value and the
simple payback for each project. Place these values in the tables on the previous page
in spaces indicated.
B. Using only the financial criteria for project selection, which project should Nova Western
select and why?
C. Using only the weighted scoring model for project selection, which project should Nova
Western select and why.
D. Based on the above case scenario, determine the project priority matrix for the project
and write it in the space provided. Why do you think this is what the client and Nova
Western have agreed to?
Problem # 2
You are creating a project network for a market research project for FUN, Inc. With the information
provided below, draw the project network on the next page. Complete the forward pass, the backward
pass and compute the activity slack.
Activity
A
B
C
D
E
F
G
Description
Contract signed
Survey design
Identify target market
Data collection
Develop presentation
Analyze results
Present Results
Predecessor
None
A
A
B,C
B
D
E,F
Time (days)
3
3
3
7
2
2
1
A. Network diagram
Legend
ES
SL
LS
DUR
ID
LF
EF
B. Gantt Chart
Take the Network Diagram that you created on the previous page make a Gantt Chart for the project in
the space provided below. Be sure to identify or distinguish between working time and slack time
for each activity as appropriate.
0
1
2
3
4
5
6
7
8
9
10
11 12 13 14 15 16 17 18
C. Network Questions
1. What is (are) the critical path (s) _____________________________________________
2. What is the planned project completion time? ____________
3. What is the slack for activity E? ____________
4. If there are burst activities, identify them here:
____________
5. If there are any merge activities, identify them here :
____________
6. How sensitive is this project network?
Problem #3
You are given the following information regarding a project. The earliest, midpoint and latest
estimated time for each activity is noted. Based on this information:
a. Compute the te and Variance for each activity to complete the table. (20 Points)
Activity
Predecessors
a
m
b
A
---
7
9
11
B
A
1
2
3
C
A
7
8
9
D
B
2
5
11
E
C
2
3
4
F
C
1
4
8
G
D, E
6
7
8
H
E, F
2
6
9
I
G, H
1
2
3
te
Variance
a. What are the Expected Time and the Variance for the project?
b.
What is the probability of completing the project within the Expected Time?
c. If you were told that you must finish this project in 32 days, what level of
confidence (probability) would you assign to meeting this deadline?
Problem #4
Given the data and information that follow and given the indirect costs for each project duration
are $400 (19 time units), $350 (18), $300 (17), and $250 (16) respectively; compute the total
direct cost for each project duration from the normal time through the crash point and provide
that in the table on the next page. What is the optimum cost-time schedule for the project? What
is this cost?
Normal Normal
Activity Predecessor
Time
Cost
A
B
C
D
E
F
G
A
A
A
B
C
E, F, D
3
5
3
10
6
7
5
50
60
70
50
100
90
50
Maximum
Crash
Time
Crash
Cost
1
2
1
0
3
3
1
20
60
40
0
50
100
70
a. Complete the table below:
Duration
Direct Costs
Indirect Costs
Total Costs
b. What is the optimum Cost-Duration solution for the project you just analyzed?
Cost: ___________________
Duration:_____________________
c. Reducing the project duration increases the risk of being late. Explain.
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
____________________________________________________________________________________
Problem #5
The National Science Foundation is planning a research study on ice flow in Antarctica. The
activities and their predecessors, along with the budget item are included in the following table:
Task/Activity
Time
(mo.)
Predecessor(s)
A. Preliminary Plan
B. Detail Plan
C. Hire staff
D. Equipment selection
E. Train staff
F. Buy clothing/supplies
G. Plane Transportation
H. Get custom equipment
I. Get additional equipment
J. Test equipment
K. Ship clothing/supplies
L. Travel
3
2
2
1
1
3
2
5
3
1
5
1
None
A
B
B
C
C
C
D
H
E, I
F
G, K, J
Total
Budget
($000)
3
2
4
5
3
9
60
36
20
6
15
9
Work Package by Month
1
2
3
4
5
1
1
1
1
1
4
0
5
3
3
0
6
5
55
5
5
10 10
6
10
5
5
6
3
3
0
0
9
9
A. Create a Time-Phased Budget
ID
A
B
C
D
E
F
G
H
I
J
K
L
Task
Dur Budget
Prel Plan
Det. Plan
Hire Staff
Sel. Equip
Train
Purch. Clothing
Plane Transport
Custom Equip.
Additonal Equip.
Test Equip.
Ship Supplies
Travel
Total Budget
Cumulative Budget
0
1
2
3
B. Create a Time-Cost Duration Graph.
Cost
Period
4
5
6
7
8
9
10
11
12
13
14
15
16
C. Use the information on the previous two pages to respond to the questions below:
1. What is the BAC for the project?
2. What is the Planned Value after the completion of month 9 of the project?
3. If the project is 60% complete in terms of cost at the completion of month 9 of the project
and your actual cost incurred thru this same time period is $108,000, what is your revised
estimate for the project cost at completion? Is the project ahead or behind in terms of
scheduled work?

Similar Questions
DEFINE MANAGEMENT & ITS FUNCTIONS
DEFINE MANAGEMENT & ITS FUNCTIONS...
What is Opinion Leadership?
What is Opinion Leadership?...
Discussion 7 need A+ work
Read the various perspectives on the death penalty on pages 262-268. Evaluate each argument for validity and soundness. ...
"The Purchasing Power of the U.S. Government
Determine the biggest hindrance to getting more people engaged in contracting
with the government. Not every business own...
Discussion 7 need A+ work
Read the various perspectives on the death penalty on pages 262-268. Evaluate each argument for validity and soundness. ...
Process improvement case
If you don't work for an organization at
the present time or the organization does not address process
improvement, th...
need help in information system homework asap
New Microsoft Office Word Document.docx meeting all the requirements and instructions...
need help in information system homework asap
New Microsoft Office Word Document.docx follow all the instructions and complete all the requirements .........
Human Resource Management.
How would you apply the dynamic culture leadership model to a real (or hypothesized) health leadership situation or case? ...
Hot Questions
MLA Works Cited - Quiz 10 question
Question 1 (1 point) The student is quoting from "Surveillance: Taking It Downtown" by Br...
Appropriate Quotation (MLA Style) - Quiz 10 quetion
Question 1 (1 point) [Original:]
Most editors test their covers in focus groups in an endless search for
the magi...
HMGT 300 Week 6 Quiz
Question
1 (4 points)
According to the National Institute
for Health Care Management: Understanding U.S...
questions end of term British and world literature
1. In his stories, Arthur Conan Doyle portrays Sherlock Holmes as __________.(Points : 5) an intelligent a...
Childhood Anxiety/ Ashford Univ EDU644
Hourigan, Settipani, Southam-Gerow, & Kendall (2012) explain, “Childhood anxiety disorders are among the most common...
Payroll project.
I need help with this payroll project from Chapter 7. This is the book: Payroll Accounting, by Beig, Toland, edition 2017....
Need help with some Discussions about cultural issues that may impact on you as an ICT professional
Question 1Describe and discuss what cultural issues may impact on you as an ICT professional if your organisation mer...
The table lists the average annual cost of tuition and fees, algebra homework help
The table lists the average annual cost of tuition and fees
at private 4-year colleges for sel...
Identifying an Acceptable Paraphrase (MLA Style) - Quiz 10 question
Question 1 (1 point) [Ed: error here relates to close wording]The
original vision of charter schools in 1988, when ...
Related Tags
Study Guides
Cant Hurt Me - Master Your Mind and Defy the Odds
by David Goggins
Of Mice and Men
by John Steinbeck
The Iliad
by Homer
Freakonomics
by Stephen J. Dubner and Steven D. Levitt
Unf*ck Yourself
by Gary John Bishop
The Scarlet Letter
by Nathaniel Hawthorne
Z for Zachariah
by Robert C. O’Brien
Alice in Wonderland
by Lewis Carroll
Murder on the Orient Express
by Agatha Christie