Description
- Create a risk template by listing the risks that you think are appropriate for ADC.
- You may need to make assumptions about the project. Just be sure to document them in the description of the risk.
- When identifying your risks, be sure to consider the following:
- Project and product risks
- External and internal risks
- Project budget risks
- Scheduling risks
- Resource risks
- Product quality risks
- Be sure to categorize and quantify all of the identified risks.
- use the attached copy of the risk template
Unformatted Attachment Preview
Purchase answer to see full attachment
Explanation & Answer
Attached.
Answer outline to risk assessment
•
Discussion of risk in the email system upgrade.
Santianna Horseson-Eversole
PM630: Contracting & Procurement in PM
Unit 3 Group Project: Part One
April 24, 2017
Colorado Technical University Online
Professor Burke
Project: ADC Project Management Scheduling Software & Server Upgrade
Task: Risk Assessment
Probability Scale:
Impact Scale:
Very low: 1
Low: 2
Moderate: 3
High: 4
Very high: 5
Very low: 1
Low: 2
Moderate: 3
High: 4
Very high: 5
ID # Risk
1
Product Risk
1.1 Migration of the
system
Description
Probability Severity Risk Response
The complex features of
the new product affecting
the multiple areas of the
already existing
infrastructure.
A new DB server,
programming language
and an integration system.
4
5
3
4
1.2
New technologies in
the new product
1.3
New development
team
Lack of experience in the
new team may pose risk
to the existing product
and the new one.
3
4
1.4
Tight schedules
With tight schedules the
staff will work in a rush
and hence commit more
mistakes due to reduced
concentration on each
task.
3
4
Conduct a system
match between the
new server
requirements with the
existing server.
A system analysis to
ensure compatibility
before purchase of the
new servers.
Close supervision
from the chief
engineer to ensure
that all milestones are
achieved according to
the grand architect to
the project.
• Having a
schedule that
will meet the
project
deliverables to
allow enough
time for testing
the servers and
correcting
errors so that
each task is
handled with
1.5
Delay in the delivery
of the AUT system for
testing
Due to coding
complexities AUT system
may not be available for
testing as scheduled.
3
5
1.6
Hardware upgrade
Not all the 2000 users in
the 12 departments will
have their computer
hardware upgraded on the
testin...