In Assignment 2, you developed a project plan. Now, using the information from your project proposal, create a multi-level work breakdown structure (WBS) and detailed project schedule.
Your project must include the following criteria:

  • The project must consist of at least twenty-five (25) tasks.
  • Each task must contain a start date, a finish date, and have main staffing and non-staffing resources assigned.
  • Assume that your work activities are completed during normal weekdays (no weekend work) under normal conditions (8 hours per day).
  • In terms of holidays, you can assume no work will be done the following days: New Year’s Day, President’s Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year’s Eve.
  • Write a one to two (1-2) page response in which you:
    1. Analyze your project in terms of project completion, critical path, and slack / float. Specifically, be sure to answer the following:
      • When will the project be completed?
      • What is the critical path for the project?
      • How much slack / float is in your project? What activities have the greatest slack / float?
    2. Summarize the recommendations or improvements you would make to your project schedule. Specifically, be sure to answer the following:
      • Identify the top three (3) activities that you believe could impact the project completion date.
      • What additional activities would you add to this project to make it more complete, from a project management viewpoint?
    3. Format your assignment according to the following formatting requirements:
      • Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides.
      • Include a cover page containing the title of the assignment, the student’s name, the professor’s name, the course title, and the date. The cover page is not included in the required page length

User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Ok, trying this again. If this goes through, I enjoyed this project. My gnatt excel charts only held ten items at a time, so I have three of them total to make the 25 tasks. Please let me know if you have edits. I appreciate you working with me and hope to do so again.Kristen

Outline for Project Schedule
1.
2.
3.
4.
5.
6.

Read information given
Create outline for project
Research information needed
Complete paper as instructed
Edit paper with Grammarly and other plagiarism checker
Submit to student


Running head: PROJECT RESPONSE

1

Project response
Name
Professor
Course
Date

PROJECT RESPONSE

2

Zentech Company Project Response
The Zentech company construction project which involves construction of 20 residential
units is scheduled to commence on the 5th of June 2017 and run for about ten months. The
project completion date is on 12th April of 2018. The handing over of the completed project is
scheduled to take place on the 14th of April 2018. For all the 20 units, work is supposed to run
simultaneously and end at the same time. Similar work for all of them is slotted the same time
and same resources. For instance land clearance will start for all the units and preparation for
construction phase commence for all of them. This is meant to cut in the cost of construction and
utilize maximally some of the leased project machinery.
The critical path of the project is given by the most critical tasks that include, site
clearance and setting out the foundation together with concrete pouring and leveling. Any delay
on these tasks means that the completion date will change. This also means the tasks have zero
float. The total critical path is 60 days from these tasks. There is however tasks which have
higher float or slack including the concreting and wall construction process (Kelley & Walker,
2002). This is because delay in construction has to be allowed to give the previous construction
task time for curing before the subsequent task commences. The curing time for the foundation
and first floor slabs is supposed to be 28 days before the form work is removed...