How to Develope the Project Plan and Determining Critical Path, management homework help

User Generated

gval10ghegyr

Business Finance

Description

Project Planning – Developing the Project Plan and Determining Critical Path

  1. Using the District4WarehouseMove WBS.xls provided, create a project plan for the District 4 Warehouse Move project. Use the PDF document, Project Plan Check – District4Move, to check your work to be sure you have created your starting project plan correctly. ProjectLibre is required for this task. If you have not yet downloaded ProjectLibre, please click here and follow the directions to do so now.

    Note: you will need to insert a column to include your WBS codes, then you will need to sequence the tasks to show tasks by work package.
  2. Based upon the details in the WBS and the project case, determine which tasks need to be completed first and which tasks are dependent upon other tasks to be completed prior to starting. Using this information identify predecessors in your project plan’s predecessor column. Complete the predecessor column by entering the line number of tasks that must be completed in order for each task to start. This will create your project timeline.
  3. Using ProjectLibre's Network or flow diagram view, determine the critical path for this project. In a MS Word document, list the activities that are on the critical path. Considering the risks identified in the risk table below, identify which risks would be most likely to increase your project timeline. Justify your responses.
  4. Submit both your completed project plan and your MS Word document.

District 4 Production Warehouse Move Project - Risk Table


1

Permits are not received per the schedule

2

Finish work contractors walk off the job half way through

3

Framing and drywall contractors are running behind schedule and can only produce half their crew as scheduled

4

Work benches are poor quality and 1/3 will have to be rebuilt

Unformatted Attachment Preview

ID WBS Task Name Duration Start Finish Predecessors Resource Names 2/1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 1 1.1 1.2 1.3 1.4 2 2.1 2.2 2.3 2.4 3 3.1 3.2 3.3 4 4.1 4.2 4.3 4.4 4.5 5 5.1 6 6.1 7 7.1 8 8.1 8.2 8.3 8.4 9 9.1 9.2 9.3 9.4 10 10.1 10.2 Project Kick-off Book location for meeting Invite stakeholders Prepare presentation Conduct the meeting Project Documents Develop Charter/Scope Develop WBS Develop Project Plan Develop Communication Plan Status Reports/Meetings Develop Status Report Set schedule for team meetings Set schedule for stakeholder meetings Initial Planning Meetings with Vendors Meet with Framing/Drywall Meet with Electrical Meet with Plumbing Meet with Finish Work Meet with Student Workers Electrical Permits Obtain Electrical Permits Plumbing Permits Obtain Plumbing Permits Building Permits Obtain Building Permits Framing Framing-Order Supplies Framing-Build Framing-Inspect Framing-Project Sign-off Electrical Electrical-Order Supplies Electrical-Install Electrical-Inspect Electrical-Project Sign-off Plumbing Plumbing-Order Supplies Plumbing-Install Project: District4Move.mpp Date: Sat 1/8/11 1 day 1 day 1 day 1 day 1 day 7 days 2 days 7 days 2 days 2 days 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 1 day 10 days 10 days 10 days 10 days 10 days 10 days 15 days 3 days 15 days 10 days 1 day 10 days 3 days 10 days 10 days 1 day 10 days 3 days 10 days Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Tue 1/11/11 Tue 1/4/11 Tue 1/11/11 Tue 1/4/11 Tue 1/4/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Fri 1/14/11 Fri 1/14/11 Fri 1/14/11 Fri 1/14/11 Fri 1/14/11 Fri 1/14/11 Fri 1/21/11 Wed 1/5/11 Fri 1/21/11 Fri 1/14/11 Mon 1/3/11 Fri 1/14/11 Wed 1/5/11 Fri 1/14/11 Fri 1/14/11 Mon 1/3/11 Fri 1/14/11 Wed 1/5/11 Fri 1/14/11 January Februar 1/2 1/9 1/16 1/23 1/30 2/6 Project Manager Project Manager Project Manager Project Manager and A Project Manager Project Manager Project Manager Project Manager and Attend Project Manager Project Manager and W Project Manager Project Manager Project Manager Project Manager and Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager and E Project Manager and S Project Manager and W Project Manager and W Project Manager and S Project Manager and East S Project Manager and Spark Project Manager and Water Project Manager and Wood Project Manager and Stude Sparks Electrical PM Sparks Electrical P Waterworks Plumbing Waterworks Plumbi East Side Framing & D East Side Framing East Side Framing & D East Side Framing & D City & County Project Manager East Side Framing & Dryw East Side Fra City & County Project Manager Sparks Electrical PM Sparks Electrical City & County Project Manager Sparks Electrical PM Sparks Electrical City & County Project Manager Waterworks Plumbing Waterworks Plumbing Task Milestone External Tasks Split Summary External Milestone Progress Project Summary Deadline Page 1 2/2 Waterworks Plumbing PM Waterworks Plumbi ID WBS Task Name Duration Start Finish Predecessors Resource Names 2/1 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 10.3 10.4 11 11.1 11.2 11.3 11.4 12 12.1 12.2 12.3 12.4 13 13.1 13.2 13.3 13.4 14 14.1 14.2 14.3 15 15.1 15.2 15.3 16 16.1 16.2 16.3 17 17.1 17.2 17.3 Plumbing-Inspect Plumbing-Project Sign-off Drywall Drywall-Order Supplies Drywall-Install Drywall-Inspect Drywall-Project Sign-off Finish Work Finish-Order Supplies Finish-Install Finish-Inspect Finish-Project Sign-off Workbenches Workbenches-Order Supplies Workbenches-Build Workbenches-Quality inspection Workbenches-Project Sign-off Equipment Packing Pack production equipment Pack non-production equipment Project Sign-off Move Move production equipment Move non-production equipment Project Sign-off Procurement Closure Review contract work Release contractors Pay contractors Project Closure Final report Archive documentation Lessons Learned Project: District4Move.mpp Date: Sat 1/8/11 10 days 1 day 15 days 3 days 15 days 10 days 1 day 15 days 3 days 15 days 10 days 1 day 15 days 2 days 15 days 2 days 1 day 2 days 2 days 2 days 1 day 3 days 3 days 3 days 1 day 3 days 3 days 1 day 1 day 3 days 3 days 3 days 1 day Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Mon 1/3/11 Fri 1/14/11 Mon 1/3/11 Fri 1/21/11 Wed 1/5/11 Fri 1/21/11 Fri 1/14/11 Mon 1/3/11 Fri 1/21/11 Wed 1/5/11 Fri 1/21/11 Fri 1/14/11 Mon 1/3/11 Fri 1/21/11 Tue 1/4/11 Fri 1/21/11 Tue 1/4/11 Mon 1/3/11 Tue 1/4/11 Tue 1/4/11 Tue 1/4/11 Mon 1/3/11 Wed 1/5/11 Wed 1/5/11 Wed 1/5/11 Mon 1/3/11 Wed 1/5/11 Wed 1/5/11 Mon 1/3/11 Mon 1/3/11 Wed 1/5/11 Wed 1/5/11 Wed 1/5/11 Mon 1/3/11 City & County Project Manager January Februar 1/2 1/9 1/16 1/23 1/30 2/6 City & County Project Manager East Side Framing & D East Side Framing & D City & County Project Manager East Side Framing & Dryw East Side Fra City & County Project Manager Woodcraft Carpentry P Woodcraft Carpentry City & County Project Manager Woodcraft Carpentry PM Woodcraft Car City & County Project Manager Student Workers Mana Student Workers Project Manager Project Manager Student Workers Manager Student Worke Project Manager Project Manager City Equipment Mover City Equipment Mover Project Manager City Equipment Movers PM City Equipment Movers Project Manager Express Moving Comp Express Moving Comp Project Manager Express Moving Company Express Moving Company Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Project Manager Task Milestone External Tasks Split Summary External Milestone Progress Project Summary Deadline Page 2 2/2 Work Breakdown Structure Project Name: Project Manager: Date: District 4 Warehouse Move Work Breakdown Structure Purpose and Limitations The purpose of this worksheet is to: Identify the work to be done Identify the types of resources required for the work Develop estimates for each work element This worksheet does not address: When the work will be completed Use the following table to define the major deliverables and associated task detail for each deliverable. Use the example (in r help in determining how to break up the work and identify the Work ID numbers. Expand the table as needed. Work Package Task ID 1 1.1 1.2 1.3 1.4 2 2.1 2.2 2.3 2.4 3 Tasks Project Kick-off Book location for meeting Invite stakeholders Prepare presentation Conduct the meeting Develop Charter/Scope Develop WBS Develop Project Plan Develop Communication Plan 4 Initial Planning Meetings with Vendors 5 6 Project Manager Project Manager and Workers Project Manager Project Manager Status Reports/Meetings Develop Status Report Set schedule for team meetings Set schedule for stakeholder meetings 5.1 Project Manager Project Manager Project Manager Project Manager and Attendees Project Documents 3.1 3.2 3.4 4.1 4.2 4.3 4.4 4.5 Resource(s) Required Meet with Framing/Drywall Meet with Electrical Meet with Plumbing Meet with Finish Work Meet with Student Workers Project Manager Project Manager Project Manager Project Manager and East Side Framing PM Project Manager and Sparks Electrical PM Project Manager and Waterworks Plumbing PM Project Manager and Woodcraft Carpentry PM Project Manager and Student Workers Manger Electrical Permits Obtain Electrical Permits Plumbing Permits Sparks Electrical PM 6.1 7 7.1 8 8.1 8.2 8.3 8.4 9 9.1 9.2 9.3 9.4 Obtain Plumbing Permits Building Permits Obtain Building Permits East Side Framing & Drywall PM Framing Framing-Order Supplies Framing-Build Framing-Inspect Framing-Project Sign-off East Side Framing & Drywall PM East Side Framing & Drywall City & County Project Manager Electrical Electrical-Order Supplies Electrical-Install Electrical-Inspect Electrical-Project Sign-off 10 Plumbing 10.1 Plumbing-Order Supplies Plumbing-Install Plumbing-Inspect Plumbing-Project Sign-off 10.2 10.3 10.4 Waterworks Plumbing PM 11 Drywall 11.1 11.2 11.3 11.4 Drywall-Order Supplies Drywall-Install Drywall-Inspect Drywall-Project Sign-off 12 Finish Work 12.1 12.2 12.3 12.4 Finish-Order Supplies Finish-Install Finish-Inspect Finish-Project Sign-off 13 Workbenches 13.1 13.2 13.3 13.4 Workbenches-Order Supplies Workbenches-Build Workbenches-Quality inspection Workbenches-Project Sign-off 14 Equipment Packing 14.1 14.2 14.3 Pack production equipment Pack non-production equipment Project Sign-off 15 Move 15.1 15.2 15.3 Move production equipment Move non-production equipment Project Sign-off 16 Procurement Closure 16.1 16.2 16.3 Review contract work Release contractors Pay contractors 17 Project Closure Sparks Electrical PM Sparks Electrical City & County Project Manager Waterworks Plumbing PM Waterworks Plumbing City & County Project Manager East Side Framing & Drywall PM East Side Framing & Drywall City & County Project Manager Woodcraft Carpentry PM Woodcraft Carpentry City & County Project Manager Student Workers Manager Student Workers Project Manager Project Manager City Equipment Movers PM City Equipment Movers Project Manager Express Moving Company PM Express Moving Company Project Manager Project Manager Project Manager Project Manager 17.1 17.2 17.3 Final report Archive documentation Lessons Learned Project Manager Project Manager Project Manager or the work h deliverable. Use the example (in red) for the table as needed. Estimated Duration (in days) Tasks Estimated Duration (in days) Work Package 4 1 1 1 1 13 2 7 2 2 3 1 1 1 5 1 1 1 1 1 10 10 10 10 10 10 24 3 15 5 1 19 3 10 5 1 19 3 10 5 1 24 3 15 5 1 24 3 15 5 1 20 2 15 2 1 5 2 2 1 7 3 3 1 5 3 1 1 7 3 3 1
Purchase answer to see full attachment
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

Explanation & Answer

Attached.

SURNAME 1
Student Name
Name of Instructor
Unit Code
Date
Critical Task Path
Book location for meetings, Invite stakeholders, Prepare presentation, Conduct the meeting, Develop
Charter/Scope, Develop WBS, Develop Project Plan, Develop Communication Plan, Develop Status
Report, Meet with Framing/Drywall, Obtain building permits, Framing-Order Supplies, Framing-Build,
Framing-Inspect, Framing-Project Sign-off, Electrical-Install, Electri...