Can someone do a WBS?

funrlrf
timer Asked: Nov 20th, 2017

Question Description

The case and project needed was downloaded.

Thanx

Unformatted Attachment Preview

Project Management: The Managerial Process, 6th Edition Page 1 of 1 Greendale Stadium Case The G&E Company is preparing a bid to build the new 47,000 seat Greendale baseball stadium. The construction must start July 1, 2011, and be completed in time for the start of the 2014 season. A penalty clause of $100,000 per day of delay beyond May 20, 2014, is written into the contract. Ben Keith, the president of the company, expressed optimism at obtaining the contract and revealed that the company could net as much as $2 million on the project. He also said if they are successful, the prospects for future projects are quite good since there is a projected renaissance in building classic ball parks with modern luxury boxes. ASSIGNMENT Given the information provided in T able 6.3, construct a network schedule for the stadium project and answer the following questions: 1. Will the project be able to be completed by the May 20 deadline? How long will it take? 2. What is the critical path for the project? 3. Based on the schedule would you recommend that G&E pursue this contact? Why? Include a one-page Gantt chart for the stadium schedule. CASE APPENDIX: TECHNICAL DETAILS OF THE GREENDALE BASEBALL STADIUM The baseball stadium is an outdoor structure with a retractable roof. The project begins with clearing the site, an activity that lasts 70 days. Once the site is clear, work can start simultaneously on the structure itself and demolishing an adjacent building site. This demolition is necessary to create a construction stage for storing materials and equipment. It will take 30 days to demolish the buildings and another 70 days to set up the construction site. Page 203 https://jigsaw.vitalsource.com/books/1259766608/epub/OEBPS/16 chapter06.xhtml 11/20/2017 Project Management: The Managerial Process, 6th Edition 1 ID 1 2 3 4 5 6 8 9 10 11 12 13 14 15 16 17 18 19 20 Page 1 of 1 6.3 Greendale Stadium Case Activity Duration Baseball Stadium Clear stadium site Demolish building Set up construction site Drive support piling Pour lower concrete bowl Pour main concourse Install playing field Construct upper steel bowl Install seats Build luxury boxes Install jumbotron Stadium infrastructure Construct steel canopy Light installation Build roof supports Construct roof Install roof tracks Install roof Inspection 70 days 30 days 70 days 120 days 120 days 120 days 90 days 120 days 140 days 90 days 30 days 120 days 75 days 30 days 90 days 180 days 90 days 90 days 20 days Pred essor s) 3 2 5 3,6 3,6 3,6 7,9 7,9 7,9 7,9 10 14 6 16 16 17,18 8,11,13,15,19 The work on the stadium begins by driving 160 support pilings, which will take 120 days. Next comes the pouring of the lower concrete bowl (120 days). Once this is done and the construction site has been set up, then the pouring of the main concourse (120 days), the installation of the playing field (90 days), and the construction of the upper steel bowl can occur (120 days). Once the concourse and upper bowl are completed, work can start simultaneously on building the luxury boxes (90 days), installing the seats (140 days), installing the jumbotron (30 days), and installing stadium infrastructure (120 days) which includes: bathrooms, lockers, restaurants, etc. Once the seats are installed then the steel canopy can be constructed (75 days) followed by the installation of the lights (30 days). The retractable roof represents the most significant technical challenge to the project. Building the roof track supports (90 days) can begin after the lower concrete bowl is constructed. At this time the dimensions of the roof can be finalized and the construction of the roof at a separate site can begin (180 days). After the roof supports are completed then the roof tracks can be installed (90 days). Once the tracks and the roof are completed then the roof can be installed and made operational (90 days). Once all activities are completed it will take 20 days to inspect the stadium. For purposes of this case assume the following: https://jigsaw.vitalsource.com/books/1259766608/epub/OEBPS/16 chapter06.xhtml 11/20/2017 Week 8 — BUS375075VA016-1178-001 Page 1 of 1 This assignment consists of two (2) parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the assignment it is written for. Part A: Project Schedule (Submit as one [1] Microsoft Project file) 1. Create a multi-level work breakdown structure (WBS) and detailed project schedule, using the information from the "Greendale Stadium Case" located at the end of Chapter 6, and incorporating the following constraints. Note: When you create your MS Project schedule, you will need to update your project per the following constraints: • The project must consist of at least twenty (20) tasks. • Each task must have a start and finish date that matches the duration noted in the assignment. • Each task must be assigned to a resource (e.g., Demolishing Crew; Construction Crew; Landscaping Crew). • Assume that the crew works during normal weekdays (no weekend work) under normal conditions (8 hours per day). In terms of holidays, you can assume no work will be done the following days: New Year's Day, President's Day, Good Friday, Good Monday, Friday before Memorial Day, Memorial Day, the business day before Independence Day, Independence Day, the Friday before Labor Day, Labor Day, the day before Thanksgiving Day, Thanksgiving Day, Black Friday (day after Thanksgiving), the business day before Christmas, Christmas Day, the business day after Christmas Day, and New Year's Eve. Part B: Written Response (Submit as a Microsoft Word file) 1. Respond to the following questions in a one to two (1-2) page paper based on your project schedule. • When will the project be completed? What is the critical path for the project? • How much slack / float is in your project? What activities have the greatest slack / float? • Identify the top three (3) activities that you believe could impact the project completion date. • What additional activities you would add to this project to make it more complete, from a project management viewpoint? 2. Format your assignment according to the following formatting requirements: • Typed, double spaced, using Times New Roman font (size 12), with one-inch margins on all sides. • Include a cover page containing the title of the assignment, the student's name, the professor's name, the course title, and the date. The cover page is not included in the required page length littp s ://blackboard. strayer. edu/webapps/blackboard/content/listC ontent.j sp?course_id= 2... 11/20/2017
User generated content is uploaded by users for the purposes of learning and should be used following Studypool's honor code & terms of service.

This question has not been answered.

Create a free account to get help with this and any other question!

Similar Content

Related Tags

Brown University





1271 Tutors

California Institute of Technology




2131 Tutors

Carnegie Mellon University




982 Tutors

Columbia University





1256 Tutors

Dartmouth University





2113 Tutors

Emory University





2279 Tutors

Harvard University





599 Tutors

Massachusetts Institute of Technology



2319 Tutors

New York University





1645 Tutors

Notre Dam University





1911 Tutors

Oklahoma University





2122 Tutors

Pennsylvania State University





932 Tutors

Princeton University





1211 Tutors

Stanford University





983 Tutors

University of California





1282 Tutors

Oxford University





123 Tutors

Yale University





2325 Tutors