Of the three problems below, choose and solve one problem. Show your work. Along with your answer, define each term and explain the significance (meaning) of the solution.
1. During a project, Earned Value Analysis is performed and gives the following numbers:
EV: 523,000; PV: 623,000; AC: 643,000.
Which results are correct?
A. CV: +120,000; SV: +100,000
B. CV: +100,000; SV: +120,000
C. CV: -100,000; SV: -120,000
D. CV: -120,000; SV: -100,000
2. You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0
A. The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B. The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
C. The project's deliverables have all been finished. The project came in on schedule but over budget.
3.You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000; BAC is 500,000.
What is right?
A. EAC = 550,000
B. EAC = 525,000
C. EAC = 500,000
D. EAC = 425,000
Explanation & Answer
Hey buddy, I...
Review
Review
24/7 Homework Help
Stuck on a homework question? Our verified tutors can answer all questions, from basic math to advanced rocket science!
Similar Content
Related Tags
The Turn of the Screw
by Henry James
A Farewell To Arms
by Ernest Hemingway
Frankenstein
by Mary Shelley
Their Eyes Were Watching God
by Zora Neale Hurston
The Prince
by Niccolò Machiavelli
Broke Millennial: Stop Scraping by and Get Your Financial Life Together
by Erin Lowry
Salt To The Sea
by Ruta Sepetys
The Catcher in the Rye
by J. D. Salinger
The Glass Castle
by Jeannette Walls